中圖分類號(hào):TU472 文獻(xiàn)標(biāo)志碼:B 文章編號(hào):1004-4345(2025)03-0035-06
Abstract Taking a large smelter project as an example,a comprehensive treatment strategy is proposed for a 113hm2 treatment areainphases,levelsandregions.Firstly,thearea-widepre-treatmentshouldbeimplementedbyusingvacuumpre-loadingmethod (de-wateringdynamiccompactionmethodadopted inlocalareas).Then,thecompositefoundationmethodwithbondingstrength reinforcementisusedforsecondaryreinforcementforkeyareassuchasslagstockyardandconcentratestockyard.Thestudyresults showthatthecharacteristicvalueofthefoundationbearingcapacityaftertreatmentisincreasedto2OkPatheaverageconsolidation of the soft soil reinforcement zone is greater than 80% ,and the cumulative settlement after construction is controlled within 30 cm, whichisbeterthanthestandardlimitTeefectivenessofthisstrategyinacceleratingsoildrainageconsolidation,educingpile foundationnegativefritionresistance,andcontrolingfoundationdeformationhasbeeverifiedthroughmonitoringandinspectionof the foundation treatment effect by a third-party agency.
Keywordssoft foundation;foundation treatment;vacuum preloading;dynamiccompaction;consolidationcontrol;layered settlement monitoring
軟弱地基的主要特點(diǎn)包括承載力低、壓縮性高等,這使得其在物理力學(xué)性能上具有復(fù)雜性。對(duì)存在軟弱地基場(chǎng)地的工程,軟弱地基處理方案,對(duì)工程的質(zhì)量、成本及進(jìn)度控制,都起到了關(guān)鍵性的作用。本文通過(guò)對(duì)實(shí)際工程軟弱地基處理方案進(jìn)行設(shè)計(jì)分析,為軟弱地基處理工程綜合解決方案提供了參考。本文方案采用了分層次、分區(qū)域進(jìn)行地基處理,消除了地基沉降帶來(lái)的不可預(yù)見(jiàn)的安全隱患和不可控制的投產(chǎn)后維修費(fèi)用,也降低了地基處理投資。
1工程概況
本項(xiàng)目為新建大型冶煉廠項(xiàng)目,總規(guī)劃用地面積約113萬(wàn) m2 處理面積共約113萬(wàn) m2 ,具體分區(qū)詳見(jiàn)圖1。預(yù)處理后,設(shè)計(jì)標(biāo)高為 +6.50m 。項(xiàng)目總工期 150d ,分階段實(shí)施:場(chǎng)地平整 15d ,排水板施工30\~45d,真空預(yù)壓 105~90d 。地基預(yù)處理目標(biāo)為[2]:第1次地基處理處理后地基承載力特征值達(dá)120kPa ,工后累計(jì)沉降量 ?30cm ,軟土加固深度范圍內(nèi)平均固結(jié)度 ≥80% ;第2次地基處理處理后地基承載力特征值達(dá) 200kPa ,工后累計(jì)沉降量 ?30cm ,軟土加固深度范圍內(nèi)平均固結(jié)度 90% 。
2 場(chǎng)地地質(zhì)條件
2.1地形地貌
擬建場(chǎng)地單元屬于漫灘沉積地層,地形平坦,地勢(shì)起伏較小,地層分布均勻?,F(xiàn)狀地面標(biāo)高 4.6~6.5m 。
2.2巖土體工程地質(zhì)層的劃分和評(píng)述
項(xiàng)目場(chǎng)地地質(zhì)層分布與特征指標(biāo)見(jiàn)表1,土的物理力學(xué)性質(zhì)、壓縮性指標(biāo)見(jiàn)表2。地基土承載力特征值綜合確定結(jié)果見(jiàn)表3。
本項(xiàng)目場(chǎng)地勘探深度范圍內(nèi)的主要含水層為表層填土及以下土層。擬建場(chǎng)地屬濕潤(rùn)區(qū),含水層中的可溶性鹽一般已溶于水中,地下水的腐蝕性能反映含土層的腐蝕性(詳見(jiàn)表4\~6)。故地基土腐蝕性同地下水腐蝕性是一致的。
根據(jù)水質(zhì)資料及依據(jù)《巖土工程勘察規(guī)范》(GB50021—2001)(2009版)綜合判別,該場(chǎng)地環(huán)境類型為Ⅱ類,淺部受地下水位升降而呈干濕交替作用,場(chǎng)地地下水對(duì)混凝土結(jié)構(gòu)具微腐蝕,對(duì)鋼筋混凝土結(jié)構(gòu)中鋼筋具微腐蝕。
根據(jù)場(chǎng)地含水層埋藏、賦存條件、分布、水理性質(zhì)和水力特征,場(chǎng)地勘探深度范圍內(nèi)地下水埋藏類型主要為淺層潛水,主要賦存于第 ① 層松散狀態(tài)填土及下部含水層中(具體參數(shù)詳見(jiàn)表2)。這表明該場(chǎng)地地下水上下貫通,水量較多。地下水的主要補(bǔ)給源為大氣降水和側(cè)向補(bǔ)給,主要排泄途徑為自然蒸發(fā)和地表徑流。在勘察期間鉆孔中觀測(cè)到,地下水位埋深為 0.80~1.40m ,地下水高程為 5.76~5.86m 。場(chǎng)地地下水水位受季節(jié)性影響較大,地下水年變化幅度約 1.5m 。
3深層軟土層存在引發(fā)的典型問(wèn)題
在深厚軟土地基上建設(shè)大型冶煉廠時(shí),由于大荷載的建(構(gòu))筑物較多,工廠建設(shè)對(duì)地面變形的要求較為嚴(yán)格,在建設(shè)和運(yùn)行過(guò)程中主要面臨以下三類巖土工程問(wèn)題。
1)次固結(jié)沉降影響。軟土屬典型的欠固結(jié)土體,在其自重應(yīng)力作用下會(huì)緩慢產(chǎn)生次固結(jié)沉降,并發(fā)生變形,導(dǎo)致建(構(gòu))筑物傾斜失穩(wěn)、基礎(chǔ)開(kāi)裂與脫空、廠房?jī)?nèi)外地坪開(kāi)裂并危及管線安全。一些對(duì)沉降敏感的車間生產(chǎn)線,會(huì)直接影響到產(chǎn)品質(zhì)量,工廠需投入高額維護(hù)資金進(jìn)行長(zhǎng)期治理。如某鋼廠精煉廠車間因沉降不均勻?qū)е碌孛婧蛪w開(kāi)裂、生產(chǎn)線輥道扭曲及桁車軌道變形,最終被迫停產(chǎn)將廠房和生產(chǎn)線拆除重建(如圖2)。
2)深厚淤泥層沉降對(duì)樁基產(chǎn)生雙重不利影響。(1)對(duì)樁基礎(chǔ)產(chǎn)生的負(fù)摩擦阻力增大,導(dǎo)致樁基費(fèi)用增加。(2)淤泥特有的流變性、觸變性,導(dǎo)致樁基施工時(shí),PHC管樁沉樁過(guò)程出現(xiàn)傾斜、偏移,鉆孔灌注樁樁孔縮徑,嚴(yán)重影響成樁質(zhì)量。特別對(duì)于含地下室的工程,基坑開(kāi)挖后再補(bǔ)樁面臨空間限制和技術(shù)風(fēng)險(xiǎn)。如圖3所示。某典型案例顯示,項(xiàng)目在未實(shí)施地基預(yù)處理的條件下,基坑(深 2.7~3.7m )開(kāi)挖引發(fā)坑壁垮塌,PHC管樁群出現(xiàn)大面積傾斜或斷樁率,如圖4所示。
3)軟土抗剪強(qiáng)度非常低,極易產(chǎn)生邊坡失穩(wěn)。當(dāng)?shù)孛嬗卸演d時(shí),堆載區(qū)域易產(chǎn)生地基整體失穩(wěn),威脅廠房等建筑物安全,甚至造成工廠停產(chǎn),經(jīng)濟(jì)損失巨大,如圖5。
4軟弱地基處理設(shè)計(jì)方案
根據(jù)處理目標(biāo),本項(xiàng)目擬分兩次進(jìn)行地基處理方案設(shè)計(jì);首先實(shí)施全場(chǎng)域預(yù)處理,采用真空預(yù)壓法(局部結(jié)合降水強(qiáng)夯法);隨后針對(duì)渣堆場(chǎng)、精礦堆場(chǎng)等部分重點(diǎn)區(qū)域進(jìn)行二次加固處理
4.1地基預(yù)處理
經(jīng)驗(yàn)表明,對(duì)深厚軟土地基進(jìn)行預(yù)處理,能在一定程度上解決地基原本存在的一些問(wèn)題,例如:事先消除 80% 以上的地面沉降,確保道路、管網(wǎng)、室內(nèi)外地坪安全運(yùn)行;基本消除樁身負(fù)摩阻,使樁體不易偏斜,降低樁基工程造價(jià);加大基坑側(cè)壁土層穩(wěn)定性,淺基坑可采用坡率法施工,節(jié)省基坑工程造價(jià);降低精礦堆場(chǎng)、強(qiáng)酸性區(qū)地坪二次處理造價(jià);對(duì)輕型建(構(gòu))筑物、堆載不大的堆場(chǎng),預(yù)處理后可直接采用天然地基。也有一些問(wèn)題,指用于改善支撐建筑物的地基(土或巖石)的承載能力或改善其變形性質(zhì)或滲透性質(zhì)而采取的工程技術(shù)措施。
4.2第1次地基處理方案
地基處理做法為對(duì)上部填土及軟土厚度區(qū)域采用塑料排水板 + 真空預(yù)壓,預(yù)壓完成后進(jìn)行表層填土并進(jìn)行低能級(jí)滿夯;對(duì)于上部填土及軟土厚度小于 7.0m 區(qū)域,采用降水 + 強(qiáng)夯的復(fù)合處理工藝;地基處理完成后,場(chǎng)地最終標(biāo)高為 6.5m (具體根據(jù)總圖標(biāo)高確定)。
4.2.1處理范圍與目標(biāo)
處理后地基承載力特征值達(dá) 120kPa ,軟土加固深度范圍內(nèi)平均固結(jié)度 ≥80% 。
4.2.2真空預(yù)壓設(shè)計(jì)方案(處理軟土厚度大于 7.0m )
1)真空度控制。本次膜內(nèi)真空度要求 ≥80kPa ;真空泵配置單機(jī)功率 ?55kW ,單個(gè)分區(qū)面積約 4~7hm2 O
2)排水網(wǎng)絡(luò)設(shè)置。豎向排水體采用塑料排水板(不低于B型板),間距不大于 1.2m ,插入深度達(dá)到粉砂層上部 1m 。橫向排水次排水管( ?α25mm 通過(guò)手型板連接,間距約 5m ;主排水管( Δ?50mm 通過(guò)三通/四通與次排水管連接,間距約 30m 。
4.2.3黏土封隔墻設(shè)計(jì)
考慮到場(chǎng)地處理范圍內(nèi)存在高滲透性砂性土,其孔隙連通性易導(dǎo)致地下水滲流及氣體逸散,影響真空預(yù)壓系統(tǒng)的密閉性。因此,需設(shè)置低滲透性的黏土封隔墻阻隔地下水與氣體的流動(dòng)通道,確保真空度。黏土封隔墻結(jié)構(gòu)參數(shù)如下:墻體厚 1.2m (雙排樁徑 0.7m ,搭接 0.2m );深度約為 13m ,設(shè) 1m 虛孔;材料采用黏土粉造漿。
4.2.4堆載設(shè)計(jì)
真空荷載約 80kPa ,為了防止膜結(jié)構(gòu)壓縮或破損需在膜上尚需加載約 10kPa ,考慮到真空度損失及工期約束,本次堆載設(shè)計(jì)采用輕微超載,上覆約1.0m 深水體,總預(yù)壓荷載約 90kPa 。
4.2.5沉降與固結(jié)度計(jì)算
1)計(jì)算模型。依據(jù)《建筑地基處理技術(shù)規(guī)范》(規(guī) 范編號(hào))經(jīng)典堆載預(yù)壓法公式進(jìn)行計(jì)算,將真空荷載 轉(zhuǎn)換為當(dāng)量厚度的堆載土方。
2)沉降修正系數(shù)。按《真空預(yù)壓加固軟土地基技術(shù)規(guī)程》(JTS147-2—2009),在純真空預(yù)壓條件下,地基的最終沉降修正系數(shù)取1.0\~1.3。
3)沉降與固結(jié)度計(jì)算結(jié)果。結(jié)合固結(jié)度、沉降計(jì)算及類似工程經(jīng)驗(yàn),根據(jù)欠固結(jié)土/固結(jié)土沉降計(jì)算公式或Gibson地基沉降計(jì)算理論(有限非線性應(yīng)變固結(jié)理論),計(jì)算各鉆孔沉降量,并繪制沉降等高線圖。塑料排水板在施工過(guò)程中應(yīng)減少對(duì)淤泥質(zhì)土層的擾動(dòng),確保抽真空時(shí)長(zhǎng)滿足固結(jié)要求。
4.2.6降水強(qiáng)夯設(shè)計(jì)方案(處理軟土厚度 lt;7.0m )
1)降水系統(tǒng)設(shè)計(jì)。采用真空降水法,真空降水井間距 3~4m ,井深長(zhǎng)短組合( 7.0m 與 3.0m ;場(chǎng)地平整后,進(jìn)行3輪強(qiáng)夯,每輪強(qiáng)夯前在真空降水井內(nèi)抽水?dāng)?shù)天,使其達(dá)到要求。一般而言,第1遍強(qiáng)夯前抽水 7~10d ,第2遍強(qiáng)夯前抽水8\~12d,第3遍強(qiáng)夯前抽水 5~7d 。降水井示意見(jiàn)圖6。
2)強(qiáng)夯設(shè)計(jì)。第1遍夯擊采用 1000~1500kN?m 單點(diǎn)夯擊3\~4次,夯點(diǎn)間距 3~4m 。第2遍夯擊采用 1500~3000kN?m ,單點(diǎn)夯擊5\~7次,夯點(diǎn)間距3~4m 。拔出中間井點(diǎn)管,進(jìn)行第3遍夯擊,采用1000kN?m ,單點(diǎn)夯擊2\~3次,滿夯搭接 1/3D 。具體參數(shù)可根據(jù)勘察報(bào)告進(jìn)行調(diào)整。夯點(diǎn)示意見(jiàn)圖7。
3)含水率、水位、真空度控制。含水率控制一般是在3次強(qiáng)夯前對(duì)土層(地表下 2m 處)取樣進(jìn)行含水率檢測(cè)。第1遍強(qiáng)夯前砂性土含水率約 30% (砂性土含水率稍大,黏性土含水率偏小)第2遍、第3遍的含水率分別控制在 28%25% 以下。水位控制的方式是在降水區(qū)域內(nèi)埋設(shè)水位觀測(cè)孔。一般情況下,每1000m2 埋設(shè)1個(gè)觀測(cè)孔,每天進(jìn)行觀測(cè)、記錄,待水位低于地表 2m 才能強(qiáng)夯。為了控制抽水和停泵時(shí)間,在抽水泵和水氣分離器之間安裝真空表觀測(cè)真空度。觀測(cè)結(jié)果表明,開(kāi)始抽水時(shí)真空度 ?70 kPa ,隨著時(shí)間延長(zhǎng)水位下降,真空度逐漸降低;當(dāng)真空度 lt;20kPa 時(shí),地下水很難再抽上來(lái),此時(shí)管內(nèi)一般只能抽氣。抽氣時(shí)間超過(guò) 2h ,該泵暫停抽水。停泵超過(guò) 2h 后,再次啟動(dòng)抽水,直至完成強(qiáng)夯施工。強(qiáng)夯過(guò)程中,井點(diǎn)管一直要進(jìn)行高真空排水,所以不需要拔出。強(qiáng)夯施工結(jié)束3d后方可拆除外圍井點(diǎn)。
4)效果檢測(cè)。檢測(cè)項(xiàng)目包括孔隙水壓力、地下水位、沉降量、靜力觸探及地基土靜載試驗(yàn)等。為使設(shè)計(jì)參數(shù)達(dá)到最優(yōu)、加固效果達(dá)到最佳,綜合考慮工期因素,正式施工前應(yīng)在場(chǎng)地內(nèi)選有代表性的區(qū)域進(jìn)行試夯先導(dǎo)試驗(yàn)。
4.3第2次地基處理方案
根據(jù)建構(gòu)筑物的特性和重要等級(jí)進(jìn)行針對(duì)性的處理,擬采用有黏結(jié)強(qiáng)度增強(qiáng)體復(fù)合地基或強(qiáng)夯置換夯實(shí)地基法。針對(duì)用地規(guī)劃較明確、地質(zhì)情況清楚、且地基承載力特征值不超過(guò) 200kPa ,建構(gòu)筑物沉降敏感性一般的區(qū)域可考慮將一、二次地基處理合并完成,即一步處理到位。
4.3.1處理范圍與目標(biāo)
處理后地基承載力特征值達(dá) 200kPa ,工后累計(jì)沉降量 ?30cm ,軟土加固深度范圍內(nèi)平均固結(jié)度 ? 90% 。
4.3.2強(qiáng)夯置換法[5]
根據(jù)處理后復(fù)合地基地基承載力 200kPa 的要求,置換墩承載力暫定 450kPa 的要求,本工程擬采用強(qiáng)夯置換法。強(qiáng)夯置換夯坑填塊石置換方法,塊石粒徑 gt;300mm 的含量不應(yīng) gt;30% ,最大粒徑不應(yīng) gt;800 mm ,不宜采用不適宜用砂、礫、山皮土等作為置換料,強(qiáng)夯置換要求水位降至起夯點(diǎn)以下 2m ,置換后再進(jìn)行一遍滿夯的施工,強(qiáng)務(wù)置換初設(shè)參數(shù):采用正方形布點(diǎn),間距 2.0~ 3.5m ,置換深度: gt;7m ;夯錘重: gt;20t ,夯錘直徑: 1.0~ 1.2m ,落距: gt;15.0m ,單擊夯擊能為 :3000~5000kN?m :平均墩體直徑: 1.1~1.4m ,滿夯夯擊能: 1000kN?m 。強(qiáng)夯置換工藝施工順序,如圖8所示,
5 地基土監(jiān)測(cè)與檢驗(yàn)
地基處理效果由第三方機(jī)構(gòu)檢測(cè)與監(jiān)測(cè),相關(guān)檢測(cè)與監(jiān)測(cè)內(nèi)容如下
5.1現(xiàn)場(chǎng)監(jiān)測(cè)
現(xiàn)場(chǎng)監(jiān)測(cè)包括地表沉降、分層沉降、孔隙水壓力、水平位移(測(cè)斜)地下水位、膜下真空度等內(nèi)容。
1)地表沉降。每道工序前進(jìn)行高程測(cè)量或淺層沉降板觀測(cè)
2)分層沉降(可選)。以前述垂直位移監(jiān)測(cè)基準(zhǔn)點(diǎn)作為基準(zhǔn),每 3m 設(shè)置1個(gè)分層沉降磁環(huán),采用國(guó)產(chǎn)電磁式分層沉降儀測(cè)量塑料測(cè)管孔口的高程以及孔口各磁環(huán)之間的距離,據(jù)此計(jì)算各磁環(huán)位置的實(shí)際標(biāo)高及沉降量。為減少測(cè)量誤差,每一磁環(huán)應(yīng)重復(fù)測(cè)量3次,測(cè)量結(jié)果取3次測(cè)量的平均值。
3)土體深層水平位移觀測(cè)(測(cè)斜)。采用國(guó)產(chǎn)測(cè)斜儀監(jiān)測(cè)處理區(qū)周邊土體位移,測(cè)斜主要沿處理區(qū)域周邊布置。測(cè)量自孔底開(kāi)始,自下而上沿導(dǎo)槽全長(zhǎng)每隔一定距離(通常間隔為 0.5m 測(cè)讀1次。通常,測(cè)斜儀可以同時(shí)測(cè)量相互垂直兩個(gè)方向的水平位移。每次測(cè)量時(shí),應(yīng)將測(cè)頭穩(wěn)定在某一位置上。測(cè)量完畢后,將測(cè)頭旋轉(zhuǎn) 180° 插入同一對(duì)導(dǎo)槽,重復(fù)再測(cè)量1次。兩次測(cè)量的點(diǎn)應(yīng)在同一位置,確保兩次讀數(shù)數(shù)值接近(絕對(duì)值不超過(guò)20)符號(hào)相反。如果測(cè)量數(shù)據(jù)有疑問(wèn),應(yīng)及時(shí)補(bǔ)測(cè)
4)孔隙水壓力監(jiān)測(cè)(可選)。夯點(diǎn)間布設(shè)監(jiān)測(cè)孔,根據(jù)淤泥層厚度確定傳感器埋設(shè)個(gè)數(shù)(每 2~4m 埋設(shè)1個(gè)),監(jiān)測(cè)強(qiáng)夯過(guò)程中和強(qiáng)夯后超靜孔隙水壓力增長(zhǎng)和消散。觀測(cè)頻率為:強(qiáng)夯過(guò)程中連續(xù)監(jiān)測(cè),抓獲孔隙壓力峰值,一般每天3次;停夯時(shí)每天測(cè)1次;特殊情況加密觀測(cè)。
5)地下水位監(jiān)測(cè)(可選)。在距孔隙水監(jiān)測(cè)孔2m 內(nèi)設(shè)地下水觀測(cè)孔1個(gè),監(jiān)測(cè)強(qiáng)夯過(guò)程中和強(qiáng)夯后地下水位的變化規(guī)律,同時(shí)結(jié)合孔隙水壓力監(jiān)測(cè)結(jié)果計(jì)算超孔隙水,判定其變化規(guī)律。(6)真空度測(cè)量。采用壓力真空表進(jìn)行監(jiān)測(cè),根據(jù)膜下真空壓力的變化規(guī)律,驗(yàn)證地基處理區(qū)密封的效果。每個(gè)處理區(qū)布設(shè)3\~5個(gè)監(jiān)測(cè)點(diǎn),驗(yàn)證密封效果。
5.2現(xiàn)場(chǎng)檢測(cè)
現(xiàn)場(chǎng)檢測(cè)內(nèi)容包括十字板試驗(yàn)或靜力觸探試驗(yàn)、鉆孔取土試驗(yàn)、淺層載荷板試驗(yàn)等。
1)十字板剪切試驗(yàn)(可選)。檢測(cè)在夯前和地基變形穩(wěn)定后進(jìn)行,檢測(cè)點(diǎn)設(shè)置在孔隙水監(jiān)測(cè)孔附近軟土層中,每隔 1m 試驗(yàn)1次。測(cè)定原狀土和重塑土的強(qiáng)度。
2)靜力觸探。檢測(cè)在夯前和地基變形穩(wěn)定后進(jìn)行,檢測(cè)點(diǎn)設(shè)置在孔隙水監(jiān)測(cè)孔附近,主要測(cè)定錐尖阻力與側(cè)壁摩阻力的變化規(guī)律。
3)土工試驗(yàn)。土工試驗(yàn)在地基處理前后鉆孔取樣進(jìn)行,試驗(yàn)項(xiàng)目包括天然含水率、天然重度、相對(duì)密度、孔隙比、飽和度、液限、塑限、塑性指數(shù)、液性指數(shù)、抗剪強(qiáng)度(直快、UU)、壓縮系數(shù)、無(wú)側(cè)限抗壓強(qiáng)度等。
4)載荷試驗(yàn)。淺層平板( 1.0m×1.0m 載荷試驗(yàn),超過(guò) 1hm2 的每個(gè)區(qū)設(shè)1\~2個(gè)點(diǎn)。
6結(jié)論
本文針對(duì)新建大型冶煉廠項(xiàng)目用地填土 + 淤泥質(zhì)土的復(fù)合地層特點(diǎn),采用分階段、分層次、分區(qū)域的綜合處理策略,通過(guò)真空預(yù)壓與強(qiáng)夯協(xié)同處理,使地基承載力提升至 120kPa ,工后沉降量 ?30cm 。預(yù)處理階段,采用塑料排水板 + 真空預(yù)壓的方式,輔以黏土封隔墻,有效阻隔了砂性土的水力遷移通道,使真空預(yù)壓系統(tǒng)密閉效率大幅提升。二次處理階段,采用增強(qiáng)體復(fù)合地基法,使地基承載力提升至不小于200kPa ,工后沉降量 ?30cm 。經(jīng)第三方機(jī)構(gòu)監(jiān)測(cè)與檢測(cè),驗(yàn)證了該方案在加速土體排水固結(jié)、降低樁基負(fù)摩阻力及控制地基變形方面的有效性。本項(xiàng)目工程地基處理技術(shù)方案,既滿足業(yè)主要求的質(zhì)量可控、進(jìn)度最快、投資經(jīng)濟(jì)的目標(biāo),又使軟弱地基得到了系統(tǒng)性加固與長(zhǎng)效穩(wěn)定的處理。復(fù)合工藝的深度整合代表了軟弱地基處理的前沿方向。傳統(tǒng)的技術(shù)組合往往停留在簡(jiǎn)單疊加階段,而新一代時(shí)序優(yōu)化型復(fù)合工藝通過(guò)精確控制各技術(shù)單元的介入時(shí)機(jī)和作用強(qiáng)度,實(shí)現(xiàn)了‘ 1+1gt;2 ”的協(xié)同效應(yīng)。
參考文獻(xiàn)
[1]中華人民共和國(guó)住房和城鄉(xiāng)建設(shè)部.建筑地基基礎(chǔ)設(shè)計(jì)規(guī)范:GB50007—2011[S].北京:中國(guó)建筑工業(yè)出版社,2011.
[2]中華人民共和國(guó)住房和城鄉(xiāng)建設(shè)部.建筑與市政地基基礎(chǔ)通用規(guī)范:GB55003—2021[S].北京:中國(guó)建筑工業(yè)出版社,2021.
[3]中華人民共和國(guó)住房和城鄉(xiāng)建設(shè)部.建筑地基處理技術(shù)規(guī)范:JGJ79—2012[S].北京:中國(guó)建筑工業(yè)出版社,2012.
[4]中華人民共和國(guó)住房和城鄉(xiāng)建設(shè)部.建筑地基基礎(chǔ)工程施工質(zhì)量驗(yàn)收標(biāo)準(zhǔn):GB50202—2018[S].北京:中國(guó)建筑工業(yè)出版社,2018.
[5]中華人民共和國(guó)工業(yè)和信息化部.強(qiáng)夯地基技術(shù)規(guī)程:YS/T5209—2018[S].北京:中國(guó)計(jì)劃出版社,2018.