• <tr id="yyy80"></tr>
  • <sup id="yyy80"></sup>
  • <tfoot id="yyy80"><noscript id="yyy80"></noscript></tfoot>
  • 99热精品在线国产_美女午夜性视频免费_国产精品国产高清国产av_av欧美777_自拍偷自拍亚洲精品老妇_亚洲熟女精品中文字幕_www日本黄色视频网_国产精品野战在线观看 ?

    Safety of small and medium dams in permafrost regions

    2014-12-15 05:55:34RudolfZhangSergeyVelikin
    Sciences in Cold and Arid Regions 2014年4期

    Rudolf V.Zhang ,Sergey A.Velikin

    1.Melnikov Permafrost Institute,Siberian Branch of the Russian Academy of Sciences,Yakutsk 677010,Russia

    2.Vilyui Permafrost Research Station,Melnikov Permafrost Institute,Siberian Branch of the Russian Academy of Sciences,Chernyshevsky 678185,Russia

    1 Introduction

    Safe operation and performance of dams is one of the key issues in permafrost regions.Intensive geocryological processes (thermokarst,thermal erosion,frost heaving,suffosion,concentrated seepage along the voids left by melt ice and others) begin to develop at the early stages of construction.These processes are hazardous both in the upstream and the downstream areas.It should be noted that large Class I–II dams,50 m or more in height (primarily for hydropower production) have a lower catastrophic failure rate compared to medium (20 to 50 m in height)and small (20 m or lower) Class III and IV dams (At its 2000 meeting,the International Commission on Large Dams (ICOLD) has defined large dams as dams with a height of 15 m or more from the foundation,or dams between 5–15 m high with a reservoir volume of more than 3 million cubic meters).ICOLD statistics show that the failure rate for small embankment dams accounts for approximately 36% or higher of all dam failures.In Russia,half of the Class III and IV dams,90% of which are under the jurisdiction of the Federal Ministry of Natural Resources and Environment,are identified as unsafe (Zoteevet al.,2003).Dam failures can have disastrous consequences for populations and property in the downstream areas,especially where development occurs in the low floodplains in violation of all existing building norms and regulations.

    In permafrost regions,the percentage of dam failures is higher due to the unique environmental and geotechnical conditions,as well as due to global climate change observed since the mid-twentieth century.In Central Yakutia,for example,about 90% of small embankment dams built for land reclamation fail within the first few years of operation (Zhang,1969).Over 40% of medium dams for domestic and industrial water supply are subject to failures,about 50% of which occur in the first 3 years of operation and 31%–35% occur between the third and fifth years(Pridorogin,1979).

    At present,the surviving dams are 40–45 years old and they are reaching their design life limit.It is appropriate to mention here that not a single water project has been completed in Russia over the last half a century.The only projects currently under construction are the Boguchany and Bureya hydroelectric power stations initiated in 1974–1978 and to be completed in 2014,as well as the Svetlinskaya and Ust-Srednekanskaya hydroelectric power stations to be completed in 2016.In this context,rehabilitation becomes important to prolong the useful life of the dams that are adequately operating.This fact should be taken into account in dam safety declaration.It is known that ageing and degradation of the hydraulic structure as a whole and its materials begin from the moment of placement of the material (Mirtskhulava,2008).These processes are even more intensive in harsh permafrost environments due to the large thermal and moisture gradients and the resulting complex thermal stress-strain state in the structures(Grechishchev and Sheshin,1973;Zhang,2002).

    2 Dam safety terms and definitions

    The safety of dams and other hydraulic structures(HS) in Russia is regulated by the Federal Law of the Russian Federation of 21.07.97 No.117,On the Safety of Hydraulic Structures (State Duma of the Russian Federation,1997).This Law uses the following basic notions:

    1) "operator of a hydraulic structure" is a public owned or municipal unitary enterprise or entity of any other organizational or legal form,on whose balance sheet the hydraulic structure is recorded;

    2) "owner of a hydraulic structure" is the Russian Federation,federal unit,municipality,legal entity irrespective of its organizational or legal form,or a natural person,having the rights of ownership,usage and disposal of a hydraulic structure;

    3) "area of a hydraulic structure" means a tract of land and/or water within the boundaries established according to existing land and water legislation;

    4) "emergency" means a condition developed by HS failure which have or may result in loss of lives,damage to public health or the environment,or significant economic and social losses;

    5) "safety of a hydraulic structure" refers to a HS quality to ensure the protection of the life,health and legitimate interests of persons,the environment,and property;

    6) "safety assessment of a hydraulic structure"means the evaluation of compliance of the condition of a hydraulic structure and of the qualifications of operator’s employees with the standards and rules approved in accordance with the procedure established by the Federal Law;

    7) "ensuring safety of a hydraulic structure" refers to the development and implementation of measures to prevent HS failure;

    8) "declaration of safety of a hydraulic structure"is a document which gives the grounds for HS safety and defines measures to ensure HS safety;

    9) "failure of a hydraulic structure" means HS failure or damage caused by unforeseen conditions(outside the design assumptions or safety rules) and accompanied by the uncontrolled release of impounded water or mine tailings;

    10) "failure risk level" is a HS safety characteristic which can be presented in the probabilistic form or in the form of a deterministic parameter (hydraulic-structure safety level) characterizing the deviation of HS performance or operating conditions from the requirements identified in the regulatory documents;

    11) "permissible failure risk level" is a HS failure risk value established by the normative documents;

    12) "controlled parameters" are quantitative parameters measured instrumentally or calculated from instrumented measurements,as well as qualitative parameters characterizing the condition of the hydraulic structure;

    13) "diagnostic parameters" are the most significant controlled parameters which are used to assess the safety of the dam-foundation-reservoir system as a whole or its elements.

    14) "safety criteria":

    ?K1 is the first (warning) level of diagnostic parameters,within which the stability and seepage strength of the dam and its foundation as well as the discharge capacity of outlet works and spillways are still in line with normal performance conditions;

    ?K2 is the second (threshold) level of diagnostic parameters,beyond which further operation of the hydraulic structure is inadmissible under design conditions.

    15) "performance condition of a hydraulic structure":This term has no definition in the Law.It recognizes three different performance conditions("normal condition","potentially unsafe condition","pre-failure condition") which are defined further.

    16) "normal condition" is the condition when the structure performs in accordance with the standards of practice and the design,and the diagnostic parameters do not exceed theK1 criterial values;

    17) "potentially unsafe condition" means the condition when the value of any diagnostic parameter has become higher (lower) than its first,warning level(K1)or has gone beyond the range of values predicted for a given load combination.The condition of the structure does not meet the standards,but it is not in immediate danger of breaching and may be operated for a limited time;

    18) "pre-failure condition" is the condition when the value of any diagnostic parameter has become higher (lower) than the second,threshold level (K2).Further operation of the structure is not allowed under design conditions without immediate measures taken to restore the required safety level and without special permission from the supervising agency.

    3 Procedure for determining the dam safety criteria

    To properly implement the Federal Law on the Safety of Hydraulic Structures,the Unified Energy System of Russia has developed a regulating document,RD 153-34.2-21.342-00,Methodology for Determining Safety Criteria for Hydraulic Structures (Unified Energy System of Russia,2001),as well as a guide to this regulation (Unified Energy System of Russia,2006).The regulating document applies to all agencies responsible for the development,approval,and employment of safety criteria for hydraulic structures of all classes with regard to projects in the power generation industry.It requires that criterial values for diagnostic parameters (safety criteria) should be established at two phases of a project:design phase and operation phase.Criterial values developed at the design phase should be corrected at the commissioning phase taking into account all the information obtained during construction,as well as possible extension of the scope of supervision.

    The performance condition and safety of the hydraulic structure are evaluated by comparing the measured (or calculated from measurements) quantitative and qualitative diagnostic parameters with the respective criterial valuesK1 andK2,as well as with the predicted range of diagnostic parameters.

    The criterial relationships have the following form:

    (a) the hydraulic structure is in a normal (good)condition,if

    (b) the structure is in a potentially unsafe condition,if

    (c) the structure is in a pre-failure condition,if

    whereFmeasis the measured or calculated value of the diagnostic parameter;K1 andK2 are the values which,if reached by any one diagnostic parameter,will indicate transition from one condition to another.

    Apart from comparing the measured (calculated)parameters with their criterial values,diagnostic control includes comparison of the measured diagnostic parameter with its predicted value.In other words,the diagnostic parameter should also be checked against the confidence interval predicted for actual loads acting at the time of checkup:

    whereFpredis the diagnostic parameter value predicted for actual loads and impacts by the deterministic or statistic model;δis the maximum permissible error of the prediction model.

    Both checkups,comparisons with criteria(1)–(3)and with criterion(4)changing with actual loads and impacts,are mandatory.They are necessary and sufficient conditions of safety.

    Determining safety criteria is a critical and difficult task in dam safety management.The existing procedures need to be continuously refined and improved depending on dam importance class.Some researchers (e.g.,Mirtskhulava,2008;Kayakin and Bobkov,2010) recommend introducing process development criteria (stability,destabilization,and extremality) for more objective assessment of dam safety,in addition to the existing two condition criteria.In other words,they call for a multi-factor dam–environment interaction system.As a rule,these multiple processes have a synergistic effect.

    Other researchers (e.g.,Shchedrin and Kosichenko,2011) advocate that safety declaration should be simplified to an expert safety review and the use of complicated performance criteriaK1 andK2 (justified for large dams for power generation) must be cancelled for Class III–IV dams.It should be noted that RD 153-34.2-21.342-00 (Unified Energy System of Russia,2001) eases up on Class IV hydraulic structures,and if properly justified,on Class III hydraulic structures,permitting the use of criterionK2 only.The existing Federal law on hydraulic structure safety applies to all types of hydraulic structures.Apparently,this is not very correct,because its application to Class IV dams entails additional,unnecessary costs.

    We would like to make a few remarks regarding the simplification of safety criteria assessment for medium and small dams with low storage capacity.The existing methodologies were developed for the safety analysis of large,primarily hydropower,projects.If applied to smaller water-retaining structures,they would lead to significant economic errors.For small and medium dams on permafrost,however,the following considerations must be kept in mind.

    In permafrost regions with their complicated engineering-geological conditions,medium dams for industrial and public water supply are facilities of increased importance,because they are integrated into the mining and power generation complexes of high economic and social value for the region.We,therefore,think that the level of safety requirements for this category of dams should not be lowered.As for land reclamation dams,we are inclined to support the arguments in favor of simplifying the safety assessment procedures:the existing methodologies have been developed based on experience with large projects which,applied to small dams,will lead to significant errors;no reliable procedures for hydrologic characterization (streamflow volume,runoff generation,maximum discharge estimates,etc.) have been developed as yet;there are no building codes or other regulations for this type of dams;inadequate permafrost information is collected during dam site investigations due to funding constraints leading to serious flaws in the design,construction and operation of dams;and the lack of qualified and competent monitoring personnel.Given these circumstances,there appear to be too many unknowns to undertake analyses with the existing safety assessment methodologies.A simplified procedure of expert safety review is therefore thought to be economically justified for small dams.

    4 Declaration of safety:discussion and a case study

    As mentioned above,the existing law on hydraulic structure safety requires that the owner or operator of the hydraulic structure must file a declaration of safety with the relevant authorities.This declaration must be developed for each hydraulic structure supervised by the Mining Safety Inspectorate (Gosgortechnadzor)and the Technical Inspectorate (Gostechnadzor) following the current standards,guidelines and manuals in force in Russia.

    The following case study is presented to illustrate the development of a dam safety declaration.

    4.1 Project description

    The Sytykan River Project in western Yakutia is a water scheme utilizing Sytykan River to meet the municipal,rural and industrial water needs for the town of Udachny,surrounding communities and diamond mines.This Class III project was commissioned in September 1976 (Biyanovet al.,1989;Aleshinet al.,2005).It is located within the zone of continuous permafrost.The permafrost at the project site ranges from 500 to 600 m in thickness.The depth of seasonal thaw varied from 0.7 to 3.5 m during the geotechnical investigation.The permafrost temperature varies from-7.2 °C to-5.3 °C.The permafrost is underlain by the highly mineralized Metiger-Ichera aquifer.A talik was present beneath the river bed extending to a depth of 17.0 m and to a width of 30.0 m.

    The Sytykan is a semi-mountain river.The valley at the project site is U-shaped and the floodplain ranges in width from 120 to 200 m.The channel is 18.0 m wide at low water time and 36 m at high water time,with water depth varying from 2.3 to 6.5 m respectively.The river bed downstream the dam has a weighted mean slope of 0.009.The catchment area is 880 km2.The mean annual flow is 195 million m3,while the mean flood flow is 122 million m3.The 100-year flood flow in the river is 158 million m3,while the 200-year flood flow is 246 million m3.The period of spring high flow occurs,on average,from May 25 to June 10.Most of the annual flow,from 70% in a normal year to 98% in a dry year,occurs in spring.During the winter months,the river has no flow.

    The bedrock in the dam and right abutment area consists,down to 50.8 m depth,of Lower Ordovician limestone with layers of marl.The limestone thickness varies from 10.0 to 40.8 m.The bedrock is overlain by 3.8 to 9.2 m of clayey silts with lenses of gravel to cobble-sized fragments of dolerite,limestone and marl.

    The subsurface investigation in 1995 (The Declaration of Safety of the Sytykan River Project,2006)showed the dam embankment and foundation materials were in thawed and frozen states.The thawed material was water saturated.Borings revealed its table to be at depths of 5.0 to 11.0 m extending down to depths of 7.6 to 17.2 m.The frozen materials had massive,reticulate or fractured cryostructures.Ice contents were up to 5%.Groundwater was encountered while drilling with the steady level at 311.1 to 313.3 m a.s.l..

    The Sytykan River Project consists of a reservoir,a retaining dam,a side channel spillway,a refrigeration system,and outlet works.Figure 1 shows a general view of the project.

    The reservoiris of mountain-valley type in topography.It has a full storage capacity of 34.1 million m3,and its active capacity is 27.72 million m3.

    The damis a rockfill dam with a central silty clay core and a frozen membrane.The crest is 650 m long and,after adding material on the upstream and downstream faces,is 16 to 76 m wide.The maximum embankment height is 23.2 m.The upstream and downstream slopes are 3H:1V and 2H:1V respectively.The dam slopes are protected by a layer of dolerite riprap.The frozen impervious barrier is maintained by two refrigeration systems:a cold air refrigerant system consisting of 431 freeze pipes and a liquid refrigerant system of 162 freeze pipes.The maximum embedment depth is 37 m for cold air pipes and 55 m for liquid refrigerant pipes.

    Two 500-mm-diameter steel pipes for seepage collection cross the dam at Sta.2+80 (temperature borehole #52).A siphon steel pipe 500 mm in diameter is located here to provide the release of water from the reservoir to the downstream area.Figure 2 shows the typical cross section of the dam.

    Figure 1 The Sytykan River Project,view from upstream,2006 (The Declaration of Safety of the Sytykan River Project,2006)

    Figure 2 The Sytykan dam,typical cross section

    The dam rehabilitation plan provides for the creation of a combined grouting and freezing system,which will be completed in several phases.

    The side channel spillwayis cut through bedrock in the right abutment of the dam and is used for channel diversion and emergency water release.The spillway is an open reinforced concrete trough with a trapezoidal cross section,changing to rectangular at the end.With the size of 10.0m×5.0m,length of 500 m and slope of 0.04,the spillway has a capacity of 293 m3/s.At its head portion,the spillway has a 3-m-high gallery with a 3-m-deep concrete cutoff.A cold air refrigerant system was installed from the gallery embedded to a depth of 7 m.Later,an additional refrigeration system was installed before the spillway crest,which consisted of 30 vertical freeze pipes embedded to a depth of 30 to 35 m.

    The outlet works located on the right bank of the Sytykan River 500 m downstream of the dam provide a municipal and industrial water supply to the town of Udachny.The outlet works consist of a pumping station,two steel pipelines 802 mm to 273 mm in diameter,each 7,408 m long,and a 6-m-diameter well in the center of the pumping plant partitioned into two sections.The sections are connected by an overflow pipe 800 mm in diameter during normal operation.

    4.2 Brief characterization of the performance of the Sytykan River Project facilities

    Figure 3 shows the location of temperature boreholes (red line).Figure 4 shows the combined geological and geothermal profile along the Sytykan dam.During the first thirteen years of operation (1976 to 1989),no serious stability problems with any structures were experienced on the Sytykan River Project.The first signs of ground warming in the dam embankment,foundation and abutments,as well as along the spillway channel were detected in 1990.This warming caused by refrigeration system failures in 1989 triggered the development of seepage,icings,thermal suffosion,frost cracking and sinking,and slope slides.

    Between 1995 and 1998 the thaw zone significantly increased both horizontally,extending 250 m into the left abutment,and vertically,deepening from 17.0 to 35.0 m.Seepage problems developed in and below the dam,especially near its right abutment,creating a serious risk of breach.A contingency plan was developed to prevent dam failure.

    In early December 1999,Aqua-Eco Co.divers inspected the reservoir between the dam and the intake structure.To reduce leakage from the reservoir,Aqua-Eco Co.placed geomembrane liners covering a total area of 9,700 m2near the intake and approach channel area.During the period from 2003 to 2006,a project was undertaken,designed by Geostroyproekt Co.,to create a frozen grouting curtain in the right dam abutment and the right reservoir slope.As a result of these measures,the upward expansion of the talik into the dam embankment was arrested,but the talik continued to move to the right bedrock bank as seen in figure 4.In addition,a clay blanket was laid on the upstream face to reduce the seepage.Rockfill consisting of dolerite was added on the upstream and downstream slopes which enhanced the freezing of the dam slopes and foundation,thereby improving the structural stability of the dam.Surveys of the slopes,berms,crest and abutments showed no movement or sliding.No seepage exits were observed on the downstream slope of the dam embankment.However,seepage below the spillway continued,resulting in no reduction in total seepage discharge.The foundation below the right dam abutment thawed to a depth of 40.0 m (to an elevation of 282.00 m),i.e.,21 m lower than the minimum reservoir-bottom elevation.Permafrost degradation was also observed beneath the spillway channel.New seepage areas appeared on the right bank about 1 km downstream of the damsite.

    Other structures and systems on the Sytykan River Project also suffered problems,requiring repair and modification.For example,the freezing system which is the key component in seepage and stability control was reconstructed several times.For better freezing of the ground,cold air and liquid refrigeration systems were used in a year-round operation mode.At present,the refrigeration systems,as well as the instrumentation system,are operating satisfactorily.

    The spillway channel allows the safe passage of 100-year flood flow,but the concrete wall of the chute requires repair.Significant efforts are being undertaken to control seepage beneath the spillway.

    The outlet works with the pumping station,as well as the pressure water pipelines are in a good condition and are able to fully perform their water-supply functions.

    A special monitoring program was developed for permafrost control at the Sytykan River Project.The analysis of temperature observations indicates that the thermal regime is very complicated and strongly variable.In some parts of the Project area the ground temperatures hold steadily below 0 °C preventing seepage through the dam and its foundation,while in others ground warming continues,calling for sophisticated seepage control measures.

    Figure 3 The Sytykan dam,location of temperature boreholes

    Figure 4 The Sytykan dam,the longitudinal profile showing geology and temperature distribution

    4.3 Safety declaration

    As shown above,the Sytykan River Project has had a recurrent history of seepage over its 38-year operation period.The operator has to take costly remedial measures to maintain the project’s function of supplying municipal and industrial water to the town.The declaration of safety is intended to promote effective monitoring of the performance of all critical components of the project.Six declarations have been developed for the Sytykan River Project and the seventh is now under development.The declaration contains all the information on the condition of the dam,reservoir and appurtenant structures and details the measures to ensure their safe performance.

    The first step in developing a safety declaration is identifying the subjects of monitoring and the diagnostic parameters.

    Based on the analysis of potential risks and operation conditions,the following subjects of monitoring have been identified for the monitoring program in accordance with the guidelines (Gosgortechnadzor of Russia,2001;Unified Energy System of Russia,2001):(a) structures and systems—the dam,including all its elements (foundation,embankment,core,frozen barrier,refrigeration system,instrumentation system);the reservoir;the side channel spillway;the siphon spillways;the pumping stations;and the water pipelines;(b) the environment;and (c) project documentation.

    The main measures used in evaluating the project safety are the safety criteria.The performance parameters to be monitored include qualitative and quantitative parameters for the dam,spillway,and reservoir,and qualitative parameters for the spillway,pumping stations,outlet works,instrumentation system,environment,project documentation,and operations and maintenance and monitoring programs.

    The qualitative parameters are determined by visual inspections and expert assessment,while the quantitative parameters are monitored instrumentally or calculated from measurements.The quantitative diagnostic parameters provide the best indicators of the condition of the hydraulic structure and its impact on the environment.Omitting the calculation procedures which are performed in accordance with the current regulations and guidelines (Gosgortechnadzor of Russia,1998,2001,2002a,b;Unified Energy System of Russia,2004,2006),we will list the parameters and their criterial and actual values for the structures and systems of the Sytykan River Project.

    1) List of quantitative and qualitative performance parameters

    Qualitative parameters:reservoir water level;normal freeboard;temperatures in the dam embankment and foundation;dam geometry;settlements in the dam embankment and foundation;seepage line in the unfrozen dam portion;seepage rate through the dam embankment;changes in total seepage through the dam embankment,foundation and abutment;changes in drainage discharge from the pumping stations;seepage gradient in the core of the dam unfrozen zone;spillway channel geometry;spillway crest elevation;liquid level in the liquid refrigerant system.

    Quantitative parameters:presence of established seepage pathways (seepage exits on the downstream face or in the tailwater);signs of seepage appearing as wet areas,icings in winter,puddles,muds,springs,boils,or streams;settlement or heaving on the dam crest;localized slides (slope failures);caverns and sinkholes in the embankment and foundation;cracking along the boundaries between the soil/bedrock zones with different mechanical and hydraulic properties or between the embankment and concrete structures;internal erosion and seepage along the bottom of the concrete portion of the spillway channel;piping and formation of deposition cones;scours,erosion gullies and runnels;cracking in the embankment(transverse or longitudinal,surficial or deep-seated frost cracks);squeezing of the soil on the dam face or foot;solifluction of the downstream face,abutments and banks;icings and frost blisters on the downstream face and adjacent area;reservoir ice conditions;ice formation in the voids in the downstream shell;frost-related slope processes,thermokarst,frost heaving and frost weathering in the dam embankment,reservoir bed,and downstream area;settlement and deformation along the water pipelines;condition of the wells;condition and performance of the pumping stations;condition of the side spillway,accumulation of snow,ice,sediment or debris obstructing flood flows;condition of the siphon spillways;condition of the geomembrane;performance of the cold air and liquid refrigeration systems.

    A summary description of the compliance of the Sytykan River Project with the safety criteria as of 2005 is given below (The Declaration of Safety of the Sytykan River Project,2006).

    2) Adequacy of quantitative parameters

    Dam:

    ·crest elevation—adequate (criterial value ? 321.00 m,actual value ? 321.50 m);

    ·crest width—adequate (criterial ≥16 m,actual 16 to 76 m);

    ·physico-mechanical characteristics of the dam embankment and foundation—adequate;

    ·normal freeboard—adequate (criterial ≥1 m,actual 1.29 m);

    ·deformations—adequate (decreasing);

    ·ground temperature in the dam embankment and foundation—adequate in the embankment and inadequate in the right abutment (criterial ≥-2 °C,actual-7 to-14 °C in the embankment and 2 to 8 °C in the right abutment);

    ·seepage line position in the thawed zone of the dam—adequate (no seeps on the downstream face);

    ·turbidity of seepage water—adequate (same as in reservoir water);

    ·seepage rate through the unfrozen embankment and foundation zone—inadequate (actual 7×103–8×103m3/h).

    Reservoir:

    ·normal water level—inadequate (criterial ?371.71 m,actual ? 317.60 m);

    ·dead storage level—adequate (? 311.00 m);

    ·water quality—adequate (complies with the drinking water standard).

    Spillway channel:

    ·bottom width,depth,and crest elevation—adequate(10 m,5 m,and ? 317.71 m).Liquid refrigeration systems:

    ·kerosene level in the collector—adequate (20 cm below the expander lid).

    3) Adequacy of qualitative parameters

    ·documentation—compliant with the regulations;

    ·operations and maintenance program and monitoring program—compliant with the regulations;

    ·performance condition of the Project components—not compliant with the regulations;

    ·surveillance—compliant with the regulations and the monitoring plan;

    ·location and elevation of instrumentation—deficient(6 surface plates not installed);

    ·cold air refrigeration system—compliant with the Temporary Operations and Maintenance Manual for the Sytykan River Project.

    5 Conclusion

    The declaration of safety has shown that the components of the Sytykan River Project are mostly in compliance with the safety criteria.The safety of the structures is largely assured by measures taken to freeze the right abutment of the dam and its foundation,the spillway foundation,and the right shoreline of the reservoir,as well as to reduce seepage from the reservoir.The structures of the project are performing in accordance with the design,except for the temperature and seepage parameters of the right abutment,spillway,and right reservoir shoreline.The dam and its foundation are in a thawed-frozen state.The measures undertaken so far to reduce seepage through the embankment,in the foundation and below the spillway channel have allowed the Sytykan River Project to supply the essential volume of water to the town of Udachny and mining facilities,however,it is still not capable of delivering a full design water supply.

    Continual safety monitoring is implemented at the project.The maintenance and surveillance mostly conform to the requirements set in the PB 03-438-02,Safety Rules for Hydraulic Structures of Industrial Waste Liquid Storages (Gosgortechnadzor of Russia,2002a).The owner consistently seeks ways to improve the stability of the dam and reduce seepage losses from the reservoir by employing specialized research institutions.

    Currently,the main task of the operational personnel is to strictly adhere to the recommendations presented in the safety declaration,namely to prevent talik development at the right abutment and along the spillway,as well as to maintain the frozen partial cutoff beneath the spillway crest.

    It has to be admitted,however,that the seepage problem has not been satisfactorily resolved after 38 years of the dam operation.Seepage pathways are continuing to readjust in the right-bank slope.Recent geophysical investigations have detected new seepage areas along the right slope about 1 km downstream from the dam.In addition to the main talik,another large zone of increased flow has been detected 700 m from the reservoir shoreline east of the main talik(Shesternevet al.,2012).

    Aleshin DV,Shishov IN,Fedoseev VI,2005.Reconditioning of the pressure face of the waterworks facility on Sytykan River.Power Technology and Engineering,39(1):19–26.

    Biyanov GF,Kogodovsky OA,Makarov VI,1989.Embankment Dams on Permafrost.Permafrost Institute Press,Yakutsk.

    Gosgortechnadzor of Russia,1998.RD 03-259-98,Instruction on Safety Monitoring Practice for Enterprises and Organizations Supervised by Gosgortechnadzor of Russia.

    Gosgortechnadzor of Russia,2001.RD 03-417-01,Guidelines for Developing Hydraulic Structure Safety Monitoring Programs for Businesses,Facilities and Organizations Controlled by the Gosgortechnadzor of Russia.

    Gosgortechnadzor of Russia,2002a.PB 03-438-02,Safety Rules for Hydraulic Structures of Industrial Waste Liquid Storages.

    Gosgortechnadzor of Russia,2002b.RD 03-443-02,Instruction on the Practice of Determining Safety Criteria and Performance Assessment of Structures of Industrial Liquid Waste Storages at the Production Facilities,Objects and Organizations Supervised by Gosgortechnadzor of Russia.

    Grechishchev SE,Sheshin YB,1973.Theoretical and experimental investigations of temperature-induced stresses and strains in earthfill dams in winter.In:Thermal and Mechanical Interaction of Frozen Soils with Engineering Structures.VSEGINGEO,Moscow,pp.C.77–94.

    Kayakin VV,Bobkov SA,2010.On issue of safety criteria of hydraulic structures.Gidrotechnicheskoe Stroitelstvo,2:40–46.

    Mirtskhulava TE,2008.Approaches to aging assessment of dams in long-term operation.Gidrotechnicheskoe Stroitelstvo,6:41-49.

    Pridorogin VM,1979.Reliability of earth structures built in the northern engineering-climatic zone.In:Hydraulic Engineering in Permafrost and Cold Areas.Leningrad,pp.8–12.

    Shchedrin VN,Kosichenko YM,2011.Safety problems of water-development works designed for land reclamation.Power Technology and Engineering,45(4):264–269.

    Shesternev DM,Velikin SA,Radosteva AV,2012.Problems of safe operation of hydroengineering systems in western Yakutia,a case study of the Sytykan River project.In:Underground Hydrosphere,Proceedings of Russian Conference on Groundwater in Eastern Russia (XX Conference on Groundwater in Siberia and Far East).Irkutsk,pp.413–418.

    State Duma of the Russian Federation,1997.Federal Law of the Russian Federation of 21.07.97 No.117,On the Safety of Hydraulic Structures.

    The Declaration of Safety of the Sytykan River Project,Udachny Mine Complex,2006.Udachny.

    Unified Energy System of Russia,2001.RD 153-34.2-21.342-00,Methodology for Determining Safety Criteria for Hydraulic Structures.

    Unified Energy System of Russia,2004.RD 153-34.2-21.546-2003,Rules for Establishing and Performing Field Observations and Investigations on Embankment Dams.St.Petersburg.

    Unified Energy System of Russia,2006.Guide to RD 153-34.2-21.342-00,Methodology for Determining Safety Criteria for Hydraulic Structures.

    Zhang RV,1969.Heat and moisture regime of small embankment dams for irrigation systems in central Yakutia.In:Abstracts"Temperature and Moisture Regime of Dams under Severe Climatic Conditions of Siberia and Far East".Leningrad,pp.75–78.

    Zhang RV,2002.Temperature Regime and Stability of Small Dams and Earthen Canals on Permafrost.Melnikov Permafrost Institute SB RAS Press,Yakutsk.

    Zoteev VG,Shakhov IS,Morozov MG,et al.,2003.Methodological principles of risk assessing at small-capacity reservoirs.Power Technology and Engineering,37(5):290–296.

    国产成人免费观看mmmm| 成人高潮视频无遮挡免费网站| 国产伦一二天堂av在线观看| 男女啪啪激烈高潮av片| 国产精品一及| 亚洲国产最新在线播放| 欧美成人免费av一区二区三区| 国产欧美日韩精品一区二区| 精品熟女少妇av免费看| 亚州av有码| 成人无遮挡网站| 中文字幕免费在线视频6| 亚洲人成网站在线观看播放| 欧美精品一区二区大全| 高清av免费在线| 国产在视频线精品| 成人美女网站在线观看视频| 欧美日韩一区二区视频在线观看视频在线 | 午夜福利在线在线| 亚洲国产欧美人成| 国产乱来视频区| 秋霞伦理黄片| 国产高潮美女av| 免费不卡的大黄色大毛片视频在线观看 | 亚洲婷婷狠狠爱综合网| 99热这里只有精品一区| 人人妻人人澡人人爽人人夜夜 | 亚洲18禁久久av| 一区二区三区乱码不卡18| 内地一区二区视频在线| 一个人看视频在线观看www免费| 2022亚洲国产成人精品| 一级毛片久久久久久久久女| 晚上一个人看的免费电影| 亚洲性久久影院| 日产精品乱码卡一卡2卡三| 成人特级av手机在线观看| 能在线免费观看的黄片| 一级毛片aaaaaa免费看小| 日本-黄色视频高清免费观看| 日韩制服骚丝袜av| 99久久无色码亚洲精品果冻| 欧美另类亚洲清纯唯美| 精品不卡国产一区二区三区| 国产精品av视频在线免费观看| av视频在线观看入口| 免费看日本二区| 高清视频免费观看一区二区 | av在线天堂中文字幕| 欧美色视频一区免费| 国产精品蜜桃在线观看| 亚洲欧美日韩东京热| 中文欧美无线码| 国产精品精品国产色婷婷| 午夜激情福利司机影院| 亚洲人成网站在线观看播放| 亚洲成人中文字幕在线播放| 三级国产精品片| 国产一区有黄有色的免费视频 | 日产精品乱码卡一卡2卡三| 亚洲最大成人av| 国产精品一区www在线观看| 欧美一级a爱片免费观看看| 国产一级毛片七仙女欲春2| 爱豆传媒免费全集在线观看| 精品人妻熟女av久视频| 国产成人一区二区在线| 婷婷六月久久综合丁香| 毛片女人毛片| 免费一级毛片在线播放高清视频| 2021天堂中文幕一二区在线观| 亚洲av电影在线观看一区二区三区 | 色综合站精品国产| 亚洲一区高清亚洲精品| 女人久久www免费人成看片 | 午夜免费男女啪啪视频观看| 亚洲自拍偷在线| 久久综合国产亚洲精品| 欧美成人午夜免费资源| 最近中文字幕2019免费版| 亚洲av男天堂| 天天躁日日操中文字幕| 久久久a久久爽久久v久久| 欧美日韩一区二区视频在线观看视频在线 | 看黄色毛片网站| 男人舔奶头视频| 青春草亚洲视频在线观看| 人妻系列 视频| 亚洲国产日韩欧美精品在线观看| 欧美bdsm另类| 丰满少妇做爰视频| 国产探花在线观看一区二区| 亚洲国产精品sss在线观看| 一夜夜www| 亚洲欧美精品综合久久99| 岛国毛片在线播放| 国产精品,欧美在线| 亚洲av免费高清在线观看| 精品久久久噜噜| 亚洲精品aⅴ在线观看| 国产精品日韩av在线免费观看| 亚洲欧美一区二区三区国产| 亚洲最大成人中文| 爱豆传媒免费全集在线观看| 国产精品国产三级国产专区5o | 嫩草影院新地址| 欧美成人免费av一区二区三区| 国产黄片美女视频| 国产成人福利小说| 桃色一区二区三区在线观看| 老司机影院毛片| 在线免费观看的www视频| 男人和女人高潮做爰伦理| 国产伦精品一区二区三区四那| 波多野结衣高清无吗| 国产精品精品国产色婷婷| 蜜桃亚洲精品一区二区三区| 美女脱内裤让男人舔精品视频| 日韩大片免费观看网站 | 美女脱内裤让男人舔精品视频| 精品午夜福利在线看| 成人性生交大片免费视频hd| 国产亚洲精品av在线| 美女大奶头视频| 91久久精品国产一区二区成人| 国产在线一区二区三区精 | 国产精品久久久久久av不卡| 国产欧美日韩精品一区二区| 在线观看一区二区三区| 国产老妇伦熟女老妇高清| 99久久精品一区二区三区| 国产极品天堂在线| 欧美成人a在线观看| 亚洲在线自拍视频| 人人妻人人澡欧美一区二区| 女人十人毛片免费观看3o分钟| 国产久久久一区二区三区| 欧美三级亚洲精品| 亚洲av一区综合| 高清毛片免费看| 免费观看在线日韩| 免费观看人在逋| 99热这里只有精品一区| 中文字幕av成人在线电影| 观看美女的网站| 成年av动漫网址| 在线天堂最新版资源| 国产一区二区亚洲精品在线观看| 一卡2卡三卡四卡精品乱码亚洲| 国语自产精品视频在线第100页| 97超视频在线观看视频| 国产亚洲一区二区精品| 精品国产一区二区三区久久久樱花 | av女优亚洲男人天堂| 国产亚洲精品av在线| 男人舔女人下体高潮全视频| 久久久国产成人免费| 啦啦啦观看免费观看视频高清| 久久欧美精品欧美久久欧美| 插阴视频在线观看视频| av在线亚洲专区| 日韩制服骚丝袜av| 日韩一区二区三区影片| 欧美三级亚洲精品| 最近中文字幕高清免费大全6| 级片在线观看| av在线观看视频网站免费| 综合色丁香网| 一级毛片aaaaaa免费看小| 国产一区二区三区av在线| 六月丁香七月| 亚洲人成网站在线观看播放| 最近最新中文字幕免费大全7| 成人性生交大片免费视频hd| 老司机影院毛片| 久久久久久国产a免费观看| 国产精品伦人一区二区| 身体一侧抽搐| 色播亚洲综合网| 亚洲av成人精品一区久久| 亚洲精品乱码久久久久久按摩| 搡老妇女老女人老熟妇| 精品人妻一区二区三区麻豆| 久久99精品国语久久久| 一区二区三区乱码不卡18| 午夜免费男女啪啪视频观看| 免费不卡的大黄色大毛片视频在线观看 | 中文字幕制服av| 插逼视频在线观看| 日韩成人av中文字幕在线观看| 国产在视频线在精品| 久久热精品热| 一区二区三区四区激情视频| 日韩一区二区视频免费看| 亚洲成人中文字幕在线播放| 大香蕉97超碰在线| 九草在线视频观看| 中国国产av一级| 亚洲精品乱码久久久v下载方式| 国产免费一级a男人的天堂| 久久久精品94久久精品| 老女人水多毛片| 国产三级在线视频| 99在线视频只有这里精品首页| 特级一级黄色大片| 高清av免费在线| 中文字幕制服av| 91久久精品电影网| 91在线精品国自产拍蜜月| 日本一本二区三区精品| 热99在线观看视频| 桃色一区二区三区在线观看| 欧美一区二区精品小视频在线| 丝袜美腿在线中文| 国产成人一区二区在线| 久久人人爽人人爽人人片va| 一卡2卡三卡四卡精品乱码亚洲| 中文天堂在线官网| videossex国产| 日韩成人伦理影院| 国产精品一区二区三区四区久久| 超碰97精品在线观看| 国产精品久久久久久久电影| 一区二区三区四区激情视频| 亚洲欧美成人精品一区二区| 日韩欧美三级三区| 精品99又大又爽又粗少妇毛片| 边亲边吃奶的免费视频| 插阴视频在线观看视频| 大又大粗又爽又黄少妇毛片口| 亚洲国产高清在线一区二区三| a级毛片免费高清观看在线播放| 色综合站精品国产| av视频在线观看入口| 一级黄片播放器| 最近最新中文字幕大全电影3| 亚洲av二区三区四区| 日本wwww免费看| 亚洲国产最新在线播放| 亚洲av成人精品一区久久| 人体艺术视频欧美日本| 国产成人91sexporn| 亚洲四区av| 精品国内亚洲2022精品成人| 久久热精品热| 美女xxoo啪啪120秒动态图| 干丝袜人妻中文字幕| 亚洲欧美日韩东京热| 国产精品av视频在线免费观看| 插阴视频在线观看视频| 国产精品电影一区二区三区| 国产亚洲5aaaaa淫片| 欧美激情在线99| 99久久人妻综合| 久久久久久久久久久免费av| 我的女老师完整版在线观看| 亚洲av免费高清在线观看| 波多野结衣巨乳人妻| 亚洲乱码一区二区免费版| 卡戴珊不雅视频在线播放| 国产亚洲av片在线观看秒播厂 | 日韩视频在线欧美| 精品人妻偷拍中文字幕| 午夜亚洲福利在线播放| 亚洲精品乱码久久久v下载方式| 成年女人看的毛片在线观看| 国产一区二区在线av高清观看| 啦啦啦啦在线视频资源| 国产精品一区二区在线观看99 | 热99在线观看视频| 日本一二三区视频观看| 亚洲av中文字字幕乱码综合| 日本色播在线视频| 一区二区三区免费毛片| 成人一区二区视频在线观看| 日韩 亚洲 欧美在线| 欧美极品一区二区三区四区| 国产麻豆成人av免费视频| 国产精品久久久久久久久免| 亚洲不卡免费看| 亚洲欧美成人精品一区二区| 亚洲色图av天堂| 少妇熟女aⅴ在线视频| 色尼玛亚洲综合影院| 日韩欧美国产在线观看| 国产午夜精品一二区理论片| 你懂的网址亚洲精品在线观看 | 少妇被粗大猛烈的视频| 午夜a级毛片| 日韩精品青青久久久久久| 男人舔奶头视频| www.色视频.com| 国产一区二区亚洲精品在线观看| 99国产精品一区二区蜜桃av| 简卡轻食公司| 国产精品久久电影中文字幕| 欧美变态另类bdsm刘玥| 成年版毛片免费区| 久久精品人妻少妇| 久久精品夜夜夜夜夜久久蜜豆| 七月丁香在线播放| 在线观看美女被高潮喷水网站| 午夜老司机福利剧场| 99热6这里只有精品| 两个人视频免费观看高清| 69av精品久久久久久| 成人av在线播放网站| 内地一区二区视频在线| 18+在线观看网站| 高清午夜精品一区二区三区| 国产精品无大码| 免费不卡的大黄色大毛片视频在线观看 | 男人的好看免费观看在线视频| 久久人人爽人人片av| 色尼玛亚洲综合影院| 国产伦精品一区二区三区四那| 亚洲欧美日韩东京热| 国产极品精品免费视频能看的| 午夜福利在线在线| 色综合亚洲欧美另类图片| 精品久久久久久久久av| 最近中文字幕高清免费大全6| 午夜免费激情av| 国产中年淑女户外野战色| 国产精品久久电影中文字幕| 国产激情偷乱视频一区二区| 色综合色国产| 成人毛片a级毛片在线播放| 97人妻精品一区二区三区麻豆| 亚洲av免费在线观看| 少妇裸体淫交视频免费看高清| 国产在视频线精品| 一级av片app| 夜夜爽夜夜爽视频| 伦理电影大哥的女人| 久久鲁丝午夜福利片| 午夜激情福利司机影院| 亚洲久久久久久中文字幕| 欧美激情久久久久久爽电影| 日韩一本色道免费dvd| 天堂√8在线中文| 亚洲va在线va天堂va国产| 久久久久久久国产电影| 赤兔流量卡办理| 中文字幕av在线有码专区| 久久精品国产亚洲av涩爱| 亚洲精品亚洲一区二区| 我要看日韩黄色一级片| 精品人妻熟女av久视频| 日韩一区二区视频免费看| 天天躁夜夜躁狠狠久久av| 亚洲国产欧美人成| 久99久视频精品免费| 欧美潮喷喷水| 国产高潮美女av| 国产黄a三级三级三级人| 99九九线精品视频在线观看视频| 亚洲国产精品成人综合色| 日本一二三区视频观看| 久久久a久久爽久久v久久| 久久精品91蜜桃| 亚州av有码| 一二三四中文在线观看免费高清| 性插视频无遮挡在线免费观看| 免费看av在线观看网站| 精品久久久久久久人妻蜜臀av| 91久久精品电影网| or卡值多少钱| 久久精品国产亚洲网站| 国产成人精品一,二区| 国产精品一区二区性色av| 在线免费观看的www视频| 激情 狠狠 欧美| 青春草国产在线视频| 亚洲欧美成人精品一区二区| 国产精品福利在线免费观看| 丰满乱子伦码专区| 日韩亚洲欧美综合| 国产久久久一区二区三区| 国产精品.久久久| 色综合亚洲欧美另类图片| 亚洲四区av| 午夜视频国产福利| 日韩人妻高清精品专区| 最近视频中文字幕2019在线8| 久久国内精品自在自线图片| 麻豆成人午夜福利视频| 欧美日本视频| 亚洲精品乱久久久久久| 51国产日韩欧美| 亚洲在久久综合| 长腿黑丝高跟| 国产精品伦人一区二区| 精品熟女少妇av免费看| 18禁在线播放成人免费| 中文字幕人妻熟人妻熟丝袜美| 亚洲自拍偷在线| 1024手机看黄色片| 国产精品乱码一区二三区的特点| 亚洲av福利一区| 亚洲图色成人| 欧美三级亚洲精品| av在线蜜桃| 成人漫画全彩无遮挡| 级片在线观看| 亚洲精品久久久久久婷婷小说 | 最后的刺客免费高清国语| 亚洲在线观看片| 男人舔女人下体高潮全视频| 亚洲欧美一区二区三区国产| 夫妻性生交免费视频一级片| 中国国产av一级| 中文字幕久久专区| 热99在线观看视频| 秋霞在线观看毛片| 国产免费一级a男人的天堂| 免费观看的影片在线观看| 成人亚洲欧美一区二区av| av在线播放精品| 美女被艹到高潮喷水动态| 日韩人妻高清精品专区| 国产视频首页在线观看| 少妇人妻精品综合一区二区| 国产 一区 欧美 日韩| 国产乱人偷精品视频| 亚洲第一区二区三区不卡| 亚洲av成人av| 国产精品久久视频播放| 男女那种视频在线观看| 精品久久久久久久久亚洲| 一本一本综合久久| 国语自产精品视频在线第100页| 精品免费久久久久久久清纯| 日本一本二区三区精品| 中文字幕av成人在线电影| 秋霞在线观看毛片| 国产高清有码在线观看视频| 久久久精品大字幕| 精品一区二区免费观看| 国产精品伦人一区二区| 欧美一区二区精品小视频在线| av国产久精品久网站免费入址| 国产精品人妻久久久久久| 一边亲一边摸免费视频| 亚洲天堂国产精品一区在线| 五月伊人婷婷丁香| 成人鲁丝片一二三区免费| 久久精品人妻少妇| 在现免费观看毛片| av天堂中文字幕网| 69av精品久久久久久| 中国美白少妇内射xxxbb| 高清av免费在线| 亚洲精品一区蜜桃| www日本黄色视频网| 亚洲av熟女| 中文资源天堂在线| 精品久久久久久久久亚洲| 韩国av在线不卡| 欧美不卡视频在线免费观看| 我要搜黄色片| 成人午夜精彩视频在线观看| 亚洲av成人精品一二三区| 麻豆精品久久久久久蜜桃| 亚洲欧美精品自产自拍| 午夜福利在线观看吧| 特级一级黄色大片| 久久精品综合一区二区三区| 亚洲人成网站高清观看| 亚洲欧洲国产日韩| 老司机福利观看| av国产免费在线观看| 成年免费大片在线观看| 欧美精品一区二区大全| 男人和女人高潮做爰伦理| 插逼视频在线观看| 欧美成人一区二区免费高清观看| www.av在线官网国产| 天美传媒精品一区二区| 亚洲精华国产精华液的使用体验| 国产亚洲午夜精品一区二区久久 | 日韩欧美精品免费久久| 国产精品综合久久久久久久免费| 亚洲一区高清亚洲精品| 最近最新中文字幕免费大全7| 麻豆一二三区av精品| 久久综合国产亚洲精品| 插逼视频在线观看| 三级国产精品片| 午夜a级毛片| 国产色婷婷99| 一夜夜www| 欧美日韩一区二区视频在线观看视频在线 | 亚洲成人av在线免费| 久久久久网色| av国产免费在线观看| 国产一区有黄有色的免费视频 | 午夜福利在线观看吧| 欧美一区二区精品小视频在线| 国产精品伦人一区二区| 亚州av有码| 久久久久免费精品人妻一区二区| 97热精品久久久久久| 成年女人看的毛片在线观看| 秋霞在线观看毛片| 国产成人91sexporn| 亚洲人成网站在线观看播放| 嫩草影院入口| 日韩av在线免费看完整版不卡| 中文字幕亚洲精品专区| 高清av免费在线| 国产精品乱码一区二三区的特点| 日韩亚洲欧美综合| 亚洲成人中文字幕在线播放| 国产色婷婷99| 亚洲欧美日韩卡通动漫| 亚洲中文字幕一区二区三区有码在线看| 色视频www国产| 日韩大片免费观看网站 | 国产精品国产三级国产av玫瑰| 欧美一级a爱片免费观看看| 日本免费a在线| 天堂中文最新版在线下载 | 女人十人毛片免费观看3o分钟| 国产一级毛片七仙女欲春2| 欧美3d第一页| 国产精品国产三级国产av玫瑰| 尾随美女入室| 日本一二三区视频观看| 深夜a级毛片| 亚洲在线自拍视频| 日本爱情动作片www.在线观看| 日本免费在线观看一区| 一本一本综合久久| eeuss影院久久| 久久久久久久亚洲中文字幕| 舔av片在线| 熟女电影av网| 超碰97精品在线观看| 国产成年人精品一区二区| 熟妇人妻久久中文字幕3abv| 99久国产av精品国产电影| 哪个播放器可以免费观看大片| 夜夜爽夜夜爽视频| 一二三四中文在线观看免费高清| 精品人妻偷拍中文字幕| 久久久久久久久久久丰满| 激情 狠狠 欧美| 你懂的网址亚洲精品在线观看 | 欧美一区二区精品小视频在线| 精品99又大又爽又粗少妇毛片| 99热网站在线观看| 欧美日本视频| 国产亚洲精品久久久com| 国产 一区精品| 大又大粗又爽又黄少妇毛片口| 69av精品久久久久久| 日韩一本色道免费dvd| 国产在线一区二区三区精 | 秋霞伦理黄片| 天天躁日日操中文字幕| 国产极品天堂在线| 亚洲人成网站高清观看| 美女xxoo啪啪120秒动态图| 中文亚洲av片在线观看爽| 国产精品国产三级国产专区5o | 成人综合一区亚洲| 国产免费视频播放在线视频 | 欧美一区二区亚洲| 寂寞人妻少妇视频99o| 亚洲av不卡在线观看| 国产成人福利小说| 国产高清不卡午夜福利| 欧美3d第一页| 国产成人福利小说| 三级经典国产精品| a级毛色黄片| 在线免费观看的www视频| 伦精品一区二区三区| 99久久精品国产国产毛片| 精品久久久久久久久亚洲| 亚洲av中文字字幕乱码综合| 最近中文字幕高清免费大全6| 22中文网久久字幕| 亚洲天堂国产精品一区在线| 一夜夜www| 美女脱内裤让男人舔精品视频| 久久精品国产99精品国产亚洲性色| 亚州av有码| 高清视频免费观看一区二区 | 国产精品一区www在线观看| 亚洲真实伦在线观看| 欧美成人免费av一区二区三区| 国产私拍福利视频在线观看| 亚洲成av人片在线播放无| 99久国产av精品国产电影| 午夜a级毛片| 尾随美女入室| 亚洲国产精品成人久久小说| 亚洲欧美成人综合另类久久久 | 成人无遮挡网站| 亚洲国产精品sss在线观看| 国产伦精品一区二区三区四那| 欧美性猛交╳xxx乱大交人| 成人毛片60女人毛片免费| 亚洲精品一区蜜桃| 嫩草影院新地址| 亚洲精品自拍成人| 欧美另类亚洲清纯唯美| 嫩草影院精品99| 国内精品美女久久久久久| 亚洲成色77777| 亚洲成人久久爱视频| 色综合亚洲欧美另类图片| 日韩国内少妇激情av|