• <tr id="yyy80"></tr>
  • <sup id="yyy80"></sup>
  • <tfoot id="yyy80"><noscript id="yyy80"></noscript></tfoot>
  • 99热精品在线国产_美女午夜性视频免费_国产精品国产高清国产av_av欧美777_自拍偷自拍亚洲精品老妇_亚洲熟女精品中文字幕_www日本黄色视频网_国产精品野战在线观看 ?

    Cost Estimate and Input Energy of Floor Systems in Low Seismic Regions

    2022-08-24 03:26:02SayedMahmoudandAlaaSalman
    Computers Materials&Continua 2022年5期

    Sayed Mahmoud and Alaa Salman

    Department of Civil and Construction Engineering,College of Engineering,Imam Abdulrahman Bin Faisal University,P.O.Box 1982,Dammam 31441,Kingdom of Saudi Arabia

    Abstract: Reinforced concrete (RC) as a material is most commonly used for buildings construction.Several floor systems are available following the structural and architectural requirements.The current research study provides cost and input energy comparisons of RC office buildings of different floor systems.Conventional solid,ribbed,flat plate and flat slab systems are considered in the study.Building models in three-dimensional using extended threedimensional analysis of building systems (ETABS) and in two-dimensional using slab analysis by the finite element (SAFE) are developed for analysis purposes.Analysis and design using both software packages and manual calculations are employed to obtain the optimum sections and reinforcements to fit cities of low seismic intensities for all the considered building systems.Two ground motion records of low peak ground acceleration(PGA)levels are used to excite the models to measure the input energies.Uniformat cost estimating system is adopted to categorize building components according to 12 divisions.Also,Microsoft(MS)Project is utilized to identify the construction cost and duration of each building system.The study shows that floor system significantly causes changes in the input energy to structures.In addition,the slight increase in the PGA increases the amount of input energy particularly flat plate system.Estimated cost of the flat plate system that the flat slab system is of higher value as compared to ribbed and conventional slab systems.The use of drop panels increases this value as well.Moreover, the estimated cost of the ribbed slab system exceeds that of conventional system.

    Keywords: Uniformat system;office buildings;floor systems;energy response;cost estimating

    1 Introduction

    Currently, RC is considered as one of the most commonly used materials in construction.It is extensively and widely used in performing different engineering projects such as buildings, bridges and dams.Such a wide use in engineering applications is due to its relatively low cost in comparison with the use of other materials,particularly steel.The importance of cost,as one of the main factors that influence construction projects, is continuously increasing.Nowadays, most project managers call for an accurate estimation of the cost of the construction project during the design phase as guidance for the selection of the most suitable design system.Building structures are designed not only to achieve safety aspects but also to consider the economic aspects as well.Construction of RC buildings is mainly dependent on the availability of the materials required for construction process.The level of construction technology and the use of necessary services such as elevators are other factors that influence the building construction.

    2 Related Works

    Kose and Sirikci [1] performed a comparative study between RC concrete and steel structures having similar plan dimensions.Both structural design and cost of the structural elements were calculated and compared with each other.STA4CAD and SAP2000 software packages were used to perform the design and analysis of concrete and steel buildings respectively.Although the study indicated that the cost of steel structure is higher than that of concrete structure, the time required for completion of concrete structures is about three times the completion time required for steel structures.Project information availability together with understanding the scope of the works enables engineers to accurately estimate the expected total costs of the project [2,3].The accurate cost of building structural elements requires the definition of the correct applied load to effectively distribute the required cross-sectional dimensions to be able to bear such loads and effectively reduce costs[4].Guerra and Kiousis[5]investigated the effect of selecting the optimum sizing and reinforcements for horizontal and vertical structural elements in terms of beams and columns respectively on the cost of multi-bay and multistory RC structures.Optimum design of beam and column sections incorporates ideal stiffness correlation which results in cost savings over typical-practice design solutions.The reinforced concrete slab serves as the horizontal unit to mainly support the gravity load.In addition,the slab also forms an integral part of structural frames to resist lateral loads.Several research-works seek the best performance,cost,and safety of buildings.Zekirija and Isak[6]utilized an RC building to perform a comparative study between a waffle and solid slab systems;based on the optimal solution of the economic structural system, the satisfactory safety level, and the performance of a building.On the other hand, Halkiyo et al., [7] analyzed and designed an RC building with solid and ribbed slab systems under gravitational and lateral loads.The obtained results from the comparison showed that buildings with solid slabs requires fewer materials in terms of concrete and steel by about 5%as compared to buildings with ribbed slab systems.Nassar and Al-Qasem developed a 3D model to analyze and design different types of floor systems in terms of one-and two-way ribbed slabs, solid slab,and flat plate using ETABS.Following the analysis and design procedures,cost estimation of the designed systems was performed for each of the considered systems[8].From energy side,in the last few decades,several research studies investigated the principle of using the energy-based methods as a reliable technique in comparison with utilized conventional methods[9,10].In the field of earthquake engineering, collapse of a structure due to exceedance of energy demand over the amount provided by the structure itself was extensively investigated[11–13].In addition,energy-based design methods require reliable estimations of input energy to be considered as an influential parameter in the seismic design of building structures [14].Apparently, minimizing the amount of input energy enhances the building safety.Input energy based seismic design for a four-story building hit by different ground motion records has been investigated through computation of forces and energy showing that the energy approach is relatively more consistent than the base shear approach[15].

    The current study investigates the variation of input energy and cost of low-rise RC office buildings with different floor systems.The utilized herein systems are,conventional solid slab,one-way ribbed slab,flat plate and flat slab.The commercial software ETABS is used to build the models considering the designed RC sections following the ACI-318-14 design code.The developed models are excited using two real earthquake records of low PGA levels to measure the variations in input energies with the floor systems.Costs of sub-and super-structural elements are calculated.Cost analysis based on the calculated cost data for materials;concrete and steel reinforcements,formworks,labors,...etc.is also performed.Project duration in days for the four designed systems is provided as well.

    3 Office Building Models

    The selected office building is square in plan and consists of five panels of equal spacings of 6.0 m in both directions,as shown in Fig.1.In elevation,the building is of four stories of total height equal to 12.0 m.Two-way floor systems with a solid slab,flat plate,and flat slab systems are used to perform the current study.Besides,a one-way slab is also used in terms of the ribbed slab system.In order to use the available structural software packages to develop the model,the initial concrete dimensions of the structural elements are calculated according to the design code requirements.

    For the solid slab systems,the slab thickness,and beam dimensions is firstly calculated to satisfy deflection requirements.The thickness of the flat plate, flat slab and drop panel are also calculated according to a similar procedure.The definition of the ribbed slab requires dimensions of ribs, the thickness of compression slab,drop and hidden beams dimensions.The beams of the solid slabs and ribbed slabs are distributed as perimetrical and intermediate.The internal and external columns are uniformly distributed within the axes of the building.An isolated footing system beneath columns is used to carry the applied vertical loads from the structure weight itself and the other dead and live loads applied to the office buildings.The developed models require the used material properties and the values of the gravitational loads in terms of the dead and live loads as well.The used live load value is 2.4kN/m2.The equivalent flooring cover over slabs is 15kN/m2.The equivalent wall load distributed over the flat slab and flat plate is taken as 3.0kN/m2.

    4 Computer Models

    The office building considered here is situated in Dammam,a major city in the Eastern Province of KSA.The plan of the office building covers an area of around 900 m2.The developed building models are skeleton-type with rigid-cast in-situ RC columns, slabs, drop, and hidden beams.3D models of the office buildings are created using the ETABS software structural package as shown in Fig.2.Beams and columns are modeled as frame elements.Shear elements are utilized to model the different types of slabs with calculated different thicknesses.The drop panels are also modeled as shell elements.Foundation is modeled as fixed supports.The utilized frame and shell elements are divided into sub-elements of finite sizes for accuracy purposes.The used concrete density and compressive strength to model the buildings areγc=25 kN/m3and fc′= 28 N/mm2.The used steel is of yield strength of 420 N/mm2.The employed Young’s modulus of concrete is calculated in terms of the used compressive strength as 4700Similarly,the utilized Young’s modulus of steel is 200,000 MPa.For seismic design,the response modification factor has been set to be 4.The maximum spectral response acceleration at a short period of 0.2 sec Ss and a period of 1 sec S1 for Dammam city are taken as 0.083 and 0.03 respectively as per the ASCE-7–16.In the performed analysis,a modal damping ratio of 5%is assumed for all the considered modes of analysis.

    Figure 1:Two-dimensional(2D)models of the used floor systems of the considered office building in terms of two-way and one-way slab systems

    5 Earthquake Modelling

    The developed building models with different floor systems shown in Fig.2 were excited by two earthquake records.One of the selected records is 1995 Aqabq earthquake which occurred in the central part of the Gulf of Aqaba and recorded at EILAT station 0616.The second one is from Northridge earthquake records occurred on 1994 in the San Fernando Valley region of the city of Los Angeles and recorded at USC station 90070.The selected ground motions for conducting the seismic analysis are of PGAs 0.097 g and 0.11 g to ensure to fit regions of low seismic intensity.Fig.3 presents the acceleration time histories of the selected two ground motions.The considered time durations for performing the simulation analysis are 60 and 35 s for the Aqaba and Northridge respectively.These records are selected from PEER Strong Motion Database developed by University of Berkeley(http://peer.berkeley.edu/smcat/).

    Figure 2:Developed three-dimensional(3D)models of the used floor systems of the considered office building in terms of two-way and one-way slab systems

    Figure 3:Acceleration time histories for the Aqaba and Northridge ground motion records

    6 Designed Sections

    Following the analyses of the considered structural models,straining actions in terms of bending moments,shear forces and axial forces are obtained considering gravitational and seismic load actions of low seismic regions.The dimensions of the concrete sections and the required steel bars are calculated based on the obtained straining actions following load combinations recommended by the design codes.The obtained dimensions and reinforcements are presented in the form of Tabs.1–4 and Figs.4–7.

    Figure 4:Cross-sections of the projected beams carrying the solid slab system.

    Figure 5:Cross-sections in ribs carrying the hollow block slab system

    Figure 6:Cross-sections in hidden beam carrying the hollow block slab system at support and mid-span

    Figure 7:Cross-sections in the drop panel of the flat slab system

    Table 1:Columns dimensions and reinforcements

    Table 2:Foundations dimensions and reinforcements

    7 Input Energy

    To get some insight into how the building’s floor systems affect the input energy to the structure subjected to seismic actions,structural building models including solid slab,hollow block,flat plate and flat slab systems are developed and excited by two different excitation records of low PGA.The total input energy to each of the considered models is calculated using the considered accelerograms of Aqaba(1995)and Northridge(1994)records that represent PGA of almost 0.1 g.Figs.8 and 9 show the time-history curves of the building’s input energy for the considered different floor systems under the Aqaba and Northridge earthquake records.As can be seen in the figures,the obtained input energy curves under Aqaba records show almost similar trends as those time-history curves under Northridge records.However,the floor system significantly influences the induced input energy curves under the same ground excitation records.For all the considered floor systems,the input energy response curves increase till reaching almost unchanged values after passing the interval of PGA of the records till the end of the applied ground motions.Incorporating a flat plate as a flooring system significantly increases the input energy compared with the other flooring systems as can be observed under the considered ground motion records.On the other hand,the solid slab system provides the lowest input energy curve as compared to the other systems.From percentage point of view,the flat plate system increases the input energy by about 51%, 63% and 67% with respect to hollow block, flat slab and solid slab systems respectively under Aqaba records.For Northridge records used as excitation, the corresponding percentages of increase are 66%, 79% and 83%.Theses calculated percentage results clearly indicate that the use of horizontal elements in terms of drop beams, hidden beams or even drop panels contributes substantially in decreasing the input energy response under seismic excitation records.This can be due to the role of these provided horizontal structural elements in improving the stiffness of the designed buildings and attenuating the input energy response to the building structures.It seems that,the intensity of the seismic records influences the induced input energy to structure where Northridge records of PGA equals 0.11 g provide higher input energy to building models of different floor systems compared with Aqaba records of PGA equals 0.0967 g.

    Table 3:Projected beams dimensions and reinforcements

    Table 4:Projected and hidden beams dimensions and reinforcements

    Table 4:Continued

    Figure 8:Input energy curves for low-rise buildings with different floor systems subjected to Aqaba earthquake

    8 Cost Estimating Systems

    When more than one alternative is available to be selected, the cost is a major factor of the selection.Other factors(such as quality,duration,service life,etc.)are directly related to project costs.In either case,the final cost value is a key of the owner to decide.In parallel,the comparison of several alternatives must be done with respect to the project’s stage.The complete design details with the required resources and the rate at low expected risk can be used to complete an accurate cost estimate,and the Master Format(MF)system is suitable for use in this situation.However,in the early stage of the project development,Uniformat(UF)cost estimating system is suitable to be utilized instead of using Master Format(MF)system due to the following[16]:

    i.Limited resources and detailed design package.

    ii.It only includes 12 divisions,while MF requires 16 or 50 divisions.

    iii.It helps the specialist to select the alternatives based on the essential cost information.

    Figure 9:Input energy curves for low-rise buildings with different floor systems subjected to Northridge earthquake

    Hence,the application of UF is easier to identify the differences and similarities between the design systems(in this case;conventional solid,ribbed,flat plate and flat slab systems).The UF 12 divisions and their subdivisions are listed in Tab.5.The 12 divisions and their subdivisions are considered to estimate the cost of the building with respect to each designed floor system.Each division and subdivision are carefully checked in terms of the differences and similarities between the four designed systems.

    Table 5:Uniformat elemental classifications

    Table 5:Continued

    9 Cost Estimating Process

    Tab.6 depicts the cost of estimating divisions using the UF system.It shows the similar and different divisions of the four design systems.

    Table 6:Similarities and differences of the four design systems

    Amongst the twelve divisions, only Foundation “division#1” and Superstructure “division#3”have different costs due to the nature of the design, which has been identified in the above sections.Therefore, the total cost of a building can be estimated one time for other divisions, and individual calculations are required for the Foundation and the Superstructure of each design system.Data collected regarding the cost rate of required resources, productivity, duration, and logical relations among project activities of the four systems had been collected from several local Saudi companies that are in Dammam (Saudi Arabia).Using MS Project, total cost and duration are determined accordingly.

    MS Project is used to determine the total cost and duration of the construction of the four building systems.The presented tables and figures in the previous section are used to calculate the costs of steel bars,formwork,and concrete in the designed structural elements such as slabs,beams,columns,and foundations.Fig.10 presents the estimated cost of sub-and super-structural elements of the considered different floor systems.As can be seen from the figure that the estimated cost for the sub-structure elements of the flat slab and the flat plate is almost identical.Similarly,the difference between the costs of sub-structural elements of solid and ribbed slabs show insignificant variation.From a percentage point of view,the cost of the sub-structure elements of the flat plate and the flat slab systems exceeds the corresponding costs of the solid and ribbed slab systems by about 33%.The calculated percentages of increase of the super-structural elements of flat plate and flat slab systems with respect to the solid slab system are about 29%and 34%respectively.The cost of the super-structural elements of the ribbed slab exceeds the one associated with the solid slab by about 7%.

    Figure 10:Cost (SAR) of sub- and super-structure elements in terms of concrete and steel for the considered different floor systems

    Fig.11 presents the total cost of steel and concrete for the considered flooring system.It is clear from the figure that, the flat slab system provides the highest cost compared with the other floor systems.On the other hand,the solid slab system shows the lowest cost value amongst the other systems considered in the study.Contrasted to the conventional solid slab system, the estimated cost of the concrete and steel of the flat slab system excels by about 35%.The flat plate shows a percentage increase of about 30%.This 5%decrease compared to the flat slab can be due to the removal of the drop panel portion.The ribbed slab floor system provides a percentage of increase of about 10% compared to the sloid slab floor system.This can be due to the use of blocks in the compression zone instead of concrete.The blocks are considered as a cheap nonstructural element compared with the concrete.

    Figure 11:Total cost(SAR)of the considered different floor systems in terms of concrete and steel

    Fig.12 identifies the total costs of the building using the four designed systems.Flat Slab has the maximum cost due to the foundation and superstructure costs.On the other hand,solid slab system provides the lowest total cost among all the considered systems.The flat slab system increases the total cost by about 15%compared with the solid slab one.The other two systems namely;one-way ribbed slab and flat plate systems provide total costs that exceed the conventional solid slab by about 3%and 10%,respectively.the influence of the use of drop panels on the total cost can be identified through the calculated percentage of increase of 4.5%of total cost of flat slab compared to flat plate systems.These presented total cost values and percentages clearly indicate that changes in the floor system have a significant impact on changes to RC buildings total costs.

    Figure 12:Total Cost(SAR)of a building using the four different designed systems

    Fig.13 depicts the duration required of each system.It is shown clearly that the duration of the solid slab is the maximum between the others.It is slightly more than other designed systems.It is 2%more than Flat Slab,3%more than Flat plate,and 6%more than One-Way Hollow Block.In general,the previous percentages are not considered sufficient for the selection; especially, because it can be changed when the productivity of the different activities can be changed accordingly.Also, a large number of stories affects the above percentages in non-linear relation(which is out of the scope of this research).

    Figure 13:Project duration(day)using the four designed systems

    10 Conclusions

    Four RC buildings of four stories and different slab systems were designed to gravitational and seismic loads to serve as office buildings.Solid, hollow-block, flat plate and flat slab systems were selected as different alternatives as flooring systems.The developed building models were subjected to Aqaba and Northridge earthquake records of low PGA level.The comparison is carried out concerning the input energy,cost and duration of the construction of the building models.Uniformat cost estimating system is selected in this manner due to its suitability in the early stage of the project.Amongst 12 divisions,foundation and superstructure are considered the baseline of the comparison.The study shows that the cost of the flat plate and flat slab systems is the highest compared to ribbed and conventional slab systems Moreover,the estimated cost of the flat plate system is higher by about 30% as compared to a solid slab system.The use of drop panels increases this value to about 35%.On the other hand, the estimated cost of the ribbed slab system exceeds the estimated cost of the conventional system by about 10%.As for,the duration of the four slab systems,slight differences are observed.From energy view point, variations of floor systems can cause substantial changes in the input energy particularly for the flat plate one where the absence of horizontal elements in terms of drop and hidden beams or drop panels increases significantly the amount of total input energy to the structure.In addition,the slight increase in the PGA of one of the used records led to an increase in the amount of imparted input energy to buildings regardless the type floor.

    Acknowledgement:We thanks IAU to give us the opportunity for this research work.

    Funding Statement:The authors received no specific funding for this study.

    Conflicts of Interest:The authors declare that they have no conflicts of interest to report regarding the present study.

    色尼玛亚洲综合影院| 亚洲自偷自拍图片 自拍| 久久午夜亚洲精品久久| 午夜亚洲福利在线播放| 精品免费久久久久久久清纯| 很黄的视频免费| 久久午夜综合久久蜜桃| 欧美成人午夜精品| 少妇 在线观看| 亚洲成人免费av在线播放| 无遮挡黄片免费观看| 亚洲av成人av| 午夜精品在线福利| 国产在线精品亚洲第一网站| 一区二区三区激情视频| 亚洲成人久久性| 国产欧美日韩一区二区三| 免费高清视频大片| 超色免费av| 国产成人av教育| 久久人妻av系列| 岛国在线观看网站| 巨乳人妻的诱惑在线观看| 国产一区二区激情短视频| 黄片大片在线免费观看| 老司机午夜十八禁免费视频| 在线观看舔阴道视频| 国产精品综合久久久久久久免费 | 久久天堂一区二区三区四区| 丝袜人妻中文字幕| 一进一出抽搐动态| 人人妻人人添人人爽欧美一区卜| 悠悠久久av| 免费在线观看完整版高清| 99国产精品一区二区蜜桃av| 天天添夜夜摸| 午夜免费观看网址| 天天躁狠狠躁夜夜躁狠狠躁| 欧美+亚洲+日韩+国产| 超碰97精品在线观看| 在线观看www视频免费| 97人妻天天添夜夜摸| 女性被躁到高潮视频| 老司机深夜福利视频在线观看| 久久 成人 亚洲| 色播在线永久视频| 丝袜美足系列| 欧美乱码精品一区二区三区| 不卡av一区二区三区| 亚洲午夜精品一区,二区,三区| 亚洲色图av天堂| 一区二区三区激情视频| 欧美+亚洲+日韩+国产| 亚洲国产精品999在线| 黄色女人牲交| 久久亚洲真实| 搡老乐熟女国产| 欧美日韩精品网址| 男女做爰动态图高潮gif福利片 | 国产成人影院久久av| 国产精品久久电影中文字幕| 国产亚洲av高清不卡| 国产精品国产av在线观看| 久久亚洲真实| 日韩一卡2卡3卡4卡2021年| 国产高清国产精品国产三级| 精品无人区乱码1区二区| 91国产中文字幕| 久久人妻福利社区极品人妻图片| 国产免费现黄频在线看| 精品久久久久久久毛片微露脸| 久久精品91无色码中文字幕| 一区在线观看完整版| 国产精品美女特级片免费视频播放器 | 国产精品免费一区二区三区在线| 日韩三级视频一区二区三区| 少妇裸体淫交视频免费看高清 | 热re99久久精品国产66热6| 亚洲av美国av| 制服诱惑二区| 国产99久久九九免费精品| 三上悠亚av全集在线观看| 国产欧美日韩精品亚洲av| 成人手机av| av天堂久久9| 精品少妇一区二区三区视频日本电影| 美女高潮喷水抽搐中文字幕| 18禁黄网站禁片午夜丰满| 久久 成人 亚洲| 亚洲 国产 在线| 欧美日韩中文字幕国产精品一区二区三区 | 亚洲精品一卡2卡三卡4卡5卡| 久热爱精品视频在线9| 在线观看舔阴道视频| 中文字幕高清在线视频| 热99国产精品久久久久久7| 国产精品久久久久成人av| 色播在线永久视频| 亚洲av五月六月丁香网| 亚洲欧美日韩另类电影网站| 自线自在国产av| 亚洲精品一二三| 黄频高清免费视频| 99久久国产精品久久久| 久久久久久亚洲精品国产蜜桃av| 久久香蕉国产精品| 精品免费久久久久久久清纯| 成年人黄色毛片网站| √禁漫天堂资源中文www| 一本综合久久免费| 99久久久亚洲精品蜜臀av| 在线免费观看的www视频| 亚洲一码二码三码区别大吗| 很黄的视频免费| 久久 成人 亚洲| 国产成人欧美| 成人国产一区最新在线观看| 国产精品香港三级国产av潘金莲| 中文字幕人妻丝袜制服| 人人妻人人澡人人看| av天堂久久9| 成年版毛片免费区| 黑人巨大精品欧美一区二区蜜桃| 婷婷六月久久综合丁香| 国产成人精品在线电影| 日韩高清综合在线| www国产在线视频色| 窝窝影院91人妻| 色婷婷久久久亚洲欧美| 国产无遮挡羞羞视频在线观看| 国产欧美日韩一区二区三区在线| 精品国产一区二区三区四区第35| 欧美激情 高清一区二区三区| 黄色视频,在线免费观看| www.www免费av| 日本一区二区免费在线视频| 久久久久精品国产欧美久久久| 在线观看舔阴道视频| 亚洲 欧美 日韩 在线 免费| 午夜影院日韩av| 十八禁网站免费在线| 亚洲国产精品999在线| 三上悠亚av全集在线观看| 一进一出好大好爽视频| 天堂√8在线中文| 天堂动漫精品| 欧美黄色片欧美黄色片| 午夜福利在线免费观看网站| 中亚洲国语对白在线视频| 三级毛片av免费| 成人影院久久| 黑人操中国人逼视频| 9热在线视频观看99| 亚洲专区中文字幕在线| 日韩精品免费视频一区二区三区| 久久精品人人爽人人爽视色| 亚洲一区二区三区欧美精品| 香蕉国产在线看| e午夜精品久久久久久久| 麻豆一二三区av精品| 亚洲欧美日韩另类电影网站| 国产欧美日韩一区二区三| 亚洲av第一区精品v没综合| 高清毛片免费观看视频网站 | 久久久国产一区二区| 一本大道久久a久久精品| 日韩精品青青久久久久久| 亚洲精品国产精品久久久不卡| 18美女黄网站色大片免费观看| 亚洲免费av在线视频| av国产精品久久久久影院| 亚洲五月色婷婷综合| 亚洲国产毛片av蜜桃av| 国产一区二区在线av高清观看| av超薄肉色丝袜交足视频| 精品熟女少妇八av免费久了| 久久伊人香网站| 一级毛片精品| 色婷婷久久久亚洲欧美| 亚洲成人久久性| 亚洲第一青青草原| 国产国语露脸激情在线看| 高清欧美精品videossex| 一进一出好大好爽视频| 国产97色在线日韩免费| 亚洲精品成人av观看孕妇| 日韩欧美三级三区| 老司机午夜十八禁免费视频| 一区二区三区激情视频| 免费高清在线观看日韩| 国产人伦9x9x在线观看| 国产亚洲精品第一综合不卡| 欧美精品一区二区免费开放| 欧美人与性动交α欧美软件| 久久久水蜜桃国产精品网| 亚洲免费av在线视频| 国产精品免费视频内射| 欧美日韩亚洲综合一区二区三区_| 国产成人啪精品午夜网站| 黄色 视频免费看| 99精国产麻豆久久婷婷| 欧美大码av| 三上悠亚av全集在线观看| 国产伦人伦偷精品视频| 国产激情欧美一区二区| 男女做爰动态图高潮gif福利片 | 国产国语露脸激情在线看| 757午夜福利合集在线观看| 午夜免费观看网址| 制服诱惑二区| 欧美日韩av久久| 91精品三级在线观看| 女人精品久久久久毛片| 免费在线观看影片大全网站| 性色av乱码一区二区三区2| 国产aⅴ精品一区二区三区波| 乱人伦中国视频| 麻豆av在线久日| 中文字幕高清在线视频| 91精品三级在线观看| 亚洲欧美精品综合久久99| 色哟哟哟哟哟哟| 18禁美女被吸乳视频| 午夜免费鲁丝| 婷婷六月久久综合丁香| 精品久久蜜臀av无| 欧美+亚洲+日韩+国产| 麻豆av在线久日| 韩国av一区二区三区四区| 精品乱码久久久久久99久播| 熟女少妇亚洲综合色aaa.| 一进一出抽搐gif免费好疼 | 国产高清视频在线播放一区| 午夜免费激情av| 国产成+人综合+亚洲专区| 欧美黄色片欧美黄色片| 黑人猛操日本美女一级片| 乱人伦中国视频| 男人的好看免费观看在线视频 | 一级,二级,三级黄色视频| 中文字幕av电影在线播放| 欧美黑人精品巨大| 色婷婷av一区二区三区视频| 午夜视频精品福利| 午夜免费激情av| 国产免费男女视频| 国产精品爽爽va在线观看网站 | 中亚洲国语对白在线视频| 精品国产国语对白av| a级片在线免费高清观看视频| 国产区一区二久久| 日韩欧美国产一区二区入口| 国产黄色免费在线视频| 美女福利国产在线| 97碰自拍视频| av福利片在线| 亚洲三区欧美一区| 亚洲国产欧美一区二区综合| 亚洲精品av麻豆狂野| 久久久久亚洲av毛片大全| 天堂中文最新版在线下载| 亚洲欧美精品综合久久99| 欧美性长视频在线观看| 国产一区二区三区视频了| 国产精品香港三级国产av潘金莲| 嫁个100分男人电影在线观看| 亚洲色图综合在线观看| 国产一区在线观看成人免费| 欧美乱妇无乱码| 色老头精品视频在线观看| videosex国产| 丰满人妻熟妇乱又伦精品不卡| 老汉色∧v一级毛片| 国产精品久久久久久人妻精品电影| 精品第一国产精品| www.自偷自拍.com| 免费搜索国产男女视频| 亚洲男人的天堂狠狠| 欧美日韩国产mv在线观看视频| 老熟妇仑乱视频hdxx| 午夜免费观看网址| 国产精品 国内视频| 久久久久国产一级毛片高清牌| 在线国产一区二区在线| 日韩精品青青久久久久久| 精品乱码久久久久久99久播| 在线观看免费午夜福利视频| 一本综合久久免费| 黄片小视频在线播放| 亚洲欧美激情综合另类| 精品国内亚洲2022精品成人| 国产精品香港三级国产av潘金莲| 欧美丝袜亚洲另类 | a级毛片在线看网站| 国产成人精品久久二区二区免费| 免费av毛片视频| 精品久久久久久电影网| 日韩欧美国产一区二区入口| 中国美女看黄片| 国产成人免费无遮挡视频| 免费少妇av软件| 国产国语露脸激情在线看| 老司机在亚洲福利影院| 久久久久久久午夜电影 | 亚洲,欧美精品.| 精品熟女少妇八av免费久了| 国产视频一区二区在线看| 亚洲av第一区精品v没综合| 免费观看精品视频网站| 久久狼人影院| 久久久久久亚洲精品国产蜜桃av| 丝袜在线中文字幕| 一区在线观看完整版| 亚洲精品成人av观看孕妇| 淫秽高清视频在线观看| 亚洲中文日韩欧美视频| 少妇被粗大的猛进出69影院| 免费久久久久久久精品成人欧美视频| 激情视频va一区二区三区| 中亚洲国语对白在线视频| 亚洲午夜理论影院| 国产精品日韩av在线免费观看 | 久久国产精品人妻蜜桃| 91麻豆精品激情在线观看国产 | 日韩 欧美 亚洲 中文字幕| 波多野结衣一区麻豆| 亚洲三区欧美一区| 欧美日韩乱码在线| 国产伦一二天堂av在线观看| 国产成年人精品一区二区 | 国产深夜福利视频在线观看| 色综合站精品国产| 一级片'在线观看视频| 乱人伦中国视频| 成在线人永久免费视频| 色综合欧美亚洲国产小说| 亚洲全国av大片| av超薄肉色丝袜交足视频| 美女国产高潮福利片在线看| 国产一区二区三区在线臀色熟女 | 国产一区在线观看成人免费| 无人区码免费观看不卡| 9热在线视频观看99| 日本a在线网址| 久久青草综合色| av在线播放免费不卡| 久久久久久亚洲精品国产蜜桃av| 欧美一区二区精品小视频在线| 国产精品久久久久久人妻精品电影| 久久精品亚洲熟妇少妇任你| 日韩三级视频一区二区三区| 麻豆一二三区av精品| 国产一区二区在线av高清观看| 成人18禁在线播放| 亚洲精品一二三| 99久久综合精品五月天人人| 男女午夜视频在线观看| 精品熟女少妇八av免费久了| 欧美不卡视频在线免费观看 | 视频在线观看一区二区三区| 亚洲精品成人av观看孕妇| 久久精品成人免费网站| 精品久久久精品久久久| 琪琪午夜伦伦电影理论片6080| 国产精品电影一区二区三区| 88av欧美| 免费av中文字幕在线| 国产主播在线观看一区二区| 久久久久国产一级毛片高清牌| 国产成人系列免费观看| 亚洲欧美激情综合另类| 免费在线观看影片大全网站| 久久久久久大精品| 1024视频免费在线观看| 亚洲人成77777在线视频| 69精品国产乱码久久久| 国产精品电影一区二区三区| 身体一侧抽搐| 亚洲中文av在线| 欧美中文综合在线视频| 精品一区二区三区视频在线观看免费 | 中文欧美无线码| 精品久久久精品久久久| 久久久水蜜桃国产精品网| svipshipincom国产片| 涩涩av久久男人的天堂| 午夜精品久久久久久毛片777| 亚洲av五月六月丁香网| 欧美日韩乱码在线| 精品久久久精品久久久| 在线视频色国产色| 欧美精品一区二区免费开放| 国产精品98久久久久久宅男小说| 亚洲狠狠婷婷综合久久图片| 免费观看精品视频网站| 黄片小视频在线播放| 国产日韩一区二区三区精品不卡| 午夜a级毛片| 日韩一卡2卡3卡4卡2021年| 欧美日韩黄片免| 欧美在线一区亚洲| 午夜福利影视在线免费观看| 免费观看人在逋| 可以在线观看毛片的网站| 国产欧美日韩一区二区三| 女人被狂操c到高潮| 免费在线观看视频国产中文字幕亚洲| 黄色片一级片一级黄色片| 久久人妻av系列| 精品国产超薄肉色丝袜足j| 黑丝袜美女国产一区| 黄色a级毛片大全视频| www.999成人在线观看| 法律面前人人平等表现在哪些方面| 涩涩av久久男人的天堂| 在线观看免费午夜福利视频| 国产深夜福利视频在线观看| 操出白浆在线播放| 精品久久久久久,| 三级毛片av免费| 老汉色∧v一级毛片| www.www免费av| 精品国产亚洲在线| 久久久久九九精品影院| 精品无人区乱码1区二区| 在线观看66精品国产| 欧美激情极品国产一区二区三区| 国产亚洲欧美98| 亚洲五月色婷婷综合| 欧美日韩乱码在线| 国产成人精品久久二区二区免费| 99re在线观看精品视频| tocl精华| 老司机亚洲免费影院| 亚洲熟妇中文字幕五十中出 | 看黄色毛片网站| av欧美777| 欧美日韩视频精品一区| 一本大道久久a久久精品| 宅男免费午夜| 亚洲成a人片在线一区二区| 女人爽到高潮嗷嗷叫在线视频| 亚洲成av片中文字幕在线观看| 最新在线观看一区二区三区| 国产精品免费视频内射| 90打野战视频偷拍视频| 在线播放国产精品三级| 亚洲少妇的诱惑av| 很黄的视频免费| 亚洲专区中文字幕在线| 欧美一级毛片孕妇| 亚洲成人精品中文字幕电影 | 无限看片的www在线观看| 波多野结衣高清无吗| 99热国产这里只有精品6| 日本五十路高清| 一级片'在线观看视频| 91成人精品电影| 免费不卡黄色视频| 动漫黄色视频在线观看| 男人操女人黄网站| 新久久久久国产一级毛片| 在线观看免费午夜福利视频| 欧美+亚洲+日韩+国产| 狂野欧美激情性xxxx| 国产精品久久久av美女十八| 国产aⅴ精品一区二区三区波| 国产一卡二卡三卡精品| 丝袜美足系列| 国产精品自产拍在线观看55亚洲| 欧美精品亚洲一区二区| a级毛片在线看网站| 亚洲五月色婷婷综合| 中亚洲国语对白在线视频| 国产精品一区二区精品视频观看| 亚洲国产精品一区二区三区在线| xxx96com| 国产真人三级小视频在线观看| 狂野欧美激情性xxxx| 国产亚洲精品第一综合不卡| 首页视频小说图片口味搜索| 巨乳人妻的诱惑在线观看| av天堂久久9| 国产一卡二卡三卡精品| 老司机福利观看| 欧美老熟妇乱子伦牲交| 欧美大码av| 无遮挡黄片免费观看| 精品日产1卡2卡| 成人三级黄色视频| 大码成人一级视频| 欧美激情 高清一区二区三区| 级片在线观看| 男女做爰动态图高潮gif福利片 | 欧美中文日本在线观看视频| 欧美+亚洲+日韩+国产| 色精品久久人妻99蜜桃| 国产一区二区激情短视频| 制服诱惑二区| 精品高清国产在线一区| 亚洲成人免费av在线播放| 丝袜人妻中文字幕| 脱女人内裤的视频| 两个人免费观看高清视频| 这个男人来自地球电影免费观看| 久久精品国产综合久久久| 日本精品一区二区三区蜜桃| 婷婷丁香在线五月| 波多野结衣高清无吗| 别揉我奶头~嗯~啊~动态视频| 国产精品国产高清国产av| 成人亚洲精品一区在线观看| 国产人伦9x9x在线观看| 在线观看一区二区三区| 狂野欧美激情性xxxx| 欧美日韩亚洲高清精品| 亚洲国产欧美一区二区综合| 一本综合久久免费| 亚洲中文av在线| 99精品在免费线老司机午夜| 国产不卡一卡二| 美女扒开内裤让男人捅视频| 欧美黑人精品巨大| 日日夜夜操网爽| 视频区欧美日本亚洲| www日本在线高清视频| 啪啪无遮挡十八禁网站| 黄网站色视频无遮挡免费观看| 国产成人av教育| 亚洲精品一区av在线观看| 中文字幕人妻熟女乱码| 最好的美女福利视频网| 首页视频小说图片口味搜索| 久久国产精品男人的天堂亚洲| 欧美大码av| 亚洲av成人av| a级毛片黄视频| 电影成人av| 久久香蕉精品热| 亚洲免费av在线视频| 国产一区在线观看成人免费| 国产精品 欧美亚洲| 19禁男女啪啪无遮挡网站| 午夜91福利影院| 超色免费av| 12—13女人毛片做爰片一| 亚洲欧美精品综合久久99| 两个人免费观看高清视频| 精品一区二区三区av网在线观看| 91av网站免费观看| 老司机在亚洲福利影院| 国产精品秋霞免费鲁丝片| 丁香欧美五月| 高清av免费在线| 19禁男女啪啪无遮挡网站| 女人爽到高潮嗷嗷叫在线视频| 国产精华一区二区三区| 女人被躁到高潮嗷嗷叫费观| 极品人妻少妇av视频| 国产在线观看jvid| 成年女人毛片免费观看观看9| 亚洲av成人av| 国产亚洲精品综合一区在线观看 | 国产色视频综合| 岛国在线观看网站| 少妇粗大呻吟视频| 国产在线观看jvid| 国产极品粉嫩免费观看在线| 水蜜桃什么品种好| 一夜夜www| 国产精品一区二区免费欧美| 欧美黑人精品巨大| 亚洲一区高清亚洲精品| 午夜免费成人在线视频| 桃红色精品国产亚洲av| 日韩中文字幕欧美一区二区| 一个人观看的视频www高清免费观看 | 精品久久久久久成人av| 精品人妻1区二区| 中文字幕色久视频| 国产男靠女视频免费网站| 久久久国产成人精品二区 | 一边摸一边抽搐一进一小说| 黄色成人免费大全| 亚洲av熟女| 曰老女人黄片| 亚洲五月婷婷丁香| 午夜两性在线视频| 大香蕉久久成人网| 亚洲人成网站在线播放欧美日韩| 欧美日韩视频精品一区| 老汉色∧v一级毛片| 国产欧美日韩综合在线一区二区| 婷婷精品国产亚洲av在线| 国产麻豆69| 国产精品影院久久| svipshipincom国产片| 国产一卡二卡三卡精品| 国产精品永久免费网站| 亚洲精品美女久久av网站| 久久精品国产综合久久久| 午夜福利免费观看在线| 亚洲欧美日韩另类电影网站| 午夜精品在线福利| 久久久国产欧美日韩av| 日日爽夜夜爽网站| а√天堂www在线а√下载| 日韩免费av在线播放| 自拍欧美九色日韩亚洲蝌蚪91| 久久久久久大精品| 久久久久久免费高清国产稀缺| 97超级碰碰碰精品色视频在线观看| 亚洲熟妇中文字幕五十中出 | 国产亚洲精品久久久久5区| 欧美精品亚洲一区二区|