• <tr id="yyy80"></tr>
  • <sup id="yyy80"></sup>
  • <tfoot id="yyy80"><noscript id="yyy80"></noscript></tfoot>
  • 99热精品在线国产_美女午夜性视频免费_国产精品国产高清国产av_av欧美777_自拍偷自拍亚洲精品老妇_亚洲熟女精品中文字幕_www日本黄色视频网_国产精品野战在线观看 ?

    Case studies:Frozen ground design and construction in Kotzebue,Alaska

    2014-12-15 05:55:38DanielNichols
    Sciences in Cold and Arid Regions 2014年4期

    Daniel Nichols

    DOWL HKM,Anchorage,Alaska 99503,USA

    1 Introduction

    Alaska is the largest state in the United States of America but it is the least developed and fourth least populated.There are only 25,300 km of public roads for a total land area of 1,717,900 km2(State of Alaska,2012).Most communities in Alaska are remote — not connected to a road system outside the community,and only accessible by barge or airplane.Engineers must be able to modify standard designs to account for these limitations.For example,piping must be sized to fit within a cargo plane’s hold or construction sequencing must consider barge schedules and shortened construction seasons.

    Much of Alaska has frozen soils and permafrost.Due to either climate changes or human activities and development,permafrost often thaws and becomes unstable.Unstable soils can cause damage to infrastructure by thaw settlement,frost jacking,or heaving,which increase maintenance costs,reduce functionality,and decrease the life of constructed projects.These conditions make engineering design and construction in Alaska challenging.

    One place that exemplifies this is Kotzebue,Alaska.Kotzebue is a remote Inupiat village of approximately 3,200 people located 53 km above the Arctic Circle along the Chukchi Sea.The community is on a gravel spit at the end of the Baldwin Peninsula and is surrounded on three sides by the Kotzebue Sound.The gravel spit is approximately 0.9 km wide and 2 km long.The geology of the region is dominated by Quaternary glacial moraine and drift deposits (Golder Associates,2014).Locally in Kotzebue,these deposits are covered by layers of beach sands and gravels with surface organic mats or peats.The area has continuous permafrost except in areas of disturbance.Permafrost temperatures vary greatly due to localized conditions.

    Kotzebue is a subarctic climate,based on the Koppen Climate Classification,although it borders on a tundra climate.Monthly daily average temperatures range from-19.7 °C in February to 12.6 °C in July.Precipitation averages 257 mm annually,with an average of 99 mm in winter.The highest recorded temperature is 29 °C and the lowest recorded temperature is-50 °C.Table 1 presents the historical,current,and future engineering climate indices for Kotzebue.It is derived from the public data available from the University of Alaska-Fairbanks Scenarios Network for Alaska and Arctic Planning (SNAP)(UAF,2014).SNAP projects are calculated using a composite of five global climate models,emission scenario A1B.

    Table 1 Kotzebue Engineering Climate Indices

    2 Purpose and methods

    Engineering and construction conditions are extreme in Kotzebue.These provide significant challenges to engineers,which makes Kotzebue an ideal place to test existing engineering practices and try out new ones.In the past 12 years that I have been working in Kotzebue,I have observed and learned from my experiences as an engineer.It is my goal to document and share a few of the lessons learned,so this experience may be applied by others.

    Three case studies are presented here:the Front Loop Water Main Extension,the Wastewater Lift Station Replacement,and the Ted Stevens Way Rehabilitation.The Front Loop Water Main Extension was chosen because it represents the accumulated knowledge in the trial-and-error process of installation of water mains and service in arctic conditions.The Wastewater Lift Station Replacement was selected because existing designs were not meeting the needs of the community and new design and construction ideas were used.And when the Ted Stevens Way road was designed in 2001,it used the best design practices of the time,yet it was rapidly deteriorating and would not meet its design life.Surveying the current conditions in 2013 uncovered failures in the design and construction,but these failures provided opportunities to improve future design.

    I was the project manager for the Front Loop Water Main Extension and the Wastewater Lift Station Replacement.I was responsible for the design and management of the project from start through construction,and thus have first-hand understanding of the projects.I was able to work directly with the owner (City of Kotzebue) and the users to get their input and observations.I also had access to and reviewed the record drawings and documents of the previous projects.

    I was not involved in the design or construction of Ted Stevens Way,but I was able to review and locate the record drawings and other design documents for the project.I interviewed the owner (Native Village of Kotzebue),maintenance workers,and members of the original construction crew.I then performed my own site investigation of the road.The observations and lessons learned are presented below.

    3 Discussion

    3.1 Case Study #1:Front Loop Water Main Extension

    The City of Kotzebue (hereafter,City) operates and maintains a community water system.Kotzebue is serviced by seven circulating water loops which by 2011 were more than 30 years old.Kotzebue’s extreme temperatures require any design to incorporate extraordinary freeze protection measures.In Alaska,water mains are typically buried at 3 m,which usually provides sufficient insulation cover.The presence of permafrost and poor-strength soils in Kotzebue prevented the typical burial depths,so insulation was required to make up for the lack of cover insulation.The water loops were originally 150-mm polyvinyl chloride (PVC) pipes in insulated 300-mm aluminum corrugated metal pipe (CMP)jackets.This allowed the water loops to be buried with only about 0.7 m of cover.

    The insulation alone is insufficient to provide freeze protection.Extra freeze protection is provided by continuously pumping water from the water treatment plant through the loops.A water velocity of 0.6 m/s is deemed necessary to prevent freezing.The shallow depth also makes emergency repairs easier.The City reports that pipe bursting from freezing is the most common failure,which typically happens during extreme cold weather in the winter.The water treatment plant also adds heat to the loops to maintain the water mains above freezing.The heat is provided by waste heat from the electrical power plant located near the water treatment plant.No metering is done and it is unknown how much heat is added.

    These design measures do a reasonable job in prevent freezing in the water mains.Most freezing occurs within the water services to individual homes,and these water services are smaller and less frequently used.The population in Kotzebue is very transient and seasonal,and many homes are left empty for long periods of time.This means that individual water services are the most vulnerable to freezing.Prior to 2012,the City had reported multiple freeze-ups of water services per year.Because the water services are installed individually and by private contractors,the quality and type of freeze-prevention measures used varies.The City has difficulty in accessing and isolating the water services because there is no uniform system.

    Much of Kotzebue is built on discontinuous permafrost which tends to be classified as warm (temperature).This leaves the permafrost susceptible to thawing from environmental and man-made heat sources.When thawed,the soils tend to be unstable and subject to compression.Soil investigations have shown soils with visible ice lenses and with compressible organics and silts.Buildings,particularly houses,in Kotzebue have a variety of construction methods.Some buildings have been engineered to protect the soils from thawing further,but the majority of the buildings are private homes which have little or no such design and they vary in construction and quality.

    In the late 1990s,the City of Kotzebue put together a plan for replacement of all seven water loops.The City knew that the old PVC pipes were beginning to deteriorate,and water usage was increasing faster than population growth,indicating water being lost due to leaks.The PVC pipes were becoming unstable and fragile.In the winter of 2011,a fire hydrant was run over by a truck,breaking the water main.The City maintenance crews were unable to isolate the break because the valves were nonfunctioning.Hundreds of thousands of gallons of water were lost before the entire water main loop was shut down.The water main was so fragile that a large section of pipe had to be replaced in order to find competent pipe to which to connect repairs.The maintenance was made more difficult due to frozen ground and temperatures below-34 °C.By the time the repairs were completed,several hundred homes had been without water for four days and 100,000 gallons of water were lost.

    Issues like this made replacing the water loops and water services in Kotzebue a priority for the city government.In 2005,the City began to systematically replace the water loops.The final project was the replacement of the Southern Loop.The project design began in 2011 and was completed in 2012.The Southern Loop was 2,830 m long and serviced the southern section of the city.It was also the oldest portion of the community.The design abandoned the existing Southern Loop and expanded the Front Loop by 1,340 m,for a total of 4,175 m.The Front Loop had been replaced in 2009.

    The design and replacement of the water main loop was fairly straightforward and incorporated standard arctic design in Alaska.The water main loop was replaced with a 200-mm HDPE circulating main inside an insulated 380-mm HDPE jacket with all joints electrofusion welded.This ensured that the water main had the strength and flexibility to withstand ground movement due to thawing and settling.The water main was protected by 90 mm of pipe insulation,circulation pumps that maintained a water velocity of 0.6 m/s,and the addition of heat at the water treatment plant.

    The more difficult design issue was that of the water service piping to serve the individual buildings off the water main.The two main water service design challenges were movement due to thaw settlement at the individual buildings,and providing adequate freeze protection for the water service piping.

    HDPE piping has enough flexibility and strength to withstand movement within the trench.The movement is greatest at the connection of the water service piping and a building.The water service piping and the building move independently and are two very different systems.They move at varying rates and amounts between them.Differential settlement at the piping and building interface of 75 mm or greater has been observed,and this amount can easily shear the pipe or cause joint failure.Since the project could not stabilize all of the building foundations,the interface connection at the buildings had to be designed for inevitable movement.

    Through past experience,a design was developed to provide a flexible connection to a house that allows for movement.The project design called for installation of an"arctic box," which is a simple insulated wooden box attached to the outside of a building (Figure 1).The arctic box houses and provides access to a flexible connection system.This flexible connection allows greater movement and prevents the shearing and joint failures from differential movement.The 25-mm HDPE pipes end in a 25-mm ball valve,a 90-deg elbow,and are connected into 19-mm PEX A piping with SharkBite quick-connect fittings (SharkBite USA,Atlanta,GA).PEX A piping is cross-linked polyethylene piping,and it is used because it has greater flexibility and can withstand the differential movement within the box.Only the 25-mm HDPE pipes are connected to the house.The carrier pipe and jacket stop 0.5 m below the arctic box.A rubber boot and compressible insulation are used to seal the arctic box to the carrier pipe.Thus,movement in the carrier pipe does not place stress on the arctic box or the connections.

    The second challenge was providing adequate freeze protection for the water service piping up to the building.The water service piping requires both passive and active freeze protection.The passive freeze protection is necessary because the buildings are often left without power or are not used for long periods.The owners or operators of the buildings are mostly private individuals and the City of Kotzebue has no assurance that the owners will operate active freeze protection systems.This is especially true because many residents leave the community for extended periods for employment and subsistence activities.

    The passive freeze prevention systems include passive water circulation and insulation.Each building is serviced by a supply pipe and a return pipe.The supply line brings the water into the building and the return line recirculates the water back into the water main.The pipes are typically 25-mm HDPE pipe.The supply line is tapped into the water main with a pitorifice,a pipe that extends into the water main with a scoop that faces into the water flow in the main (Figures 2 and 3).The return line brings water back in the main with a similar pitorifice but is turned the opposite direction of the water flow in the main.This causes a differential water pressure between the supply and the return lines,which results in the water being continually pushed or circulated through the water service.The design calls for 75-mm-long pitorifice constructed of 25-mm copper pipe,type K.The copper pipe end is bent with a radius of 57 mm with an opening of 8.6 cm2.Experience has shown that these pitorifices will keep water circulating on water service runs up to 25 m.When water services exceed those distances,the pressure differential is not sufficient to maintain circulation and prevent freezing.

    Figure 1 Inside an arctic box at the connection between the water service and the building (left);outside an arctic box with a flexible boot connection to an insulated water service pipe (right)

    Figure 2 Pitorifice design detail

    Figure 3 Water service connection at a main using a pitorifice

    The 25-mm supply and return pipes are contained in a 100-mm HDPE carrier pipe in an insulated 300-mm HDPE jacket.This provides nominal 100-mm insulation.The insulation is extruded closed-cell polyurethane foam with an initial thermal conductivity factor (U) not greater than 0.023 (K·m2)/W.As a general rule of thumb,25 mm of insulation is roughly equal to 100 mm of ground cover.The insulated pipe creates passive freeze protection equivalent to 2 m of cover.

    In ideal situations these two passive systems,recirculation and insulation,should protect against the normal cold weather in Kotzebue.However,additional active systems were also added in Kotzebue because water services are a basic necessity for life and,inevitably,when these systems fail it is in the most extreme cold temperatures (-40 °C to-45 °C),which makes repairs very difficult.It is not uncommon in Alaska,when water systems freeze,to be completely shut down for weeks,leaving communities without a source of treated water.These extreme conditions require additional active freeze protection.

    The City of Kotzebue also required that each building with a water service be fitted with a recirculation pump.The pumps are 1/25 HP (30 W),115 V,5 gpm (0.003 m3/s),0.75-in.(20 mm) Grundfos UP15-42 (Grundos Pumps Corp.,Olathe,KS).These pumps ensure that even in the coldest weather the water will recirculate faster than 0.6 m/s.These pumps are controlled by the owner and can be shut off during warm periods to reduce energy costs.

    The second active freeze prevention system was the addition of two electric heat trace lines,one in the water service and one in the arctic box.The design called for 1.5 W/m,self-limiting RAYCHEM type 5XL1-CT heat traces (Pentair USA,Houston,TX).In the City’s experience,a 1.5 W/m heat trace provides the right amount of heat for the least amount of energy.Each heat trace line is connected to its own digital thermostat (DigiTrace EC-TS-10;Pentair USA,Houston,TX).Two heat trace lines are used to save energy costs.Most freezing occurs in the arctic box with the pipes at the interface with the building.In these areas,the pipes are above ground and are regularly subjected to colder temperatures than the pipes in the ground.If only one heat line were used,the entire heat trace line would be turned on whenever the arctic box temperature dropped below freezing.With two separate heat trace lines,only the short line within the arctic box turns on regularly,saving power.The heat trace line in the water service pipe is usually only used as a backup heat source.It is only turned on when the recirculation pump fails or in extreme weather.The heat trace line in the water service pipe is placed within a 25-mm Schedule 40 "orange" HDPE pipe.This pipe has a higher heat rating than the regular 25-mm HDPE pipe used for the supply and return lines.The heat trace pipe protects the return and supply lines from heating up too much,and it is sealed to keep the heat trace dry in case the carrier pipe becomes filled with water.This has been a common reason for failures in the heat trace lines.

    The construction was completed in fall 2012.The winter of 2012-2013 was unusually cold,and in February 2013 the mean daily temperature was-22.4 °C,which is 4.2 °C lower than the normal temperature.The only failures of frozen lines reported along the entire project were determined to be operational or construction errors.In one building,the heat trace had not been turned on,and in another the recirculation pump was installed backwards,pushing against the pitorifice flows.Once those problems were fixed,none of the repaired lines froze again.

    3.2 Case Study #2:Wastewater Lift Station Replacement

    The City of Kotzebue operates and maintains a wastewater collection system.The system includes a combination of gravity sewer mains,lift stations,and force sewer mains.The system has been constructed in pieces over time since the 1960s as the city has expanded and grown.Most of the system is more than 30 years old and is past its useful design life.This is most obvious at the lift stations.Many of the 12 lift stations in Kotzebue were built in the early 1980s,when the standard lift station design included a prefabricated canister-style wet well with a submersible pump.These lift stations were not enclosed in a building and were exposed to the extreme weather of Kotzebue.These prefabricated lift stations made shipping and installation simpler,but exposure to the elements decreased their design life.By the late 1990s the City reported regular failures in these canister lift stations.

    Lift Station #5 was one of these typical prefabricated,submersible pump lift stations;it was constructed in the early 1980s.It collected approximately half the sewer flow in Kotzebue,including the Northwest Arctic Borough K-12 School,the largest single user in the community.By the late 2000s,the pumps were regularly operating at or over capacity at 0.009 m3/s.Clothing or other debris would often get wrapped around the pumps,overloading them.This caused significant strain on the pumps,which would cause multiple failures each winter.Repairs typically involved a three-man crew.The wet well would have to be isolated and by-pass pumps installed.The pumps were attached on rails which were used to guide the pumps as they were raised and lowered.The rails were corroded and would ice up.All the work was done outside,often during the winter time with temperatures below-18 °C or colder.Repairing or cleaning the pumps was hazardous work that would often take 24 man-hours to complete.

    By 2012,the city had secured funding to replace Lift Station #5.The city did not have a record of the original design,but in 2009 the city had replaced Lift Station #2,which incorporated a similar submersible pump system but within a building structure.Enclosing the lift station was a huge benefit and improved the maintenance and operation of the pumps.But the new submersible pumps had the same problems as the old lift station:The hoist system would break,requiring the maintenance crews to go "fishing" for the pumps,and the rail system often jammed,causing difficulties with raising and lowering.When this happened,the whole lift station would have to be shut down and by-passed.The pump wet well would then be pumped dry to allow maintenance personnel to climb down into the wet well to manually raise the pump.

    The City was not pleased with this system.In conjunction with DOWL HKM,an engineering firm based in Anchorage,Alaska,the City reviewed other options.It was decided that the new lift station would include surface end-suction pumps.This allowed the pumps and motors to be on the surface,out of the sewer waste.The suction ends were designed to minimize clogging from clothing and other debris.If the end did become clogged,a water connection was installed and the suction pipe could be back-flushed clean.This new system took one person 10 min to accomplish what a three-man crew did in 8 h on the submersible pumps.The one downside to the surface pumps was the increased building size.A typical submersible lift station is approximately 20 m2whereas a surface lift station is 33 m2.

    The increase in building size was not just an issue of increased construction costs.The soils under Lift Station#5 were a mixture of frozen gravel and sands.The temperature of the permafrost in the area was approximately 0 °C.The City’s funding sources would not allow money to be spent on passive refrigerated foundations,such as refrigerated piles or thermosyphons.The permafrost within Kotzebue is unstable and is only likely to become more unstable over time.Without a passive refrigerated foundation there is no way to prevent the permafrost from thawing over time.As the permafrost slowly melts,there will be creep settlement.The only option is to retard the thawing and minimize the differential settlement.

    The new Lift Station #5 incorporated several designs to minimize differential settlement.A significant amount of differential movement comes from seasonal frost heaving.The first design change was to excavate down 0.6 m past the bottom of the foundation.This removed all frost-susceptible soils and organics.Insulation board 100 mm thick was placed at the bottom of the excavation and extended to 3 m outside the building footprint.The excavation was backfilled with non-frost-susceptible (NFS)gravels.The NFS gravels reduce the amount of fines below 3%,which allows for ice expansion within the gravel and minimizes seasonal frost heaving.The insulation plays two roles.The first is to decrease the depth of seasonal thaw so less of the soil column under the building is susceptible to frost heaving.The second is to draw the permafrost up and protect the permafrost from thawing due to the addition of gravel and a building.The building is also kept unheated except when occupied for extended periods during maintenance operations.This minimizes the heat transferred from the building into the ground.

    The building has a floating concrete slab on-grade.The slab reinforcement is not tied into the foundation wall,as is typically done.Instead,a large expansion joint was placed around the entire wall.This allows the slab to move independent of the building and its foundation.If settlement occurs under the slab,only the slab would move and the building foundation would not be damaged.

    The sewer wet well was another area of concern for settlement and movement.The new wet well was 5.2 m deep with the bottom of excavation 6 m deep,and operated at 1.0-1.5 m of standing water.This creates a large heat sink surrounded by permafrost.In order to minimize permafrost thawing and settlement,the wet well was over-excavated by 1 m.Six-tenths of a meter of NFS gravel was compacted in 300-mm lifts to 95% of maximum dry density.Insulation board 150 mm thick was placed directly underneath the wet well base.The new wet well was constructed of a 1.8-m-diameter concrete manhole with 150-mm walls.The wet well was coated with 150 mm of spray foam with elastomeric coating.The elastomeric coating sealed the insulation,preventing water damage and provided a smoother surface to inhibit heaving from seasonal frost.

    The new wet well was made of precast concrete sections.The barrel sections were fitted together with a groove joint filled with Ram-Nek mastic sealant (Henry Company,El Segundo,CA).Two galvanized joint straps were added at each barrel joint to minimize movement between the barrel sections.The pipe penetrations in the well and the lid included cast-in-place Kor-N-Seal rubber boots (Trelleborg Pipe Seals Milford,Inc.,Milford,NH).These allow 25-50 mm of differential movement between the pipes and the wet well without causing damage.The wet well was constructed completely separate from the building.The wet well penetrates the on-grade concrete slab without any reinforcement between the two.An expansion joint or gap was included around the entire wet well,allowing for differential movement without damage.

    Another difficulty in construction of the lift stations was the excavation depth.Six-meter or greater excavations are required to install the wet wells.United States Occupational Safety and Health Administration’s (OSHA)regulations require that all excavations 6 m or greater must have engineered trench protection.Typically,a sheet pile retaining wall is used for deep excavations,but Kotzebue’s remote location makes shipping sheet piles and pile-driving equipment very expensive.Therefore,in Kotzebue,past projects have had to cut back trench slopes to maintain safe working conditions.Typically,the loose sands and gravels in Kotzebue require a 30-m diameter hole for a 6-m-deep excavation.This would have caused difficulties at Lift Station #5 because it is located within 9 m of a road and an apartment building.In addition,excavation activities usually begin in June or July due to contractors waiting for warmer weather or barge shipping schedules.This increases the risk of permanently thawing permafrost around the excavation.Thawed soils in Kotzebue are often unstable and running sands are common,increasing excavation sizes and risks.The contractor for the Lift Station #5 developed a novel solution to this problem.The contractor began excavation work in April when the weather was warmer but still below freezing.The contractor used a 450-mm auger to drill vertical holes in a 4.6-m circle centered around the proposed wet well (Figure 4).This created a perforation or perimeter guide for excavation.The contractor used an excavator with a specialty multi-ripper bucket (Figure 5).The bucket had offset,serrated teeth for rock-ripping operations.With this excavator the contractor was quickly able to rip the permafrost out of the excavation site vertically with minimal trench protection because of the stable,frozen soils.

    Figure 4 Contractor drilling perimeter guide holes with a 450-mm auger

    This innovative method for excavation of frozen soils had great benefits to the project.This technique reduced the excavation diameter from 30 m to 4.5 m.Keeping the excavation frozen eliminated the need for dewatering and the risk of running sands.The excavation was completed in two weeks instead of the estimated four weeks.It also allowed the contractor to start work two months ahead of construction schedule.Decreasing construction time was essential to the project because of the short shipping and construction season.

    Lift Station #5 construction was completed in September 2013.As of this writing,the building and wet well have almost completed an entire winter cycle.The City reported a warmer winter with multiple freeze-and-thaw cycles,which were particularly harsh and could cause severe frost jacking and movement.The City reports that the building and wet well are stable without any observed movement or damage.The Lift Station #5 design was able to overcome difficult site and weather conditions by using multiple design innovations to minimize permafrost thaw and settlement.The design was able to save construction schedule and budget by finding alternatives to the traditional refrigerated foundation systems.

    Figure 5 Contractor using a multi-ripper bucket to excavate frozen ground in a stable excavation

    3.3 Case Study #3:Ted Stevens Way Rehabilitation

    Kotzebue is located on a narrow gravel spit in the Kotzebue Sound.The spit is less than a 1.5 km wide.The airport at the southern end of the spit effectively cuts off the City of Kotzebue from the mainland.In 2001,a bridge and gravel road was constructed from the north end of Kotzebue to the mainland.The road,which is called Ted Stevens Way,loops around and connects back to the southern end of the spit below the airport.The road is considered a critical link for the community.It provides the only access to vital utilities,including the two community water sources,a wind farm,and a solid waste landfill.It also provides valuable access to subsistence areas.The community members hunt caribou,water fowl,ptarmigan,and rabbits along the road and in the fall they pick blueberries,salmon berries,and lingonberries.

    The original road terrain is mostly flat with some gentle hills,and was constructed directly over virgin wet tundra that had several small stream crossings.There was limited soils investigation done prior to the design.Only eight test borings were drilled along the route,all of which were taken in low-lying areas.The soil columns were remarkably uniform,consisting of a 0.5-to 2.5-m layer of peat over a layer of silt down to the bottom hole.The deepest test borings were more than 30 m deep.The silts consisted of 94% to 97% fines passing a #200 sieve screen.The soils were classified by the Unified Soil Classification System (ASTM,2011),and were frozen for the entire depth.Most of the soil contained ice visible to the unaided eye;most of the soils were classified as Vr or Vs,which have notable ice formation and segregation throughout the soil.Some of the test borings had small layers of non-visible,bonded ice in excess to the soil(Nbe).The soil ice classifications were adapted from the U.S.Army Cold Regions Research Engineering Laboratory classifications (Kaplar and Linell,1966).One boring had a 3-m ice lens at 6-m depth,and another had two ice lenses totaling 1.5 m thick at 3.5 m depth.These silts are stable only when frozen.With that much visible ice in the silt,if thawed there could be 20% or greater settlement.

    The road has a total length of 6,270 m.The travel way is 5.6 m wide with a 0.6-m shoulder on either side.The design called for construction directly on top of the tundra,so a separation geotextile was placed directly on top of the tundra.No excavation was done for the road and the tundra mat was left in place as insulation.The typical cross section consisted of 1.5 m of non-frost susceptible (NFS) gravel fill.The first 1,055 m had one layer of 50-mm insulation board,and most of the rest of the road had two layers of 50-mm insulation board;all of the insulation board was placed 450 mm below the finish grade.The side slopes were designed for 3 horizontal to 1(3:1) vertical drop except where the natural grade was too steep;in those places the side slopes were 2 horizontal to 1 vertical (2:1) drop.

    The road crosses two major streams.Crossings were made with structural plate arch pipes,one 4,700mm×3,000mm and one 6,300mm×4,000mm.Thirty corrugated metal pipe (CMP) culverts,450 mm and 900 mm in diameter,were installed in drainage areas.One of the culverts was located in a larger drainage and was 1,100 mm in diameter.The design called for excavating to set the culvert half depth below existing grade,bedding rock,and 100 mm of insulation under each pipe.

    The Native Village of Kotzebue (NVK),the local Inupiat tribal government,is responsible for operation and maintenance of the Ted Stevens Way.In 2013,NVK was interested in repairing and improving the road in preparation for the construction of a 30-km road to a new deep-water port.Ted Stevens Way would need improvements if it was to handle the new traffic demands of that port.

    In July 2013,I joined an observation trip with NVK personnel to assist them in evaluating the existing condition of Ted Stevens Way.The NVK personnel who were involved with the original construction reported that construction funding was limited and the schedule was rushed.Several chronic issues were discovered during the observation trip,including culvert heaving,culvert settlement,and major side-slope subsidence.

    The majority of the culverts showed signs of heaving in the middle with large stagnant ponds at each end (Figure 6).Because water was no longer flowing through the culverts,it was traveling under and around the culverts and into the road base.The extra water under the road was freezing in winter,causing the road to heave under the culverts.Each year the heaving would jack up the middle of the culverts.NVK personnel reported,and I confirmed by observation,that during construction the culverts were not set to design grades,but were installed directly on the ground.The culverts never functioned as designed and never fully drained water under the road.As a result,water ponded up at the upstream end.The ponded water acted as a heat sink,thawing the permafrost below and causing the ground upstream to settle.Each year the culverts would heave more and the ends would settle more,and the culverts were being crushed by the heaving action.Several of the culverts no longer had sufficient road cover over them and they were being damaged by traffic loads.

    A 900-mm and a 1,100-mm culvert had the exact opposite type of failure.The culvert ends were sticking above the ground and the center of the culverts were settling in the middle (Figure 7).Both culverts were in low-lying areas relative to the surrounding road.At first it was unclear what was causing the settlement when all the other culverts were heaving.Then NVK personnel reported that during construction of those particular culverts,the project had fallen behind schedule and,to save time,no insulation was installed under the culverts.This resulted in the culverts causing thaw settlement under the road.The settlement was greater in the middle,causing the culvert ends to rise up above the ground.Afterwards,water would no longer flow through the pipes,and this caused more water to flow into the road base.The settlement created low points in the silt soils,causing water to pond in the middle of the road and accelerating the thaw of the permafrost.The culvert ends were approximately 0.5 to 1.0 m above original grade.The culverts were damaged to the point that no daylight could be seen through them.

    The most severe damage along the road was side-slope failure.All along the road,large sections of side slopes were shearing off (Figure 8).Lateral cracks 100 mm wide and 0.3 m deep ran approximately 0.8 m from the road shoulder.Guardrails were shifted 1 m down the fill slope and many of the guardrails had completely failed due to shear failure of the side slopes (Figure 9).Insulation boards had been damaged and exposed along the edges.In one area,the insulation layers had been pulled so far apart that sink holes had formed in the road large enough to see the insulation.In some areas the traveled road width had been functionally decreased from 7 m to 5 m.

    The shear failure of the side slopes was caused by the thaw settlement at the side slope toes.No lateral drainage system was installed along the road and there were no drainage ditches (the only drainage structures were the culverts at drainages crossing under the road).This resulted in small ponds forming along the toes of the slopes.The standing water acted as heat sinks,which were accelerating permafrost thawing and causing the settlement.The greatest slope failures were observed where the fill was the greatest:some of the road sections had as much as 4 m of fill.Insulation was installed only 450 mm below finished road grade.This was done because gravel absorbs heat and insulation placed higher up in the gravel reduces the transfer of heat into the underlying permafrost;in effect,this reduces the size of the heat sink.The problem arose on thicker gravel cross sections:insulation placed at the top was 7 m wide from edge of shoulder to edge of shoulder.[A 4-m-thick road section with a 2:1 slope means the base is three times wider (21 m) than the top where the insulation is placed.] Thus,two-thirds of the gravel area on Ted Stevens Way had no insulation.This caused the gravel on the side slopes to retain more heat than the road surface,allowing thaws to go deeper and thaw settlement to occur along the side slopes.The thaw settlement was causing more water collection,and the increase in water accelerated the thawing.Over time,the settlement under the slope became too great and shear failure occurred.In some areas the shear failure was so great it created gaps between the insulation boards,which resulted in a loss of gravel surface (Figure 10).

    The two main issues were improper drainage with standing water,and thaw settlement along the side slopes.These were caused by a combination of design deficiencies and faulty construction.There were several recommendations made to the NVK on how Ted Stevens Way could be rehabilitated.

    Figure 6 Culvert failure due to frost heaving under Ted Stevens Way

    Figure 7 Culvert failure due to thaw settlement under Ted Stevens Way

    Figure 8 Side slope and insulation board damage due to shear failure caused by thaw settlement

    Figure 9 Guard rail damaged by side slope failure and thaw settlement (left);side slope and guard rail damage due to shear failure and thaw settlement (right)

    Figure 10 Loss of gravel surface due to separation of insulation board layers caused by side slope shear failure

    The first would be to remove and reinstall all of the 450-,950-,and 1,100-mm culvert crossings.The culvert areas should be excavated to remove thawed soils,and this could be done in spring when the frost depth is the shallowest.NFS gravels should be used to fill in over excavations,especially at the culvert inlets and outlets.Insulation board (150-mm) should be installed under the culverts and the culvert inlets should be buried so the pipe spring line matches natural grade.The culvert outlet should be set with the bottom of the pipes on existing grade.All-weather wood splash guards should be placed at the outlets to protect them from erosion (wood should be used because it is a better insulator than gravel).Interceptor ditches should be installed lateral to the side-slope toes to direct water away from the road.

    The second rehabilitation effort would be to reconstruct the failed slopes.This would involve excavation of the side slopes and removing thawed soils.Separation geotextile should be placed between the permafrost and the gravel,and NFS gravel should be used to prevent heaving and allow drainage through the road base.Insulation board must be installed along the side slopes;on side slopes with slopes less than 3:1 the insulation can be placed parallel to the slope with 450 mm of cover material,and on side slopes with slopes greater than 2:1 the insulation must be placed horizontally in overlapping tiers.Most insulation comes in 2.4m×1.2m boards,so the boards should be placed lengthwise (2.4 m) into the slope on each 0.3 m soil lift,each board with a 0.6-m overlap on the board underneath it.Side slope insulation should be a minimum of 100 mm thick in order to provide the side slopes with the thaw protection to reduce settlement and shear failures along the slope.

    4 Conclusions

    Permafrost,unstable soils,and remote conditions are obstacles to design and construction in cold regions of the world.Kotzebue,Alaska is a perfect testing ground for frozen ground design and construction techniques,having unstable permafrost,expanding infrastructure,remote location,and a history of what works and what does not work.

    This case study of Kotzebue’s Front Loop Water Main Extension project shows that the main issues facing utilities in the Arctic are freezing and differential movement,especially at building interfaces.Freeze protection can be designed by using a combination of passive and active methods.Passive methods include non-pump circulation and insulation techniques.Active methods include heat trace lines and circulation pumps.Buildings and pipes move at different rates,causing a stress on pipes and joints.These interfaces must have sufficient flexibility and strength to withstand such stresses.

    The Wastewater Lift Station Replacement project has much to teach about protecting infrastructure from permafrost thawing caused by changing climate or human activities.Often it is not feasible to use refrigerated foundation systems in cold regions,so foundation systems must incorporate insulation to retard thawing.Because frozen ground thaw is inevitable without refrigerated foundations,buildings and their foundations must be able to move independently.

    The Ted Stevens Way Rehabilitation project shows how even the best design practices of previous times are sometimes not adequate.Engineers must constantly re-evaluate design and construction techniques,and this is especially important in an ever-changing environment.

    The issues raised in these projects are not unique to Kotzebue.I hope the lessons learned from these projects can be used in other arctic regions to improve engineered designs and projects.

    I would like to thank the City of Kotzebue Public Works Department for their assistance.I appreciate the support and encouragement from DOWL HKM.I could not have done my work and completed this report without the support and editing of my wife,Rebecca Nichols.

    ASTM International (ASTM),2011.ASTM D2487-11,Standard Practice for Classifications of Soils (Unified Soil Classification System).ASTM,West Conshohocken,PA.

    Golder Associates,2014.Geotechnical Services Report,March 4,2014,Kotzebue Youth Center,Kotzebue,Alaska.Golder Associates,Anchorage,AK.

    Kaplar CW,Linell KA,1966.Description and Classifications of Frozen Soils.Technical Report 150,U.S.Army Materiel Command,Cold Regions Research &Engineering Laboratory,Hanover,NH.

    State of Alaska,2012.Certified Public Road Mileage in Centerline Miles.http://www.dot.alaska.gov/stwdplng/transdata/pub/2012cprmFinal.p df (retrieved December 31,2012).

    University of Alaska-Fairbanks (UAF),2014.Scenarios Network for Alaska &Arctic Planning.http://www.snap.uaf.edu/charts.php (retrieved March 28,2014).

    国产精品久久久久久亚洲av鲁大| 亚洲成a人片在线一区二区| 日韩欧美国产在线观看| 免费在线观看视频国产中文字幕亚洲| 成人av一区二区三区在线看| 宅男免费午夜| 亚洲一码二码三码区别大吗| 中出人妻视频一区二区| 老司机深夜福利视频在线观看| www.自偷自拍.com| 国产精品自产拍在线观看55亚洲| av片东京热男人的天堂| 91老司机精品| 老司机靠b影院| 免费在线观看完整版高清| 亚洲欧美一区二区三区黑人| 特大巨黑吊av在线直播 | 亚洲无线在线观看| 国产极品粉嫩免费观看在线| 午夜免费鲁丝| 日本免费一区二区三区高清不卡| 亚洲精品美女久久av网站| 午夜免费激情av| 亚洲第一电影网av| 在线观看66精品国产| avwww免费| 亚洲七黄色美女视频| 最新在线观看一区二区三区| 老司机深夜福利视频在线观看| 村上凉子中文字幕在线| 亚洲精品中文字幕一二三四区| 最新在线观看一区二区三区| 欧美国产精品va在线观看不卡| 免费看a级黄色片| 成人亚洲精品一区在线观看| 久久久久久亚洲精品国产蜜桃av| 欧美精品啪啪一区二区三区| 两个人免费观看高清视频| 亚洲av熟女| 婷婷丁香在线五月| 色老头精品视频在线观看| 99久久久亚洲精品蜜臀av| 最好的美女福利视频网| 欧美午夜高清在线| 国产三级黄色录像| 久久久久国内视频| 亚洲成a人片在线一区二区| 两个人看的免费小视频| 天天一区二区日本电影三级| 亚洲中文字幕一区二区三区有码在线看 | 国产精品亚洲一级av第二区| 1024视频免费在线观看| 久久中文字幕一级| 少妇裸体淫交视频免费看高清 | 婷婷精品国产亚洲av在线| 国产不卡一卡二| 国产精品久久久久久精品电影 | 成人18禁高潮啪啪吃奶动态图| 精品国产乱子伦一区二区三区| 91在线观看av| 男女床上黄色一级片免费看| av在线天堂中文字幕| a级毛片在线看网站| 欧美乱妇无乱码| 中文字幕精品亚洲无线码一区 | 精品少妇一区二区三区视频日本电影| av天堂在线播放| 日本精品一区二区三区蜜桃| 日本a在线网址| 男人操女人黄网站| 久久精品国产亚洲av高清一级| 无限看片的www在线观看| 精品一区二区三区视频在线观看免费| 一级a爱片免费观看的视频| 亚洲av电影在线进入| 欧美日韩一级在线毛片| 国产精品 欧美亚洲| 最近最新中文字幕大全电影3 | 人妻丰满熟妇av一区二区三区| 免费观看精品视频网站| 人人妻人人看人人澡| 一区二区三区国产精品乱码| 曰老女人黄片| 亚洲精品在线美女| 波多野结衣av一区二区av| 欧美午夜高清在线| 亚洲无线在线观看| 极品教师在线免费播放| a在线观看视频网站| 国产亚洲欧美98| 91老司机精品| 熟妇人妻久久中文字幕3abv| 熟女电影av网| 此物有八面人人有两片| 久久精品国产清高在天天线| 久久中文字幕人妻熟女| 欧美人与性动交α欧美精品济南到| 成人18禁在线播放| 美国免费a级毛片| ponron亚洲| 亚洲欧美精品综合一区二区三区| 久久精品国产99精品国产亚洲性色| 久久草成人影院| 精品国内亚洲2022精品成人| 国产精品亚洲美女久久久| 999久久久国产精品视频| 男女午夜视频在线观看| 午夜免费观看网址| а√天堂www在线а√下载| 18禁黄网站禁片午夜丰满| 制服人妻中文乱码| 亚洲va日本ⅴa欧美va伊人久久| 日韩免费av在线播放| 美女大奶头视频| 成人免费观看视频高清| 久久久久九九精品影院| 精品久久久久久成人av| 日本一本二区三区精品| 欧美在线黄色| 中文字幕另类日韩欧美亚洲嫩草| 国产日本99.免费观看| 免费在线观看日本一区| 久久香蕉精品热| 亚洲第一av免费看| 一夜夜www| 国产国语露脸激情在线看| 真人做人爱边吃奶动态| 人人妻人人澡欧美一区二区| 亚洲精品国产精品久久久不卡| 一本一本综合久久| 日韩欧美在线二视频| 男男h啪啪无遮挡| 黄网站色视频无遮挡免费观看| 久久久久久久久久黄片| 中文字幕另类日韩欧美亚洲嫩草| 麻豆成人午夜福利视频| 国产在线精品亚洲第一网站| 在线观看66精品国产| 日韩成人在线观看一区二区三区| 欧美午夜高清在线| 香蕉丝袜av| 欧美日韩福利视频一区二区| 丰满人妻熟妇乱又伦精品不卡| 国产精品国产高清国产av| 日韩 欧美 亚洲 中文字幕| a级毛片a级免费在线| 女警被强在线播放| 亚洲人成网站高清观看| 国产精品国产高清国产av| 免费看a级黄色片| 啦啦啦 在线观看视频| 在线观看免费日韩欧美大片| 一卡2卡三卡四卡精品乱码亚洲| 色综合婷婷激情| 老熟妇仑乱视频hdxx| 国产精品,欧美在线| 又大又爽又粗| 最新美女视频免费是黄的| 国产精品免费视频内射| 一区福利在线观看| 精品免费久久久久久久清纯| 久久久精品国产亚洲av高清涩受| 国产激情欧美一区二区| 12—13女人毛片做爰片一| 美女午夜性视频免费| or卡值多少钱| 青草久久国产| 亚洲欧美精品综合久久99| 国产1区2区3区精品| 成人特级黄色片久久久久久久| 中文字幕人成人乱码亚洲影| 欧美日韩中文字幕国产精品一区二区三区| 黄片大片在线免费观看| 欧美黄色淫秽网站| 国产精品久久电影中文字幕| 国产1区2区3区精品| 国语自产精品视频在线第100页| 国产精品久久久久久亚洲av鲁大| 国产成年人精品一区二区| 亚洲欧美一区二区三区黑人| 91国产中文字幕| 黑人欧美特级aaaaaa片| 亚洲专区字幕在线| 午夜福利在线在线| 18禁美女被吸乳视频| 国产成人av教育| 免费观看精品视频网站| 日本黄色视频三级网站网址| 亚洲精品色激情综合| 这个男人来自地球电影免费观看| 夜夜夜夜夜久久久久| 久久久久国产精品人妻aⅴ院| 久久国产乱子伦精品免费另类| 亚洲无线在线观看| 男人操女人黄网站| 精品久久久久久久久久免费视频| 亚洲午夜精品一区,二区,三区| 成人三级黄色视频| 一个人免费在线观看的高清视频| 欧美黄色淫秽网站| 成人永久免费在线观看视频| 国产精品影院久久| 51午夜福利影视在线观看| 日韩欧美在线二视频| 黄色成人免费大全| 国产又爽黄色视频| 色综合站精品国产| 最近在线观看免费完整版| 亚洲人成网站高清观看| 妹子高潮喷水视频| 女性生殖器流出的白浆| 国产熟女午夜一区二区三区| 黄色丝袜av网址大全| 亚洲国产欧美网| 午夜免费成人在线视频| 国内毛片毛片毛片毛片毛片| 欧美一级毛片孕妇| 欧美日韩精品网址| 欧美黑人精品巨大| 精品国产乱码久久久久久男人| 一本一本综合久久| 欧美大码av| 婷婷精品国产亚洲av| 亚洲精品一区av在线观看| 哪里可以看免费的av片| 中国美女看黄片| 久久久国产成人精品二区| 日韩大尺度精品在线看网址| 婷婷亚洲欧美| 欧美黑人精品巨大| 免费人成视频x8x8入口观看| 一进一出抽搐动态| www.熟女人妻精品国产| 99久久99久久久精品蜜桃| 侵犯人妻中文字幕一二三四区| 日韩欧美国产一区二区入口| 欧美午夜高清在线| 国产黄色小视频在线观看| 久9热在线精品视频| 99热这里只有精品一区 | 国产精品电影一区二区三区| 亚洲专区国产一区二区| 人人妻人人澡欧美一区二区| 亚洲成av片中文字幕在线观看| 亚洲成av人片免费观看| 精品日产1卡2卡| 黄色毛片三级朝国网站| 女同久久另类99精品国产91| 亚洲美女黄片视频| 老汉色av国产亚洲站长工具| 国产成人精品无人区| 国产日本99.免费观看| 91老司机精品| 成人国产综合亚洲| 99国产精品一区二区三区| 国产午夜福利久久久久久| 精品不卡国产一区二区三区| 亚洲美女黄片视频| 久久久久久国产a免费观看| 嫁个100分男人电影在线观看| 美女扒开内裤让男人捅视频| 欧美乱码精品一区二区三区| 12—13女人毛片做爰片一| 黄色女人牲交| 性色av乱码一区二区三区2| 女警被强在线播放| 亚洲在线自拍视频| 少妇 在线观看| 国产真人三级小视频在线观看| 精品久久久久久久毛片微露脸| 香蕉国产在线看| 伦理电影免费视频| 岛国在线观看网站| 免费看a级黄色片| 国产一区二区在线av高清观看| 禁无遮挡网站| 中文字幕最新亚洲高清| 又黄又爽又免费观看的视频| 欧美av亚洲av综合av国产av| 亚洲无线在线观看| 欧美乱妇无乱码| 日韩欧美国产在线观看| 精品福利观看| 美女午夜性视频免费| 亚洲狠狠婷婷综合久久图片| 精品欧美国产一区二区三| 中文在线观看免费www的网站 | 国产伦在线观看视频一区| 亚洲精品一区av在线观看| 国产精品自产拍在线观看55亚洲| 在线看三级毛片| 麻豆一二三区av精品| 韩国精品一区二区三区| svipshipincom国产片| 亚洲最大成人中文| 国产又爽黄色视频| 俺也久久电影网| 国产99久久九九免费精品| 日韩欧美国产一区二区入口| 香蕉丝袜av| 亚洲国产中文字幕在线视频| 国产精品免费视频内射| 在线免费观看的www视频| 制服诱惑二区| 亚洲av片天天在线观看| 亚洲国产看品久久| 制服诱惑二区| 欧美日本视频| 国内揄拍国产精品人妻在线 | 国产99久久九九免费精品| 婷婷精品国产亚洲av在线| 欧美日韩乱码在线| 午夜成年电影在线免费观看| 一区二区三区激情视频| 90打野战视频偷拍视频| www.精华液| 国产一级毛片七仙女欲春2 | 人人妻,人人澡人人爽秒播| 99在线视频只有这里精品首页| 久久香蕉精品热| av超薄肉色丝袜交足视频| www日本在线高清视频| 国产精品爽爽va在线观看网站 | 精品国产美女av久久久久小说| 欧美日韩亚洲国产一区二区在线观看| 亚洲第一av免费看| 人妻久久中文字幕网| av中文乱码字幕在线| 亚洲人成电影免费在线| 91字幕亚洲| 在线观看日韩欧美| 日韩欧美 国产精品| 国产成人精品久久二区二区91| 欧美一级a爱片免费观看看 | 天堂动漫精品| 非洲黑人性xxxx精品又粗又长| 最新美女视频免费是黄的| 精品人妻1区二区| 在线观看午夜福利视频| 一级毛片女人18水好多| 12—13女人毛片做爰片一| 香蕉丝袜av| 久久国产精品人妻蜜桃| 男人舔奶头视频| 禁无遮挡网站| 国产精品国产高清国产av| 国产av不卡久久| 狂野欧美激情性xxxx| 日韩中文字幕欧美一区二区| 日韩三级视频一区二区三区| 两人在一起打扑克的视频| 变态另类成人亚洲欧美熟女| 亚洲无线在线观看| 日本在线视频免费播放| 亚洲国产欧美日韩在线播放| 欧美激情高清一区二区三区| 男女那种视频在线观看| 婷婷精品国产亚洲av在线| 亚洲五月婷婷丁香| 久久婷婷成人综合色麻豆| 成年人黄色毛片网站| 精品国产超薄肉色丝袜足j| 嫁个100分男人电影在线观看| 熟女电影av网| 国产欧美日韩一区二区精品| 91字幕亚洲| 三级毛片av免费| 97碰自拍视频| 成人国语在线视频| av在线播放免费不卡| 亚洲精品国产一区二区精华液| avwww免费| 欧美中文综合在线视频| 日韩 欧美 亚洲 中文字幕| 色综合欧美亚洲国产小说| 丁香欧美五月| 日本三级黄在线观看| 丰满的人妻完整版| 久久热在线av| 亚洲精品国产精品久久久不卡| 久久 成人 亚洲| 亚洲中文av在线| 国产1区2区3区精品| 亚洲无线在线观看| 久久精品国产综合久久久| 欧美性猛交╳xxx乱大交人| 国产伦一二天堂av在线观看| 免费女性裸体啪啪无遮挡网站| 搞女人的毛片| 日本 欧美在线| 亚洲专区国产一区二区| 午夜精品在线福利| 成人国产一区最新在线观看| 久久久久久亚洲精品国产蜜桃av| 久久国产精品男人的天堂亚洲| 老司机福利观看| 国产主播在线观看一区二区| 国产又黄又爽又无遮挡在线| 亚洲av成人av| 亚洲av成人一区二区三| 久久精品国产亚洲av高清一级| 手机成人av网站| 亚洲国产欧美一区二区综合| 黄网站色视频无遮挡免费观看| 精品欧美国产一区二区三| 午夜视频精品福利| 成年免费大片在线观看| 一a级毛片在线观看| 亚洲国产精品久久男人天堂| 深夜精品福利| 一区二区三区国产精品乱码| 日本免费a在线| 欧美国产精品va在线观看不卡| 亚洲av熟女| 黑人操中国人逼视频| 欧美黄色片欧美黄色片| 国产成人精品无人区| av福利片在线| 日本熟妇午夜| 亚洲激情在线av| 久久伊人香网站| 亚洲国产精品999在线| 精品国产乱码久久久久久男人| 九色国产91popny在线| 男人舔女人下体高潮全视频| 午夜激情福利司机影院| 亚洲中文字幕日韩| 久久精品国产亚洲av高清一级| 成人欧美大片| 岛国视频午夜一区免费看| 夜夜夜夜夜久久久久| 欧美一区二区精品小视频在线| 母亲3免费完整高清在线观看| 9191精品国产免费久久| 国产欧美日韩精品亚洲av| 欧美大码av| 日本 av在线| 久久久久久亚洲精品国产蜜桃av| 国产精品综合久久久久久久免费| 视频在线观看一区二区三区| 两性午夜刺激爽爽歪歪视频在线观看 | 老熟妇乱子伦视频在线观看| 亚洲一区二区三区色噜噜| 中国美女看黄片| 亚洲国产精品合色在线| 黄色视频,在线免费观看| 啦啦啦韩国在线观看视频| 欧美在线黄色| 国产麻豆成人av免费视频| 久久午夜亚洲精品久久| 国产精品乱码一区二三区的特点| 久久久久国内视频| 天天躁夜夜躁狠狠躁躁| 成人国语在线视频| 丰满的人妻完整版| 国产1区2区3区精品| 日本免费a在线| 国产精品1区2区在线观看.| 亚洲五月婷婷丁香| 久久久久亚洲av毛片大全| 91麻豆av在线| 亚洲av美国av| 亚洲国产欧美网| 99国产精品一区二区蜜桃av| 精品国产亚洲在线| 亚洲欧美激情综合另类| 男人舔女人下体高潮全视频| 午夜免费鲁丝| 免费看美女性在线毛片视频| 黑人巨大精品欧美一区二区mp4| 一级作爱视频免费观看| 一级a爱片免费观看的视频| 中文在线观看免费www的网站 | 欧美日韩一级在线毛片| 亚洲欧美日韩无卡精品| 成人18禁高潮啪啪吃奶动态图| 琪琪午夜伦伦电影理论片6080| 免费在线观看视频国产中文字幕亚洲| 俺也久久电影网| 自线自在国产av| 色综合欧美亚洲国产小说| 黄片小视频在线播放| 久久久久久久久中文| 亚洲aⅴ乱码一区二区在线播放 | 久久香蕉国产精品| 天天一区二区日本电影三级| 成年人黄色毛片网站| 婷婷精品国产亚洲av在线| 欧美中文综合在线视频| 久久香蕉国产精品| 美女国产高潮福利片在线看| 久久久国产成人免费| 天天躁狠狠躁夜夜躁狠狠躁| 久久国产精品人妻蜜桃| 极品教师在线免费播放| 国产亚洲av高清不卡| 亚洲成人久久爱视频| 国产真人三级小视频在线观看| 国产精品一区二区免费欧美| 久久中文字幕一级| 日韩中文字幕欧美一区二区| 国产亚洲欧美98| 久久精品aⅴ一区二区三区四区| 怎么达到女性高潮| 亚洲精品中文字幕一二三四区| 亚洲精品在线美女| 国产精品亚洲av一区麻豆| 国产91精品成人一区二区三区| 久久国产亚洲av麻豆专区| 久久精品国产亚洲av高清一级| 精品国产超薄肉色丝袜足j| 桃色一区二区三区在线观看| 亚洲成人国产一区在线观看| 国产亚洲精品一区二区www| 麻豆av在线久日| 欧美+亚洲+日韩+国产| 欧美中文综合在线视频| 成人免费观看视频高清| 国产精品一区二区精品视频观看| 国产麻豆成人av免费视频| 日本 av在线| 国产1区2区3区精品| 人成视频在线观看免费观看| ponron亚洲| 99热这里只有精品一区 | 此物有八面人人有两片| 国内久久婷婷六月综合欲色啪| 琪琪午夜伦伦电影理论片6080| 手机成人av网站| 高清毛片免费观看视频网站| 老汉色∧v一级毛片| 亚洲人成电影免费在线| 婷婷精品国产亚洲av在线| 狂野欧美激情性xxxx| 在线播放国产精品三级| 精品一区二区三区视频在线观看免费| 黄频高清免费视频| 免费在线观看视频国产中文字幕亚洲| 亚洲欧美一区二区三区黑人| 亚洲色图av天堂| 日韩高清综合在线| 国产成人欧美| 精品无人区乱码1区二区| 国产成人系列免费观看| √禁漫天堂资源中文www| 久久中文看片网| 亚洲精品av麻豆狂野| 久久中文字幕人妻熟女| 成人国产综合亚洲| 一本久久中文字幕| 日韩免费av在线播放| 久久久久久亚洲精品国产蜜桃av| 美女午夜性视频免费| 国产成人欧美在线观看| av中文乱码字幕在线| 精品午夜福利视频在线观看一区| www日本黄色视频网| 国产精品久久电影中文字幕| 国产精品久久久人人做人人爽| 在线播放国产精品三级| 国产av一区二区精品久久| 国产又黄又爽又无遮挡在线| 一a级毛片在线观看| 午夜久久久久精精品| 久久中文看片网| 色av中文字幕| 18禁国产床啪视频网站| 免费在线观看日本一区| 黑丝袜美女国产一区| 中文字幕精品免费在线观看视频| 久久精品国产亚洲av高清一级| 国产精品1区2区在线观看.| 成年人黄色毛片网站| 神马国产精品三级电影在线观看 | 最近最新免费中文字幕在线| 亚洲精品中文字幕在线视频| 久久这里只有精品19| 搡老岳熟女国产| 伦理电影免费视频| 久久精品影院6| 真人做人爱边吃奶动态| 国产亚洲精品久久久久5区| 亚洲精品一卡2卡三卡4卡5卡| 1024手机看黄色片| 午夜影院日韩av| 亚洲精品国产一区二区精华液| 久久久久久久久久黄片| 色播在线永久视频| 免费人成视频x8x8入口观看| 国产99白浆流出| 免费在线观看亚洲国产| av欧美777| 亚洲在线自拍视频| 女性生殖器流出的白浆| 搞女人的毛片| 日韩高清综合在线| 久久久久久人人人人人| 午夜老司机福利片| 99re在线观看精品视频| 欧美大码av| 久久久久久国产a免费观看| 久久久久免费精品人妻一区二区 | 高清在线国产一区| 久久久水蜜桃国产精品网| 99久久99久久久精品蜜桃| 一级片免费观看大全| 国产视频一区二区在线看| 国产成人av教育| 日韩 欧美 亚洲 中文字幕| 欧美久久黑人一区二区| av有码第一页| 色婷婷久久久亚洲欧美| 国产精华一区二区三区| 神马国产精品三级电影在线观看 | 怎么达到女性高潮|