• <tr id="yyy80"></tr>
  • <sup id="yyy80"></sup>
  • <tfoot id="yyy80"><noscript id="yyy80"></noscript></tfoot>
  • 99热精品在线国产_美女午夜性视频免费_国产精品国产高清国产av_av欧美777_自拍偷自拍亚洲精品老妇_亚洲熟女精品中文字幕_www日本黄色视频网_国产精品野战在线观看 ?

    Evaluation of new Austrian tunnelling method applied to Bolu tunnel’s weak rocks

    2020-07-12 12:35:38EbuBekirAygar

    Ebu Bekir Aygar

    Fugro Sial Geosciences Consulting and Engineering Ltd., Cankaya, 06690, Ankara, Turkey

    Abstract Since the development of the new Austrian tunnelling method (NATM) in the 1960s, this technique has been applied successfully in many tunnels.However,opinions of NATM principles emerged till 2000,i.e.NATM is not a tunnelling method, but an approach covering all general principles of tunnelling. To investigate the general principles of the NATM, this study focused on tunnelling practises in the Bolu tunnel,and evaluated the conditions under which the NATM practises could be effective.The Bolu tunnel project was designed following the NATM principles. It is evident that practises adopted in this tunnel are important with respect to the NATM. In addition, it shows that the solutions to the problems encountered in this tunnel are consistent with the NATM principles. Finally, the study determines the ground types of the NATM principles and proposes associated updates.

    2020 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).

    Keywords:Bolu tunnel New Austrian tunnelling method (NATM)Support types

    1. Introduction

    The new Austrian tunnelling method (NATM) was developed between 1957 and 1965.In 1944,Rabcewicz categorised rock masses into seven types (from clay to hard rock) and loosesing,squeezing and swelling.Moreover,the rock mass was classified into loosening,squeezing and swelling status (Goricki, 2003). Different support systems have been developed subsequently based on this classification(Goricki,2003).In 1957,rock mass behaviour,rock mass parameters, duration of failure, and tunnel supports were correlated with each other. The fundamental principles of the NATM were proposed by Rabcewicz(1964a,b;1965).In 1974,Pacher,Rabcewicz,and Golser (Goricki, 2003) correlated rock mass behaviour with different elements and classified rocks into four main groups:

    (1) Stable, to potential for large overbreak;

    (2) Friable, to heavily friable;

    (3) Squeezing, to heavy squeezing; and

    (4) Special classes.

    From then on,NATM has been widely applied in many countries.Significant developments in the NATM were explained by Romano(2009). In the study conducted by Golser and Mussger (1979), the application and success of the NATM with the scenarios during tunnel excavation are evaluated.Jakoubek(1986)demonstrated the advantages and applications of NATM in a tunnel. Wagner (1986)compared the applications of the NATM in shallow and deep underground structures with other methods. Studies were also conducted on deep tunnels under difficult rock conditions,applications of NATM in different tunnels, and NATM principles (Braun, 1980;Brown, 1981). In addition, Müller (1978) emphasised that NATM has often been misunderstood“It is not so much,a way of excavating and supporting,but rather a concept. Success depends on following a set of principles,one of which is to utilise the surrounding rock mass to become the main load bearing component,with the lining establishing a load bearing ring”. The importance of ring closure distance and time and that of the invert section in weak soils are also emphasised in his study.

    Romano(2009)suggested different nomenclatures that are used worldwide with respect to the NATM, such as Spritz Betonbauweisse in Germany, Méthode convergence-confinément in France,SCL (Sprayed Concrete Lined Tunnels in UK), NMT (Norwegian method of tunnelling) (Norway), several other names in Japan(CDM, UHVS), and SEM (Sequential Excavation Method) that is frequently used.

    Debates and different opinions have been proposed for the NATM since its proposal. Some researchers hold different option against the integration of general tunnelling method and classical drilling and blasting (DB) method with a single name. In addition,Kovari (1994) criticised the NATM with the concept of “Erroneous concepts behind the new Austrian tunnelling method”.In 1994,the collapse of Heathrow tunnel caused a revision of NATM, owing mainly to the English publications regarding collapses using NATM(Romano, 2009).

    In 1978, rock mass classification for tunnelling became part of the Austrian standards (Goricki, 2003). In 1983e1994, the standards were revised without changing the main concept by Rabcewicz and Golser (1973) on the basis of their principles, Rock mass was then divided into three main groups: A (stable), B(friable), and C (squeezing).

    In 2001, the rock mass classification was revised again. A significant modification of ONORM B2203 was that the issues of rock mass characterisation and classification were excluded. Standards were re-visited in 2001 and 2004 (Goricki, 2003; P?tsch et al.,2004; Schubert, 2004). In addition, a flowchart illustrating the soil behaviour and support system behaviour as geotechnical design was proposed.P?schl and Kleberger(2004a,b)developed an approach in terms of rock mass classification of geotechnical risks.In a work by Palmstrom and Stille (2007), engineering tools for tunnels were proposed. The study of Marinos (2010) on tunnel behaviour mechanism was similar to that of Schubert(2004).In the present study,the works of Goricki(2003)and P?tsch et al.(2004)were considered as the basis and compared with other methods.The behaviours of approximately 62 tunnels were examined, and eventually, a tunnel behaviour chart was created.

    In China, many highways and railway tunnels are under construction. However, some problems were encountered in these tunnels because of the high rate of deformations during tunnel excavations(e.g.Sun et al.,2019).The most popular tunnels among those in China are the Muzhailing railway tunnel and Muzhailing road tunnel.The length of the Muzhailing tunnel on the Lanzhoue Chongqing railway line is 19.1 km.Its cross-sectional area is 70 m2.The excavation process was completed in eight years.Deformations continued for three years after completion of the excavations. The tunnel has a highly complex geological structure, passing through 11 faults with a total length of 4500 m(Chen et al.,2017).Geological units along the tunnel route generally exhibit low strength,due to high content of carbonaceous slate, and high overburden stress.During tunnel excavation, failures in the steel shafts, cracks in the shotcrete, and swelling at the basement were observed. In certain parts of the tunnel,deformations reached up to 1.6 m.The supports were applied according to the principle of “strong support, weak release, support while release, rapid construction”. Rapid construction implies rapid excavation,rapid support,and rapid closure(Xi,2017).Moreover,the support system was selected with respect to pipe ahead,stringent grouting,short excavation,strong support,rapid closure,regular measurement,and tight lining principles(Xi,2017).

    Furthermore,the Zhegushan,Laodongshan,Minyazi,Xiangshan,Yingfeng, and Yezhping tunnels in China represent similar problematic cases (Wang et al., 2019). Many problems were encountered similarly in these tunnels. During excavations, many fault zones, weak soils, and shear zones were identified. While excavating these critical sections,large deformations were encountered,failures occurred in the support systems,and the deformation rates in the Xiangshan tunnel archetypally reached up to 5.4 cm per day.High-risk scenarios in these sections were successfully overcome by modifying the tunnel support systems appropriately (Wang et al., 2019).

    In this study,applications of NATM principles in Bolu tunnel will be discussed.The conditions under which NATM principles fail will be discussed and possible solution suggestion will be provided.The NATM principles which failed in weak soils and fault zones will be determined and the revisions to be made will be demonstrated.

    Fig.1. Bolu tunnel location map.

    Fig. 2. Cross-section of Bolu tunnel (unit: m) (Geoconsult,1997b).

    2. Principles of NATM

    The NATM is based on the principle of maximising the capacity of the ground to sustain its own weight by precisely and rationally balancing the pressures that affect the surrounding rock and support. This is achieved by forming a cavity in the rock or ground through which the tunnel will pass and reinforcing this cavity with support elements(Rabcewicz and Golser,1973).

    Fig. 3. Geological profile of left tunnel of Bolu tunnel (Simsek, 2004).

    Table 1Rock behaviour according to Austrian standard ONORM B2203 (Dalg??, 2002).

    There are two types of support systems. The first system involves a flexible outer arch or protective support designed to balance the structure.The system is reinforced by additional steel ribs,bolts, and shotcrete. The ring is then closed using invert concrete.During the rearrangement of forces, the behaviours of the protective support system and the ground surrounding the tunnel are controlled by a highly developed measurement system (Vardar,1979,1985).

    The second support system involves an inner concrete lining.However,this lining is not fabricated until the outer lining reaches the balance. The purpose of this concrete arch is to maintain or increase the safety factor as necessary (Rabcewicz and Golser,1973). The fundamental principles of NATM, which were proposed by Müller (1978), are listed below:

    Table 2Rock class designation according to Austrian standard ONORM B2203(Dalg??,2002).

    (1) The main element of the tunnel support is the surrounding rock.The main function of the artificial supports is to aid the rock around the tunnel in supporting itself.

    Fig. 4. Details of rocks of classes A2, B1, and B2 (unit: m) (Aygar, 2000).

    (2) The initial robustness of the rock should be preserved. The main principle is preserving the original strength of the rock mass to the feasible extent.

    (3) The loosening of the surrounding rock should be prevented to the feasible extent. This is because loosening of the rock reduces its bearing resistance and increases dead loads.

    (4) The protective zone should be formed without reducing the bearing resistance of the rock. The deformations that occur after excavation will be sufficient for forming the protective zone. However, the deformations should be controlled so that they will not lead to loosening of the rock, which will reduce the bearing resistance. If this is achieved, the safety factor and cost-efficiency of the works will increase.

    (5) Reinforcement should be carried out in a timely manner(neither too early nor too late) and with the necessary flexibility to ensure that the structure providing the lining resistance is neither too rigid nor too weak.

    (6) The reinforcement forces must be using the binding type. If substantial deformations and loosening are likely to occur after excavation, the reinforcement resistance should be in the form of distributed loads, whereas the reinforcement measure should cover the cavity surface. This is most effectively achieved by using shotcrete, which binds within a short period of time.

    (7) Both temporary and permanent reinforcement linings should be in the form of ‘thin shells’, i.e. thin, shell-shaped,and bendable. The bending moments in the shell, as well as the pull and shear fractures resulting from these, can be prevented in this way.

    (8) Reinforcement should be carried out with wire meshes,bolts, shotcrete, and steel ribs. Wire meshes and ribs can provide the necessary flexibility instead of thickening the shell.In order to enable the rock to carry its own weight,the effective stresses should be conveyed into the rock mass through anchorages.

    Fig. 5. Details of support systems for rocks of classes C1, C2, L1, and L2 (unit: m) (Aygar, 2000).

    Table 3Details of support class at design stage of Bolu tunnel.

    Table 4Anticipated support class distribution of Bolu tunnel.

    Table 5Predicted support class distribution of Bolu tunnel.

    Fig. 6. Predicted support class percentage.

    Fig. 7. Standard CM class, Option 1 (Geoconsult,1998b).

    Fig. 8. CM 35 support class details, stretch 2-Bolu tunnel by-pass class CM for metasediment refinement initial support (unit: m) (Geoconsult, 2001).

    Fig. 9. CM 45 support class, longitudinal section (Option 2) (Geocosult,1998b).

    The reinforcement shell should have a closed ring-shape.From a static perspective, the rings must be closed so that an opening could be completely load-bearing. A ring with joints, springs, or notches is unstable compared with a circle.With this consideration,excavation and reinforcement lining of the top heading and the right/left sides should adhere to the cavity wall in an annular manner. Evidently, this can be achieved well by reinforcing shells that follow the complete cross-section of the excavation. The ring should be established at the earliest. The behaviour of the rock during the formation of secondary stresses depends on the deformations of the lining. A tunnel section that is not completely closed will not assume the role of a carrier/bearing ring,and hence will lead to the loosening of the rock.

    Fig.10. CM 45 support class details, stretch 2-Bolu tunnel by-pass class CM45 initial support (unit: m) (Geoconsult, 2002).

    Rounded spacer profiles should be used.The cross-section of the underground cavity should be circular or elliptical, with no protrusions or corners. The first lining should be thin to prevent undesirable bending moments.The inner lining should also be thin and be tightly bonded to the first lining frictionlessly. However, to prevent inner lining from interfering with the loads that may be transmitted from the first lining, it must be placed firmly by using its entire surface, with no friction applied to the inner lining.

    Fig. 11. Option 3 intermediate (Bernold) lining longitudinal section, stretch 2 Bolu tunnel Option 3 Bernold initial support (unit: m) (Geoconsult,1999a).

    Fig. 12. Bench pilot tunnel support details, stretch 2 Bolu tunnel Option 4 initial support section with deformation elements (unit: m) (Geoconsult,1999b).

    Fig. 13. Predicted and practical geological cross-sections at the Elmal?k entrance(Chainage in km and elevation in m) (Geoconsult,1998d).

    Fig.14. Predicted and encountered geological cross-sections at the Asarsuyu entrance(Chainage in km and elevation in m) (Geoconsult,1998d).

    Fig.15. Vertical deformation in chainages 64 t 117 km to 64 t 246 km.

    Fig. 16. Displacement measurements at chainage 64 t 182 km in the left tunnel of Elmal?k (Astaldi,1998).

    The stability of the structure must be ensured with prereinforcement procedures. Deformations in the underground rock structure consisting of the lining and surrounding rock should be halted before the inner lining is put in place.The secondary stresses should achieve their balance. The task of the inner lining is to enhance safety and improve architectural appearance.

    The water pressure transmitted to the lining via the rock mass should be discharged through drainage. To achieve this, drainage pipes should be installed around the space.

    3. Bolu tunnel

    Fig. 17. Reinforcement work prior to the earthquake in the section that collapsed during Düzce earthquake (Aygar, 2007).

    Fig.18. Extensometer installation on shotcrete surface.

    Fig.19. Extensometer installation locations.

    Fig. 20. Extensometer measurements performed on ceiling section of Elmal?k left tunnel at chainage 64 t 034 km (Astaldi,1997).

    Bolu tunnel located on the_IstanbuleAnkara highway consists of two tunnels, each having three lanes. Excavation initiated at the Asarsuyu (Istanbul) side on 16 June 1993 and at the Elmal?k(Ankara) side on 24 June 1994. The excavation of the tunnel was completed in 2006, and it was open to traffic in 2007(Fig.1).

    Between the two tunnels, there is a buttress with 50e60 m width. The tunnels are constructed mostly 100e150 m below the ground surface,with the deepest point at 250 m.With the changes of the ground conditions, lining thickness, and deformations, the cross-sectional area of the tunnel face varies between 133 m2and 260 m2.The equivalent excavation diameters are 13e18.2 m.In the typical excavation cross-sections,the inner surface of the concrete lining has a horizontal opening of 14 m and height of 8.6 m(Fig.2).

    Fig. 21. Extensometer measurements performed at the left lower half section of Elmal?k left tunnel at chainage 64 t 034 km (Astaldi,1997).

    Fig.22. Extensometer measurements at the right lower half section at the Elmal?k left tunnel at chainage 64 t 034 km (Astaldi,1997).

    The tunnel route is located near the active North Anatolian transform fault between the Eurasia plate in the north and Anatolian plates in the south. It is shifting westward from the Anatolian plate.

    The general geological structure adopts the form of the North Anatolian metamorphic crystalline base. The Silurian, Devonian,and Carboniferous layers are composed of conglomerates, arkose,sandstone, mudstone, marl, shale, limestone, and dolomitic limestone (Astaldi, 1993), as shown in Fig. 3. The crystalline bedrock consists mostly of granite, grandiorite, quartzdiorite, and diorite,whereas metamorphic rocks in the amphibolite faults contain gneiss and amphibolites as migmatite.The ridges of the crystalline basins within Paleozoic formations have been eroded.

    In the young Paleozoic layer,the northern continental basin was separated from the marine basin to the south. This formation resulted from low-grade metamorphism transforming old sediments into marble,phyllite,and schist.Owing to many faults on the route of the Elmal?k tunnel, a large number of rock mass blocks(crystalline bedrock, metasediment rock series, and the relevant sections of the flysch formation) are buried within a large-scale matrix of clayey faults, stretching to several hundred meters.

    Fig. 23. Geology of Elmal?k entrance, where a collapse occurred during the Düzce earthquake (Geoconsult,1999c).

    Fig. 24. Support system applied in the right tunnel of Elmal?k between chainages 54 t 140 km and 54 t 080 km (Geoconsult,1996).

    The geology of the Elmal?k side in the fault zone contains flysch series with largely tectonic and rigidly weighted fault clay infilling with smooth discontinuity surfaces and exhibiting plastic properties. These flysch series comprise of claystone, siltstone, and limestone units. The Asarsuyu side is generally traversed by a metasediment series and cataclastic zones formed by these series.This formation continued until the transition to the Bakacak fault and intersects with Bolu tunnel within a 200 m wide fault zone.The fault is oriented in EW direction and crosses the tunnel route perpendicularly between chainages 62 t 800 km and 63 t 000 km(in the left tunnel).These faults have north-oriented plunge angles on cross-sections and cut the tunnel by means of fault clay materials at 75 m in the left tunnel and 91.5 m in the right tunnel,respectively.This fault clay material is comprised of the mixture of metasediments (metasilt stone, quartz limestone, crystallised limestone,low to medium plastic,dense and well-cemented sandy silty fault clay matrix, smooth and polished surface, and water flow)and quartz rocks t amphibolite t metacrystalline basement.This fault zone is located at the junction of the Asarsuyu and Elmal?k geological formations.

    Fig. 25. Excavation works performed at Elmal?k right tunnel between chainages 54 t 140 km and 54 t 080 km.

    The units in the Bolu tunnel can be classified into four main groups: metacrystalline base (Yedig?ller formation), metasedimentary base (_Ikizoluk formation), flysch sequence (F?nd?cak formation),and clayey fault zones(Dalg??,2002).The oldest unit in the tunnel route is Yedig?ller formation, located at the Asarsuyu entrance and comprised of metamorphic rocks. Yedig?ller formation is overlapped by _Ikizoluk formation comprised of Devonian metamorphic units with a tectonic contact. These two formations are primarily overlapped by intrusive granite and also sedimentary rock diversified from Upper Cretaceous to Upper Eocene. A lithological section comprised of amphibole and weathered granodiorite units are observed at the beginning of the Asarsuyu entrance.The other sections are presented to be sandstone, quartzite, and weathered granodiorite and amphibole units combined with marble. Contact between the crystalline basement and sedimentary overburden was formed by the activities of low-angle and conjugate faults.The entire sequence has a fractured structure as a result of clayey fault zones diagonally covering the units. The limestone basement at the Elmal?k entrance appears to be scattered sections in between sandstone and clayey strata containing limestone blocks. The entire sequence contains clayey fault zones and fault infillings.

    The fault zone material at the tunnel elevation is in a series of two units. The first unit is a dark brown, highly plastic, and smoothly polished surface.Meanwhile,the second unit consists of a reddish brown, medium plastic, highly smooth-hard polished surface,and these materials constitute the Bakacak fault and geology.

    Fig. 26. Measurements of vertical displacement between chainages 54 t 141.50 km and 54 t 240 km of the left tunnel of Elmal?k (Astaldi,1997).

    4. Support systems applied to the Bolu tunneldC modified support system

    Owing to the complex geological and geotechnical conditions in Bolu tunnel, there are large differences between the expected and practical rock classes.In the flysch series and the clayey fault zones,significant displacements have occurred in the support systems due to the swelling and compression characteristics of the ground.Large deformations (approximately 1.5 m) have occurred in the tunnel while crossing the clayey fault zone in the Elmal?k right tunnel.This section was filled with a backfill material to prevent the total collapse of the tunnel (Geoconsult, 1998e). In addition, deformations larger than 1 m occurred in the flysch series and minor fault zones were observed in the left tube of the Elmal?k tunnel,where regular repairs had to be conducted. Apart from these problems at the Elmal?k entrances, a water flow/entry of up to 400 L/s was observed at the metasediment series of the Asarsuyu entrances. This was caused by a large number of instability problems in the tunnel(Aygar,2000).To resolve all these problems,the C modified(CM)support system was developed and applied for the first time in Bolu tunnel (Geoconsult,1997a).

    4.1. Primary design phase of the tunnel

    In Bolu tunnel, the project was performed according to the NATM principles. Austrian standards (ONORM B2203) were also implemented.Accordingly,rock behaviours were divided into three categories as stable, brittle, and squeezing (Table 1), and the support systems were divided into eight main groups(Table 2).Figs.4 and 5 illustrate the determined support classes.

    Fig.27. Measurements of horizontal displacements between chainages 54 t 141.50 km and 54 t 240 km of left tunnel of Elmal?k (Astaldi,1997).

    Fig. 28. Displacement measurements in the right tunnel of Elmal?k at chainage 54 t 147 km (Astaldi,1997).

    Figs.4 and 5 and Table 3 detail the proposed support system for each rock class.Evidently,all the support systems were applied at the initial design phase depending on the NATM principles and flexible outer lining principle. The thickness of the shotcrete pavement increased from 5 cm to 25 cm. However, due to unpreventable deformations originated from a previous design of shotcrete thickness of 25 cm, the coating thickness had to be increased to 140 cm for the upper half and 300 cm for the bench section.

    Fig. 29. Concrete filling implemented at right tunnel of Elmal?k between chainages 54 t 140 km and 54 t 080 km following the collapse (Aygar, 2000).

    Fig. 30. General view of concrete filling implemented in Elmal?k’s right tunnel between chainages 54 t 140 km and 54 t 080 km following the collapse (Aygar, 2000).

    According to ONORM B2203, excavation would be conducted theoretically as a full face in class A1 rocks. In practise, it is excavated in two parts:top and bottom.Rocks of class A2 are similar to those of class A1. Excavation in class B1 rocks is divided into two parts:top heading and bench.In class B2,two separate excavations were performed for top heading-bench and basement,respectively.In general, excavations were conducted by DB method. Excavation of rock masses sensitive to vibration was performed by excavators.The top and bottom excavations were performed separately in class C1 rocks. Excavation was performed by DB method or excavators.Separate excavations were performed at the top heading and bench section of class C2 rocks. In many cases, reinforcements were required at the face of the top heading.Excavation was performed by DB method or tunnel excavators.

    Excavation was conducted for the top heading, middle, and basement sections in class L1 soils. In many cases, reinforcements are necessary for the face of the top heading. Excavation was conducted by vibration-free blasting or tunnel excavators. Blocks and hard rock sections need to be detonated. Staged drilling and implementation of side galleries were required to overcome instability problems at the face in class L2 ground units.Excavation was conducted with tunnel excavators.

    In the design phase of the Bolu tunnel,1% A2 rock, 9% B1 rock,40%B2 rock,19%C1 rock,11%C2 rock,10%L1 rock,and 10%L2 rock were expected.The rock classes estimated during the design stage before excavation are presented in the Table 4. The excavation in Bolu tunnel was planned to be carried out as follows:50%on A or B class rock, 30% on C1 or C2 class rock, and 20% on L1 and L2 class rock. The rock classes encountered after completion of tunnel excavation are presented in Table 5 and illustrated in Fig. 6,showing that the rocks upon tunnel excavation is composed of 75%compacted (C) rock class. In addition, 68% of C2M, CM, OP3, and OP4 rock classes were identified during excavation,which were not anticipated during design phase. These segments were entirely designed regardless of the NATM principles.

    Fig.31. The approximately 3.5 m buckling that occurred in the tunnel top heading due to excessive displacements, and the mechanism of failure in the top heading invert(Aygar, 2000).

    Fig. 32. Damage to the tunnel section due to excessive displacements (Aygar, 2000).

    4.2. CM support system

    The CM support system is essentially a method developed specifically for Bolu tunnel (Aygar, 2000). The CM support system was based on the solutions proposed for the section of Bolu tunnel where support systems were applied successfully between 1993 and 1999. That is, all these support systems, which differ significantly from each other in terms of their application ranges, are classified as CM support systems.The Bernold lining was applied in the flysch series and minor fault zone sections,whereas the bench pilot tunnel method was implemented for the large fault zones.The support systems were applied in the metasediment series and metacrystalline grounds. All these application methods belong to the CM support system.Different support systems were categorised under a single class according to the requirement of significant changes in the support systems proposed in the project design phase. The CM support system was applied on four main levels(Geoconsult,1998a; b):

    (1) Metasediments (observed in Asarsuyu);

    (2) Metacrystalline (observed in both Asarsuyu and Elmal?k entrances);

    (3) Flysch series(observed only at the entrance of Elmal?k);and

    (4) Clayey fault zones (observed in the transitional sections of the ground types mentioned above).

    These support systems were grouped under four main headings(Tokgozoglu and Isik, 2002):

    (1) Option 1: CM class temporary shotcrete basement with or without invert (CM 35);

    (2) Option 2:CM class(flysch series,low swelling potential)with reduced ring closure distance and temporary shotcrete with invert (CM 45);

    (3) Option 3:Intermediate(Bernold)lining,temporary shotcrete with invert;and

    (4) Option 4: Bench sectiondpilot tunnel excavation.

    Option 1 is implemented through metacrystalline layers,whereas Option 2 is generally excavated through fracture-crushed metasediment rocks and flysch series with low swelling potential.In addition, Option 3 is implemented for small fault zones with blocky flysch series exhibiting high swelling potential, whereas Option 4 is designed for the worst-case fault conditions such as thick fault clay layers. In accordance with the above explanations,the details of the support and excavation class of these sections are summarised below(Tokgozoglu and Isik, 2002):

    Fig. 33. Cross-section of bench pilot tunnels (unit: m) (Geoconsult,1999b).

    (a) Option 1:CM class(Metacrystalline layer):Standard CM class is a tunnel support system having shotcrete lining of a maximum of 35 cm, monolithic basement concrete, and 360 m rock bolt installed in each advance. This class has a maximum ring closure distance of 30 m. The excavation speed remains constant in this ring closure distance (Figs. 7 and 8).

    (b) Option 2: CM class (Flysch series) reduced ring closure distance, implementation for more unfavourable rock conditions. Intermediate (temporary) basement concrete is required for the top heading section. Shortening the ring closure distance does not affect the excavation speed. The shortest ring closure distance is 22e23 m. The shotcrete lining is 45 cm (Figs. 9 and 10).

    Fig.34. A view during excavation of the bench pilot tunnel method in Elmal?k tunnel.

    (c) Option 3: Intermediate (Bernold) lining: Option 3 is applied for weak flysch series and clayey fault zones(length less than 20 m).The purpose of this system is to ensure the stability of the excavation with rigid supports without applying a large amount of shotcrete in the areas where deformation increases. The intermediate linings are applied while the tunnel displacements continue at high speed, aiming to maintain the stability of excavation with an intermediate lining. The Bernold lining is implemented after installing monoblock basement concrete. The ring closure distance ranges from 20 m to 24 m, and a temporary basement is applied to the top heading section. The Option 3 project is prepared for blocky flyer floors.This project can also be used for thin clay layers of fault zones. The basement concrete is installed as a monoblock with iron reinforcements. If necessary,large deformation can be suppressed by applying a temporary basement at the top heading section extending to the bench section. The primary lining in the support systems includes highly tight rock bolts for each interval(generally 1.1 m) with a shotcrete shell supported by TH-29 steel ribs (Geoconsult, 1998c). Fig. 11 illustrates the crosssection of the Option 3 support system (Aygar, 2007).

    (d) Option 4 (Lower half pilot tunnel method): Under highly unfavourable ground conditions, pilot tunnel excavation of bench section is the only choice. Pilot tunnel excavation of bench section was performed in almost all the conditions in Bolu tunnel,particularly in clayey fault zones spreading over more than 20 m.In this case,the primary support consisted of 40 cm-thick steel fibre shotcrete applied to the tunnel face.The intermediate lining was located 8e16 m behind the face and consisted of an 80 cm-thick steel fibre lining.A bench and a deep(depth of 5.35 m)monoblock basement concrete arch were formed 22e35 m after the tunnel face so as to complete the tunnel circle (ring closure). The final lining (inner lining concrete)was comprised of 60 cm-thick concrete with class B40 iron reinforcements (Geoconsult, 1999d). Fig. 12 illustrates the support system for Option 4(Aygar,2007).

    4.3. Practical and predicted geological conditions in Bolu tunnel and stability problems

    Fig.13 illustrates the predicted geological sections and practical sections in the entrance to the Elmal?k tunnel. The predicted and practical geological sections for the entrance of Asarsuyu are presented in Fig.14.

    Fig. 35. Bernold lining (unit: m) (Geoconsult,1998c).

    The CM support system was implemented following the fundamental principles of the NATM, from 1995 to 1997. No significant differences were imparted to the support systems during this period. In accordance with the progress rate of displacement,there was no change in the support system except for altering the shotcrete thickness, steel ribs, and arrangement of the rock bolts.Meanwhile, in the left tube of the Elmal?k tunnel, the tunnel excavation was interrupted due to the unavoidable displacements.These were overcome by applying 60 cm-thick shotcrete lining to the flysch units. Subsequently, it was understood that Bolu tunnel potentially violated the fundamental principle of the NATM, and a‘flexible outer lining’failed to combat the displacements around the tunnel to form a protective zone. Therefore, it was decided that a more rigid lining method was applied in the flysch series and fault zones of Bolu tunnel. This resulted in implementation of the Bernold lining method(Option 3)(Geoconsult,1998c)and bench pilot tunnel method (Option 4) (Geoconsult, 1999d). Whereas the thickness of the first lining (shotcrete) in the metasediment and metacrystalline ground was 45 cm,this thickness exceeded 1 m in the clayey fault zones and flysch series.

    Fig. 36. Application of Bernold lining in the tunnel.

    4.4. Asarsuyu entrance

    The tunnel behaviours and recorded displacements were consistent with the predicted values in chainages 61 t 900 km(left tunnel) and 51 t 800 km (right tunnel) from the entrance of Asarsuyu. The tunnel support systems were selected based on the rock classes, ranging from A2 to C2. Moreover, the number of rock bolts was altered when the deformation exceeded 1 m at points approximately 150 m from their entrances, and a significant number of remediation processes had to be carried out.As a result,the C2 support class was adapted to C3, and the number of rock bolts installed per meter of progression of the tunnel increased from 123 to 350. Furthermore, additional support elements were used (such as double steel ribs and longer bolts). In spite of these improvements, stability could not be maintained in this area, and the first lining was severely damaged. Given these undesirable scenarios, the faces were temporarily stopped at chainages 62 t 104 km (left tunnel) and 51 t 974 km (right tunnel). The CM class support was implemented for these locations after geological and geotechnical investigations, beginning in September 1996(Aygar, 2000).

    4.5. Elmal?k entrance left tunnel

    In the Elmal?k tunnels, the class C2 support was applied at chainages 64 t 140 km in the left tunnel and 54 t 074 km in the right tunnel.Subsequently,from this location,the C2 rock class was revised according to the increase in displacement and the deterioration of the ground, and the implementation of the CM support system was initiated. In the left tunnel, an attempt was made to advance from chainages 64 t 140 km to 63 t 880 km without excessive alterations to the support. In this section, the only modifications were to increase the number of rock bolts,alter the steel ribs, and vary the thickness of the shotcrete.

    This section of the tunnel is located in the fault zone between chainages 64 t 140 km and 64 t 210 km.This fault zone is a lowangle fault zone with high plastic properties(Aygar,2000).The tunnel was excavated along the fault infilling which was dark brown-reddish brown in colour (Isik and Ozben, 2007). According to the test results, 80% of the material consists of clay fractions. Vertical deformations emerged due to the overlapping low angle fault zone,as shown in Fig. 15. The deformation value reached up to 63 cm. In addition,lateral deformations in this section of the tunnel reached up to 50 cm(see Fig.15).These measurements were taken in the period before 1996.Deformation rise was noticed in progress between 1996 and January 1998. Condition of the deformations is illustrated in Fig.16 with an uppermost value of 100 cm. When the deformation value reached 100 cm,additional shotcrete was applied as an emergency measure,as shown in Fig.17.In other words,the tunnel was at the threshold offailure andthosesupport systems were implemented to prevent tunnel collapse. Unfortunately, when the deformation valuereached100cm,Düzceearthquakeoccurred,and this partof the tunnel completely collapsed under the force of earthquake.

    The deformation in the left tunnel led to the observed fractures and cracks in the concrete. Over elapsed time, these movements continued over a distance of 200 m from the tunnel face.Comprehensive repair and strengthening work started in the tunnel (Aygar, 2000). In addition, extensometers with lengths of 6 m,9 m, and 12 m were placed at the tunnel ceiling and lateral walls.The placement of the extensometers is illustrated in Figs.18 and 19.The extensometer measurements were performed at chainage 64 t 034 km of Elmal?k’s left tunnel to gain an understanding of the plastic area around the tunnel.

    As presented in Fig.20,an examination of the measurements for the 6 m, 9 m and 12 m long single-point extensometers placed in the tunnel ceiling revealed that the displacements continued at a 12 m section in the tunnel ceiling. The 6 m, 9 m, and 12 m long extensometer underwent a total displacement of 7 cm,5.8 cm,and 2.5 cm,respectively.The extensometer measurements at 6 m,9 m,and 12 m in the left bench of the tunnel are illustrated in Figs. 21 and 22. In the lower left half (Fig. 21), the 12 m, 9 m, and 6 m long extensometers recorded displacements of 13 cm, 8 cm, and 4.8 cm, respectively. The displacements occurring at the right bench of the tunnel (Fig. 22) were observed to be 4.8 cm, 3.8 cm,and 0.8 cm by the 6 m, 9 m and 12 m long extensometers,respectively. The main reason for the differences between the measurements of the left and right benches is that the left tunnel was affected by the right tunnel excavation. Considering that the largest displacement occurred in the 12m long extensometer, it is apparent that the right tunnel severely affected the left tunnel in this section. According to the extensometer measurements, the plastic zone around the tunnel appeared to exceed 12 m. Considering that the length of the longest rock bolt placed in the tunnel system was 12 m,it was apparent that all rock bolts were placed in the plastic zone and cannot reach the elastic zone. This demonstrates that the outer lining of the tunnel did not provide a complete arch around the tunnel.

    4.6. Evaluation of the right tunnel support systems

    To cross the clayey fault zone in the right tunnel of Elmal?k between chainages 54 t 080 km and 54 t 140 km (Fig. 23), a pilot tunnel was opened in the upper half section (Geoconsult,1996). It was feasible to carry out sufficient geological and geotechnical investigations of the fault zone through this pilot tunnel. A fresh support system was developed. Then, the excavation restarted(Fig. 24). The excavation in the application phase is illustrated in Fig. 25. Despite of the application of the support system following the principle of a ‘flexible outer lining’ within the NATM, a large displacement of 160 cm occurred in this area(Aygar,2000).Severe buckling was observed in the intermediate invert in the top heading(Schubert et al.,1996).The tunnel stability was not assumed.

    The displacement measurements between chainages 54 t 141 km and 54 t 240 km in the right tunnel of Elmal?k are illustrated in Fig.26.This section is located in the main fault zone and was involved with the section of the tunnel that collapsed during the earthquake.The measurements were obtained along a 100 m tunnel line,and the vertical displacements exceeded 100 cm over a period of five months.Moreover,a deformation of 65 cm was observed in the horizontal direction (Fig. 27). That is, the tunnel was severely narrowed both vertically and horizontally.The measurements made at chainage 54 t147 km in this section areillustratedin Fig.28.Inthe top heading,a vertical displacement of 1.64 m occurred in section 1(tunnel roof),whereas a vertical displacement of 1.23 m occurred in the left and right sides of the top heading(sections 4 and 5).In this sense, stability could not be achieved in the tunnel, and displacements continued during thisperiod with increasing intensity.Owing to unexpected large displacements, this section was completely abandoned and filled with backfill material to prevent tunnel collapse(see Figs.29 and 30)(Aygar,2000).

    Figs.31 and 32 illustrate the damage at the tunnel caused by the displacements in this section. These images were captured during the reprofiling works performed after filling the tunnel with backfill material.

    Various solutions were considered for the section that was filled following the collapse. First, it was concluded that the support system should be a method not based on NATM principles. The principle of maintaining an arch through a flexible outer lining lost its validity in the fault zones. Therefore, it was decided to utilise a more rigid lining. Eventually, the most appropriate project design for crossing this fault zone would be applying the bench pilot tunnel method (Figs. 33 and 34). As is evident in Fig. 33 two 5 mdiameter pilot tunnel excavations were made in the bench of these sections, and they were filled with iron reinforcement and concrete.The top heading section comprised 70 cm shotcrete.The fault zone was passed smoothly using the bench pilot tunnel method.Apparently,this method is completely out of the scope of the NATM principles, involving a very rigid lining thickness (Aygar, 2000).

    It was not feasible to decide what support class should be implemented in the flysch series of the right tunnel (from chainages 54 t 140 km to 54 t 080 km). Based on the experience gained during applications in the left tunnel,it was clear that a rigid shotcrete layer of 60 cm would be insufficient and a middle lining would be required for these sections. The middle lining (Bernold lining) is a lining located between the shotcrete and the inner lining,for which a lining method was applied after completion of top heading, bench, and invert concrete linings (Fig. 35). The application of the Bernold lining in tunnels is illustrated in Fig. 36.

    5. Conclusions

    NATM is an approach that covers the principles of general underground support rather than a tunnelling method. The results obtained from Bolu tunnel reveal that it is not always feasible to implement the principle of“ensuring an arch with a flexible outer lining”.Thus,the implementation of this method could not always be an appropriate or economic approach. Implementation of this method resulted in significant increase in the cost of Bolu tunnel.The collapse of a 50 m section in the right tunnel can also be induced by implementation of this method.Furthermore,in the left tunnel,excavation works were halted for approximately 10 months,and continuous repair and reinforcement works were required.

    A wide range of opinions is that each tunnel brings with a sitespecific method.The results obtained in a tunnel tend to serve as a guide for other tunnels.By the time,the excavation was completed for Bolu tunnel,which was originally designed according to NATM principles, but completed without it. Implementation of NATM principles and proposing solutions for the encountered problems would be appropriate only if they are revised according to the solutions developed for a case wherein the NATM provides unsatisfactory outcomes.The NATM principles consist of 22 items set out by Müller (1978). The revised ones are as follows:

    (1) The reinforcement lining should be in the form of ‘thin shells’. However, when the ground conditions are highly inadequate(such as presence of widespread fault zones and flysch series containing low angle faults having the potential of swelling and squeezing), the outer lining should be significantly more rigid than the thin shell. If necessary, the bench pilot tunnel method should be applied in large fault zones. In sections where the ground is in good condition,both the temporary and permanent reinforcement linings should be thin, shell-shaped, and sufficiently flexible to permit bending. This aids in preventing the formation of bending moments in the shell.It also prevents the formation of associated pull and shear fractures.

    (2) Reinforcements should be made of steel meshes, bolts and steel ribs,rather than by thickening the shell,to provide the necessary flexibility to the shell. With the deterioration of ground conditions, a more rigid system such as the Bernold lining will be required as a supplement to the reinforcement elements in the fault zones and flysch series.

    (3) The inner lining should be thin and frictionless, yet tightly bonded to the outer lining.The outer lining should be thin to prevent undesired bending moments.To prevent them from interfering with the loads originating from the outer lining,the inner and outer linings should be placed firmly by using their entire surface without friction. Bolu tunnel has demonstrated that thin outer lining is not suitable for all ground conditions. This is why a rigid system should be preferred for the outer lining under weak ground conditions.

    (4) The stability of the structure must be ensured during the prestabilisation phase. Deformation in the underground rock units including the crust and surrounding rock should be halted before the inner lining is installed. That is, the secondary stress condition should be finalised in a balanced manner.The purpose of the inner lining is to enhance safety and provide an appropriate architectural appearance. However,when groundwater is present,the inner shell should be sized to receive all loads. In these cases, the layer between the outer and inner shells should be waterproof using bitumen, nylon, membranes, etc. As a highly important element of temporary stabilisation, bolts must be protected against corrosion, so that they can be relied upon for permanent strengthening.When the stability of the structure is not secured by the outer lining,the deformation could not be completely halted, and they continue to a certain extent.Thus, the inner lining should be installed as close to the tunnel face as possible. Moreover, the tunnel should be reinforced with steel bars before deformation rates decrease below 2 mm per month based on the Austrian Standards.

    Declaration of Competing Interest

    The author declares that they have no known competing financial interests or personal relationships that could have appeared to influence the work reported in this paper.

    Acknowledgments

    The author thanks to General Directorate of Highways(KGM)for their supports.

    男女无遮挡免费网站观看| av女优亚洲男人天堂| 一级毛片久久久久久久久女| 国产av国产精品国产| 黄色毛片三级朝国网站 | 一级爰片在线观看| 久久这里有精品视频免费| 高清视频免费观看一区二区| h日本视频在线播放| a级片在线免费高清观看视频| 人妻系列 视频| 狠狠精品人妻久久久久久综合| 国产精品蜜桃在线观看| 麻豆精品久久久久久蜜桃| 男人爽女人下面视频在线观看| 中文字幕精品免费在线观看视频 | 又黄又爽又刺激的免费视频.| 久久久精品免费免费高清| 国产精品不卡视频一区二区| 久久久久国产网址| 欧美区成人在线视频| 三级国产精品欧美在线观看| av网站免费在线观看视频| 亚洲av国产av综合av卡| 成人亚洲欧美一区二区av| 免费高清在线观看视频在线观看| 一级片'在线观看视频| 18禁在线无遮挡免费观看视频| 国产一级毛片在线| 岛国毛片在线播放| 26uuu在线亚洲综合色| 成人18禁高潮啪啪吃奶动态图 | 亚洲欧美日韩卡通动漫| 日本av手机在线免费观看| 日韩电影二区| 99久久精品一区二区三区| 国产伦理片在线播放av一区| 国产色爽女视频免费观看| 久久精品久久久久久久性| 亚洲精品456在线播放app| 老熟女久久久| 久久婷婷青草| 十八禁网站网址无遮挡 | 久久久久久久久大av| 日韩不卡一区二区三区视频在线| av在线老鸭窝| 午夜免费男女啪啪视频观看| 高清视频免费观看一区二区| 日韩精品免费视频一区二区三区 | 日产精品乱码卡一卡2卡三| 最新中文字幕久久久久| 日本猛色少妇xxxxx猛交久久| 色视频在线一区二区三区| 午夜福利影视在线免费观看| 中文字幕精品免费在线观看视频 | 日韩三级伦理在线观看| 狂野欧美激情性xxxx在线观看| 嫩草影院入口| 少妇人妻精品综合一区二区| 欧美成人午夜免费资源| 一级毛片aaaaaa免费看小| 亚洲久久久国产精品| 久久精品久久久久久久性| 九九爱精品视频在线观看| 尾随美女入室| 日韩不卡一区二区三区视频在线| 亚洲四区av| 亚洲av成人精品一区久久| 午夜福利在线观看免费完整高清在| 亚洲精品乱久久久久久| 国产亚洲精品久久久com| 精品亚洲成国产av| 精品人妻偷拍中文字幕| 久久青草综合色| 如何舔出高潮| 美女脱内裤让男人舔精品视频| 国产成人免费观看mmmm| 精品人妻熟女av久视频| 秋霞伦理黄片| av在线观看视频网站免费| 国产综合精华液| 亚洲精品456在线播放app| 免费大片黄手机在线观看| 精品久久久久久久久亚洲| 国产av国产精品国产| 自线自在国产av| 国产av精品麻豆| 亚洲一级一片aⅴ在线观看| 久久国内精品自在自线图片| 两个人免费观看高清视频 | 国产69精品久久久久777片| 亚洲国产精品999| 亚洲欧美精品专区久久| 毛片一级片免费看久久久久| 亚洲av在线观看美女高潮| 国产高清不卡午夜福利| 女人精品久久久久毛片| 麻豆成人午夜福利视频| 欧美高清成人免费视频www| 汤姆久久久久久久影院中文字幕| 少妇裸体淫交视频免费看高清| 国产精品蜜桃在线观看| 大话2 男鬼变身卡| 国产精品三级大全| 久久久久久久大尺度免费视频| 亚洲中文av在线| 国产成人免费观看mmmm| 97精品久久久久久久久久精品| 日韩成人伦理影院| www.色视频.com| 一本大道久久a久久精品| 精品一区二区三卡| av免费观看日本| 久久国产亚洲av麻豆专区| 亚洲不卡免费看| 九九在线视频观看精品| 18禁裸乳无遮挡动漫免费视频| 麻豆成人午夜福利视频| 人妻制服诱惑在线中文字幕| 久久久久视频综合| 简卡轻食公司| 岛国毛片在线播放| 国产男女内射视频| 亚洲国产成人一精品久久久| 亚洲av日韩在线播放| √禁漫天堂资源中文www| 三级国产精品片| 黄色配什么色好看| 久久人人爽人人爽人人片va| 久久久久久久大尺度免费视频| 黑丝袜美女国产一区| 大陆偷拍与自拍| 国产极品粉嫩免费观看在线 | 乱系列少妇在线播放| 欧美高清成人免费视频www| av免费观看日本| 精品少妇久久久久久888优播| 日韩亚洲欧美综合| 亚州av有码| 天堂8中文在线网| 精品一区二区三区视频在线| 美女视频免费永久观看网站| 中文字幕久久专区| 国产高清不卡午夜福利| 久久精品久久久久久噜噜老黄| 国产日韩一区二区三区精品不卡 | 亚洲国产欧美在线一区| 国产免费一区二区三区四区乱码| 极品教师在线视频| 日韩成人伦理影院| 欧美精品人与动牲交sv欧美| av免费在线看不卡| 嫩草影院入口| 午夜精品国产一区二区电影| 欧美人与善性xxx| 只有这里有精品99| 日韩强制内射视频| 在现免费观看毛片| av黄色大香蕉| 伦精品一区二区三区| 男女边摸边吃奶| 一级a做视频免费观看| 国内精品宾馆在线| 新久久久久国产一级毛片| 成人免费观看视频高清| 日本色播在线视频| 青青草视频在线视频观看| 久久人人爽人人片av| 一级毛片aaaaaa免费看小| 边亲边吃奶的免费视频| 日本vs欧美在线观看视频 | 久久亚洲国产成人精品v| 免费观看av网站的网址| 亚洲精品,欧美精品| 有码 亚洲区| 一区二区三区免费毛片| 不卡视频在线观看欧美| 久久热精品热| 草草在线视频免费看| 亚洲va在线va天堂va国产| 男人狂女人下面高潮的视频| 国产在线男女| 久久久久久久久久久久大奶| 最近最新中文字幕免费大全7| 91精品国产国语对白视频| 三上悠亚av全集在线观看 | 最近最新中文字幕免费大全7| 六月丁香七月| 高清毛片免费看| 日韩熟女老妇一区二区性免费视频| 欧美日韩精品成人综合77777| 嫩草影院新地址| 香蕉精品网在线| 大陆偷拍与自拍| 成人特级av手机在线观看| 丝袜在线中文字幕| 在线观看av片永久免费下载| 亚洲色图综合在线观看| 国产av一区二区精品久久| 日韩伦理黄色片| 曰老女人黄片| 国产黄片美女视频| 噜噜噜噜噜久久久久久91| 国产欧美日韩一区二区三区在线 | 各种免费的搞黄视频| 人妻系列 视频| 成人免费观看视频高清| 久久久久人妻精品一区果冻| 午夜影院在线不卡| 亚洲av成人精品一二三区| 51国产日韩欧美| 国产精品一区二区三区四区免费观看| 成人影院久久| 日本欧美视频一区| 26uuu在线亚洲综合色| a 毛片基地| 性高湖久久久久久久久免费观看| 久久ye,这里只有精品| 久久久久久久久久久丰满| 久久免费观看电影| 美女cb高潮喷水在线观看| 国产精品99久久久久久久久| 久久人人爽人人爽人人片va| 亚洲av在线观看美女高潮| 亚洲精品亚洲一区二区| 老司机影院成人| 国产欧美亚洲国产| 成人影院久久| 在线观看免费视频网站a站| 视频区图区小说| 亚洲人与动物交配视频| 亚洲欧美一区二区三区黑人 | 成人亚洲欧美一区二区av| 国产精品一区二区在线不卡| 久久狼人影院| 女人精品久久久久毛片| 成年av动漫网址| 特大巨黑吊av在线直播| 午夜福利在线观看免费完整高清在| 久久综合国产亚洲精品| 免费少妇av软件| 美女主播在线视频| 人妻系列 视频| 日本-黄色视频高清免费观看| av国产精品久久久久影院| 秋霞伦理黄片| 中文精品一卡2卡3卡4更新| 亚洲精品456在线播放app| 纵有疾风起免费观看全集完整版| 性色avwww在线观看| 中文资源天堂在线| 久久久精品94久久精品| 国产成人精品一,二区| 免费观看a级毛片全部| 精品卡一卡二卡四卡免费| 建设人人有责人人尽责人人享有的| 日韩免费高清中文字幕av| 国产精品蜜桃在线观看| 女人久久www免费人成看片| 哪个播放器可以免费观看大片| 久久99热这里只频精品6学生| 热re99久久精品国产66热6| 国产在线视频一区二区| 国内揄拍国产精品人妻在线| 国模一区二区三区四区视频| 男女无遮挡免费网站观看| 91午夜精品亚洲一区二区三区| 久久午夜综合久久蜜桃| 免费看日本二区| 波野结衣二区三区在线| 日韩中文字幕视频在线看片| 国产精品一区www在线观看| 日日摸夜夜添夜夜添av毛片| 久久99蜜桃精品久久| 国产成人免费无遮挡视频| 老女人水多毛片| 欧美精品人与动牲交sv欧美| 9色porny在线观看| 免费在线观看成人毛片| 少妇精品久久久久久久| 国产精品一二三区在线看| av在线老鸭窝| 黑丝袜美女国产一区| 亚洲国产精品专区欧美| 亚洲综合精品二区| 欧美精品高潮呻吟av久久| 永久免费av网站大全| 我要看日韩黄色一级片| 啦啦啦啦在线视频资源| 成人亚洲精品一区在线观看| 国产欧美另类精品又又久久亚洲欧美| 狂野欧美白嫩少妇大欣赏| 99国产精品免费福利视频| 亚洲欧洲国产日韩| 日本欧美国产在线视频| 久久久欧美国产精品| 五月伊人婷婷丁香| 精品久久久精品久久久| 日韩视频在线欧美| 欧美亚洲 丝袜 人妻 在线| 一区二区三区四区激情视频| 观看免费一级毛片| 国产精品福利在线免费观看| 日韩亚洲欧美综合| 精品少妇黑人巨大在线播放| 爱豆传媒免费全集在线观看| 涩涩av久久男人的天堂| 一级毛片 在线播放| 91精品国产九色| 2022亚洲国产成人精品| 人妻系列 视频| 久久热精品热| 国产老妇伦熟女老妇高清| 国产有黄有色有爽视频| 一区二区三区乱码不卡18| 国产精品.久久久| 精品少妇久久久久久888优播| 日韩在线高清观看一区二区三区| 久久午夜综合久久蜜桃| 久久亚洲国产成人精品v| 97在线视频观看| 免费人成在线观看视频色| 爱豆传媒免费全集在线观看| 亚洲av成人精品一区久久| 99热网站在线观看| 日本91视频免费播放| 日韩精品有码人妻一区| 高清毛片免费看| 看非洲黑人一级黄片| 亚洲av综合色区一区| 日韩av在线免费看完整版不卡| 久久久久网色| 伊人亚洲综合成人网| 在现免费观看毛片| 日韩欧美 国产精品| 在现免费观看毛片| 中文天堂在线官网| 国产黄色视频一区二区在线观看| 亚洲精品视频女| 简卡轻食公司| 伊人亚洲综合成人网| 五月天丁香电影| 肉色欧美久久久久久久蜜桃| 在现免费观看毛片| 男的添女的下面高潮视频| 日韩亚洲欧美综合| av网站免费在线观看视频| 亚洲国产色片| 亚洲精品视频女| 亚洲欧美一区二区三区国产| 亚洲精品视频女| 最近的中文字幕免费完整| 亚洲av欧美aⅴ国产| 在现免费观看毛片| 美女大奶头黄色视频| 简卡轻食公司| 婷婷色麻豆天堂久久| 少妇人妻精品综合一区二区| 午夜影院在线不卡| 日韩av免费高清视频| 亚洲第一av免费看| 亚洲内射少妇av| 久久婷婷青草| 成人影院久久| 久久精品国产亚洲av涩爱| 视频中文字幕在线观看| 国产在线免费精品| 精品少妇内射三级| 高清午夜精品一区二区三区| 2021少妇久久久久久久久久久| 日本免费在线观看一区| 中文乱码字字幕精品一区二区三区| 国产免费福利视频在线观看| 国产成人aa在线观看| 男女啪啪激烈高潮av片| 色视频www国产| 国产真实伦视频高清在线观看| 性色av一级| 国产精品成人在线| 亚洲国产欧美日韩在线播放 | 亚洲精品成人av观看孕妇| 亚洲精品乱码久久久久久按摩| 午夜激情福利司机影院| 亚洲美女搞黄在线观看| 最新的欧美精品一区二区| 麻豆乱淫一区二区| 亚洲美女黄色视频免费看| 婷婷色av中文字幕| 日韩不卡一区二区三区视频在线| 国产乱人偷精品视频| 国产成人免费观看mmmm| 日韩视频在线欧美| 亚洲欧洲精品一区二区精品久久久 | 你懂的网址亚洲精品在线观看| 久久精品国产鲁丝片午夜精品| 日韩制服骚丝袜av| 一级爰片在线观看| 国产亚洲午夜精品一区二区久久| 中国美白少妇内射xxxbb| 国产综合精华液| 成年人免费黄色播放视频 | 亚洲精华国产精华液的使用体验| 免费大片18禁| 精品酒店卫生间| 亚洲婷婷狠狠爱综合网| 免费观看在线日韩| 久久久久网色| 国产亚洲5aaaaa淫片| 男人狂女人下面高潮的视频| 国产精品秋霞免费鲁丝片| 亚洲av在线观看美女高潮| 99久久中文字幕三级久久日本| 少妇精品久久久久久久| 黑人猛操日本美女一级片| 熟女av电影| 久久久久久久精品精品| 成人亚洲欧美一区二区av| 最近手机中文字幕大全| 交换朋友夫妻互换小说| 国产亚洲一区二区精品| 成人国产麻豆网| 高清在线视频一区二区三区| 高清av免费在线| a级一级毛片免费在线观看| 亚洲av电影在线观看一区二区三区| 久久av网站| 国产av国产精品国产| 免费av不卡在线播放| 亚洲va在线va天堂va国产| 高清黄色对白视频在线免费看 | 久久精品国产自在天天线| 国产在线一区二区三区精| 亚洲精品乱久久久久久| 午夜免费男女啪啪视频观看| 嫩草影院新地址| 波野结衣二区三区在线| 国产淫片久久久久久久久| freevideosex欧美| 亚洲精品国产av蜜桃| 日韩制服骚丝袜av| 久久精品熟女亚洲av麻豆精品| 国产视频首页在线观看| 黄色一级大片看看| 国产精品久久久久成人av| 日韩欧美 国产精品| 99热这里只有是精品在线观看| 只有这里有精品99| 国产精品福利在线免费观看| 51国产日韩欧美| 日本黄大片高清| 国模一区二区三区四区视频| 亚洲成人av在线免费| 国产av国产精品国产| 亚洲国产精品999| 人人妻人人澡人人看| av又黄又爽大尺度在线免费看| 免费黄网站久久成人精品| 国产一区二区在线观看日韩| 国产精品国产三级国产专区5o| 边亲边吃奶的免费视频| 男人和女人高潮做爰伦理| 亚洲成人av在线免费| 久久久久久久久久久久大奶| 丰满乱子伦码专区| 日本欧美视频一区| 一本—道久久a久久精品蜜桃钙片| 久热久热在线精品观看| freevideosex欧美| 日韩 亚洲 欧美在线| 天堂中文最新版在线下载| 亚洲va在线va天堂va国产| 国产男女超爽视频在线观看| 91精品国产国语对白视频| 国产成人freesex在线| 亚洲欧洲精品一区二区精品久久久 | 日韩成人伦理影院| 伦理电影免费视频| 成人午夜精彩视频在线观看| 18禁裸乳无遮挡动漫免费视频| 在线观看人妻少妇| 亚洲欧洲日产国产| 九草在线视频观看| 国产片特级美女逼逼视频| 久久99蜜桃精品久久| 国产在线一区二区三区精| 国产男女内射视频| 看免费成人av毛片| 在线 av 中文字幕| 亚洲天堂av无毛| 久久久a久久爽久久v久久| 亚洲欧洲精品一区二区精品久久久 | 亚洲av成人精品一区久久| 丰满乱子伦码专区| h日本视频在线播放| 老司机亚洲免费影院| 中文欧美无线码| av在线app专区| 国国产精品蜜臀av免费| 大香蕉久久网| 国产淫片久久久久久久久| 成人黄色视频免费在线看| 丁香六月天网| 一级二级三级毛片免费看| 久久女婷五月综合色啪小说| 久久精品夜色国产| 亚洲国产av新网站| 国产av一区二区精品久久| 高清不卡的av网站| 中文天堂在线官网| 国产爽快片一区二区三区| 一边亲一边摸免费视频| 国产在线免费精品| 91精品伊人久久大香线蕉| 色94色欧美一区二区| 少妇的逼好多水| 亚洲精品国产色婷婷电影| 国产成人一区二区在线| 国产欧美另类精品又又久久亚洲欧美| 久久久久久久大尺度免费视频| 少妇人妻一区二区三区视频| 狂野欧美白嫩少妇大欣赏| 男女啪啪激烈高潮av片| 免费在线观看成人毛片| 日韩人妻高清精品专区| 国产精品久久久久久精品电影小说| 国产黄色免费在线视频| 少妇熟女欧美另类| 日本午夜av视频| 又爽又黄a免费视频| 丰满人妻一区二区三区视频av| 91成人精品电影| 国产欧美另类精品又又久久亚洲欧美| 亚洲第一av免费看| 中文精品一卡2卡3卡4更新| 久久精品熟女亚洲av麻豆精品| 一级a做视频免费观看| 久久毛片免费看一区二区三区| 搡老乐熟女国产| 亚洲,欧美,日韩| 久久青草综合色| 日韩熟女老妇一区二区性免费视频| 亚洲高清免费不卡视频| 人体艺术视频欧美日本| 亚洲精品国产av成人精品| 国产免费福利视频在线观看| 国产 精品1| 国产黄频视频在线观看| 极品教师在线视频| 亚洲美女视频黄频| 涩涩av久久男人的天堂| 中文精品一卡2卡3卡4更新| 日韩欧美一区视频在线观看 | 亚洲美女搞黄在线观看| 最近最新中文字幕免费大全7| 国产日韩欧美在线精品| 多毛熟女@视频| 国产伦理片在线播放av一区| 亚洲欧美清纯卡通| 亚洲天堂av无毛| 日韩精品免费视频一区二区三区 | 亚洲av男天堂| 伦精品一区二区三区| 五月天丁香电影| 又大又黄又爽视频免费| 18+在线观看网站| 亚洲精品国产av成人精品| 国产 一区精品| 成年女人在线观看亚洲视频| 热re99久久国产66热| 亚洲真实伦在线观看| 国产日韩欧美在线精品| 国产成人免费无遮挡视频| 男人舔奶头视频| 久久久国产欧美日韩av| 久久青草综合色| 日韩人妻高清精品专区| 涩涩av久久男人的天堂| 中文字幕制服av| av一本久久久久| 欧美区成人在线视频| 亚洲精品中文字幕在线视频 | 丝袜喷水一区| av在线播放精品| 日韩av在线免费看完整版不卡| 乱码一卡2卡4卡精品| 校园人妻丝袜中文字幕| 男的添女的下面高潮视频| 国产乱人偷精品视频| 少妇裸体淫交视频免费看高清| 高清黄色对白视频在线免费看 | 精品久久国产蜜桃| 99精国产麻豆久久婷婷| 91精品国产九色| 一级毛片电影观看| 亚洲电影在线观看av| 特大巨黑吊av在线直播| 大码成人一级视频| 熟女av电影| 亚洲成人手机| 国产白丝娇喘喷水9色精品| 欧美bdsm另类| 少妇精品久久久久久久| 美女xxoo啪啪120秒动态图| av天堂中文字幕网| 国产欧美另类精品又又久久亚洲欧美| 亚洲精华国产精华液的使用体验| 精品少妇内射三级| 波野结衣二区三区在线| 亚洲人与动物交配视频| 精品久久久久久久久亚洲| 新久久久久国产一级毛片| 欧美国产精品一级二级三级 | 免费av中文字幕在线| 十八禁网站网址无遮挡 | 欧美变态另类bdsm刘玥|