• <tr id="yyy80"></tr>
  • <sup id="yyy80"></sup>
  • <tfoot id="yyy80"><noscript id="yyy80"></noscript></tfoot>
  • 99热精品在线国产_美女午夜性视频免费_国产精品国产高清国产av_av欧美777_自拍偷自拍亚洲精品老妇_亚洲熟女精品中文字幕_www日本黄色视频网_国产精品野战在线观看 ?

    Physical modeling of behaviors of cast-in-place concrete piled raft compared to free-standing pile group in sand

    2018-08-30 09:21:26MehdiSharafkhahIssaShooshpasha

    Mehdi Sharafkhah,Issa Shooshpasha

    Faculty of Civil Engineering,Babol Noshiravani University of Technology,Shariati Av.,Babol,Mazandaran,Iran

    Keywords:Free-standing pile group Piled raft Pile-soil-raft interaction Physical modeling Cast-in-place concrete piles

    ABSTRACT Similar to free-standing pile groups,piled raft foundations are conventionally designed in which the piles carry the total load of structure and the raft bearing capacity is not taken into account.Numerous studies indicated that this method is too conservative.Only when the pile cap is elevated from the ground level,the raft bearing contribution can be neglected.In a piled raft foundation,pile-soil-raft interaction is complicated.Although several numerical studies have been carried out to analyze the behaviors of piled raft foundations,very few experimental studies are reported in the literature.The available laboratory studies mainly focused on steel piles.The present study aims to compare the behaviors of piled raft foundations with free-standing pile groups in sand,using laboratory physical models.Cast-in-place concrete piles and concrete raft are used for the tests.The tests are conducted on single pile,single pile in pile group,unpiled raft,free-standing pile group and piled raft foundation.We examine the effects of the number of piles,the pile installation method and the interaction between different components of foundation.The results indicate that the ultimate bearing capacity of the piled raft foundation is considerably higher than that of the free-standing pile group with the same number of piles.With installation of the single pile in the group,the pile bearing capacity and stiffness increase.Installation of the piles beneath the raft decreases the bearing capacity of the raft.When the raft bearing capacity is not included in the design process,the allowable bearing capacity of the piled raft is underestimated by more than 200%.This deviation intensifies with increasing spacing of the piles.

    1.Introduction

    The conventional approach for the design of piled raft foundations basically ignores the raft load-sharing,and it has been assumed that the piles carry the whole of structural loads.This approach is unduly conservative and leads to an uneconomic design.Only when the pile cap is elevated from the ground level(i.e.free-standing pile group),this design method is valid.Poulos and Davis(1980)suggested that for sandy soil,the bearing capacity of a piled raft could be considered as the sum of the ultimate bearing capacities of the raft plus all the piles.This approach is called “new approach”in this paper.

    A piled raft foundation consists of three main components:piles,soil and raft(Reul and Randolph,2004).Although there are a vast analytical and numerical researches about these foundations(Dung et al.,2010;Raut et al.,2014;Comodromos et al.,2016;Alnuaim et al.,2017;Huang et al.,2017),the experimental studies are limited.The available laboratory studies mainly concern the behavior of the piled raft by physical modeling.

    Lee and Chung(2005)found if piles were installed in a small space,the stresses and strains of the surrounding soil would be overlapped,and the bearing behavior of the piles would be different from that of the single pile.They also found that during pile driving,the soil density increased when the pile spacing to diameter ratio(s/d)was less than three.

    Fioravante and Giretti(2010)indicated that at the initial steps of loading due to higher stiffness of piles than surrounding soil,the loads were transmitted to the piles mostly.Thus at these steps,the slope of the load-settlement curve in the piled raft is steeper compared tounpiled raft.As the soil failed at the shaft and the point of the piles,the stiffness of the piled raft was approximately equal to that of unpiled raft with an identical slope of the load-settlement curve.Poulos and Davis(1980)also found a similar result and presented a simplified curve for the piled raft.

    EI Sawwaf(2010)defined a bearing pressure improvement(BPI)ratio,which is the ratio of the bearing pressure of a piled raft tothat of an unpiled raft at the same settlementlevel.El-Garhyet al.(2013)carried out 40 small-scale tests on single pile,unpiled raft and piled raft with central piles in sand.They also studied the effects of the raft thickness and rigidity on the results.Bazyar et al.(2009)carried out a 1g physical modeling test and concluded that the physical modeling of the piled raft could be the best way of calibrating design calculation.

    Without considering scale effect in an experimental model,the application of obtained results is limited to the same model.Sedran et al.(2001)related that with a ratio of footing diameter to grain size greater than 30,the in fluence of grain size on model response could be neglected.Tagaya et al.(1988)also reported the similar results.According to Altaee and Fellenius(1994),the soil used in 1g physical modeling must be loose suf ficiently.

    In the abovementioned laboratory researches,metal piles(aluminum or steel)were used,and the pile models were installed by driving or jacking into the soil.The angles of friction between pile and soil in cast-in-place bored concrete piles are different from that of steel piles.Unlike cast-in-place bored concrete pile,in driven piles,soil density increases during driving.

    The current study concentrates on physical modeling of piled rafts under vertical axial load in the laboratory in which cast-inplace bored concrete piles and reinforced concrete raft are used.The test models in this research include single pile,single pile in pile group,unpiled raft,free-standing pile group with 4 or 9 piles,and piled rafts with 4 or 9 piles.Some instruments record the load contribution between the piles and the raft.The effect of the pile installation in the group is also investigated.By comparing the measured bearing capacities of free-standing pile group and piled raft with the same number of piles,the differences between the traditional and new approaches in the piled raft design are studied.The effects of the number and spacing of piles on the settlement and bearing capacity of the foundation are also evaluated.

    2.Test models,material and setup

    2.1.Test models

    Fig.1.Schematic of test models.

    In this study,cast-in-place bored concrete piles are used.The dimensions of the piles after extracting from the soil are measured.The diameter and embedded length of the piles are 2.84 cm and 25.3 cm,respectively.Therefore,the length to diameter ratio is 8.91.It is assumed that the piles are rigid,thus the settlements at the top and bottom of the piles are assumed identical.The raft model is square shaped(20 cm×20 cm)and its thickness is 3 cm.The raft is made of cast-in-place reinforced concrete.The types of the test models used are shown in Fig.1.The pile spacing to diameter ratios(s/d)for the models with 4 and 9 piles are 5.2 and 2.6,respectively.Test models and their labels are as follows:unpiled raft R(#),single pile S(#),single pile in pile group SG(#),free-standing pile group with 4 and 9 piles FG-4(#)and FG-9(#),and piled rafts with 4 and 9 piles PR-4(#)and PR-9(#).Each test repeats once and the symbol#represents the sequence of tests.

    2.2.Test material

    Dry Babolsar sand is used for the test.The minimum and maximum unit weights of the soil are 14.9 kN/m3and 17.6 kN/m3,respectively,and the specific gravity is measured tobe 2.79.The soil gradation curve is shown in Fig.2.The effective grain size(D10),uniformity coefficient(Cu)and curvature coefficient(Cc)are measured to be 0.11,2.6 and 1.09,respectively.The sand is classified as SP according to the unified soil classification system.The mean grain size is 0.26 mm and thus the ratio of the pile diameter to mean grain size is calculated as approximately 109.Therefore,the grain size effect could be ignored.According to Altaee and Fellenius(1994),the testsoil should be loose suf ficiently.With this condition,the responses of the test model and the prototype are similar.Therefore,in this research,the sand with relative density of 30%is used.The peak and constant-volume angles of internal friction of the sand are 37°and 34°,respectively,from triaxial tests.The compressive strengths of the concrete raft and piles are 25 MPa and 10 MPa,respectively,and their unit weights are 22.6 kN/m3and 20.8 kN/m3,respectively.

    2.3.Test setup

    Fig.2.Grain size distribution of the test sand.

    In order to conduct the tests,a square box is prepared.The box sidewalls are made of steel frames to increase its rigidity.Inner dimensions of this box are 1.3 m×1.3 m and its height is 1 m.This box is located on a rigid reinforced concrete slabwith dimensionsof 2.2 m×2.2 m and 30 cm in height.The distance between the center of the test model to the edge of the box is three times greater than the raft width,and the distance between the pile tips to the bottom of the box is two times greater than the pile length.With these considerations,the end effects of the box side could be ignored.Four transparent Plexiglas plates are covered around the box for observation of soil surface level during filling.A steel frame provides the support needed for loading.The frame consists of two steel rods connecting a suf ficiently rigid beam to the base concrete.Beneath the beam,a hydraulic jackis placed.The testload isapplied by a transfer rod to the load cell and then to the model.In order to hold the hydraulic jack over the model and beneath the beam constant,two steel plates are used.The first plate is placed on the top of the beam and the second beneath the hydraulic jack,which is connected to the top plate.In the bottom plate,in order to provide the free movement of the shaft during loading,a hole with a diameterof 100 mm is designed.Since one of the research purposes is to measure the differential settlement and the tilt, five dial gages are used for the tests.One dial gage in the center,two in the corner and two in the middle side of the raft are placed.For single pile,two dial gages in the opposite side of the pile are installed on the two reference beams,which are located on the box edge sides.These instruments are shown in Fig.3.

    3.Testing procedure

    Forachieving a homogenous soil,the sand is poured intothe box in layers with thickness of 10 cm and relative density of 30%.The height of the soil at the end of the filling is 80 cm.A wooden plate with dimensions of 20 cm×20 cm connected to a wooden rod is used to compact the soil layers.For construction of the piled raft,a thin wall square tube with inner dimensions of 20 cm×20 cm and depth of 5 cm and wall thickness of 1 mm is lowered into the soil,and subsequently,the inside of the box is excavated.A wooden template is placed into the box and the pile casings are located into the template and the upper part of the soil.The wooden template is used to determine the accurate place of the piles and provide guidance for them.The external diameter,length and thickness of the pile casings are 25 mm,350 mm and 1.2 mm,respectively.The casing is lowered down manually by about 5 cm and the inside soil is drilled simultaneously with a hand auger.This operation is continued step by step until the embedment length of the casing reaches 25 cm.In order to construct test models,all casings are placed into the soil.The inside height of the casings should be approximately equal to the pile length.Then casting the concrete is initiated.The casings are extracted during pouring concrete.This action as well as placement of casing should be done slowly and carefully.Finally,the template must be extracted.

    Fig.3.Schematic of test setup.

    In order to measure the stress and load distribution,a number of load and pressure cells are placed on the piles and beneath the raft,respectively.Con figuration of pressure cells changes according to model type and pile arrangement,and the cells are usually installed at the corner,middle of edge,center of the raft,and the adjacent area of the piles.Fig.4 shows the names and configuration of these instruments for the unpiled raft and piled raft models.

    In the piled raft models,the level of the pile head is equal to that of surrounding soils on which the raft was built.In order to construct the single pile or free-standing pile group,the pile head is elevated about 5 cm by a guide mold.Therefore,it is assured that the load is not transferred tothe soil.At the next stage,a 3×3 rebar mesh is located at the bottom of the raft base,and the concrete is cast.

    A steel plate of 9 cm in diameter and 5 cm in thickness is placed in the center of the raft on the fresh concrete.It is used for decreasing stress concentration.At the end,the square box is extracted from the edge of the raft slowly.During construction of the free-standing pile group,the pile head is elevated about 5 cm from the surrounding soil,and the load cells are installed on the planned piles.In these cases,polystyrene foam is placed on the piles initially and the cap is constructed above it.The polystyrene foam is removed after the concrete reaches necessary strength.The dimensions of each test model are measured after loading test and discharging of the soil.

    In order to measure the vertical settlement of the foundations,five dial gages are installed over the cap with precision of 0.01 mm and travel of 50 mm.The constant load is applied incrementally.In piled raft and unpiled raft,each load increment is maintained for 3 min until the rate of settlement is not greater than 0.03 mm/min.For single pile and free-standing pile group,when the rate of settlement reduces to 0.25 mm in an hour,the test is stopped.The total applied load is measured bya load cell.During the test on the single pile,the loading is continued until the settlement equals 15%of the pile diameter.The piled raft and free-standing pile group tests are ended when the maximum settlement reaches 15%of the cap width or failure occurs.Each test is repeated once to control result accuracy.

    Fig.4.Schematic of instrument names and configuration for the unpiled raft and piled raft models.

    4.Results and discussion

    4.1.Loading test results for single pile

    The pile dimensions after extracting from the soil are measured.The pile diameter and embedded length are 2.84 cm and 25.3 cm,respectively.The increase of pile diameter from 25 mm to 28.4 mm is due tothe penetration of freshconcrete intothe adjacent soil.The result of the loading test on a single pile is shown in Fig.5.The ultimate bearing capacity of the pile is estimated to be 0.44 kN,which is determined as the load indicated by the intersection of tangent lines drawn through the initial, flatter portion of the total settlement curve and the steeper portion of the same curve(Tomlinson,2004).In order to evaluate the effect of pile installation on other piles,the loading test is carried out on the single pile in a group.Fig.6 demonstrates the results of these tests in 2×2 and 3×3 groups.

    In Fig.7,the load-settlement curve of the single pile is compared with the single pile in the group.By installation of a single pile in a group,the pile bearing capacity and stiffness increase.The bearing capacities of the central,middle side and corner piles in the 3×3 group are increased by 57%,36%and 11%,respectively.This value is about 5%for corner piles located in the 2×2 group.Corner piles have lower stiffness and bearing capacity than others.The piles located in the 2×2 group show a similar behavior as the corner piles in the 3×3 group.The stiffness and bearing capacity of the central pile are increased due to pile confinement generated by adjacent piles and increase of soil density caused by casing penetration.In fact,the confinement increases equivalent stiffness of the soil-pile composition around the pile that decreases soil deformation and pile settlement.Furthermore,due to arching effect,the stress around the pile increases and as a result,the pile ultimate bearing capacity increases.

    4.2.Loading test results for free-standing pile group

    The results of loading test on the 2×2 and 3×3 free-standing pile groups are shown in Fig.8 for two successive tests,and their averages are demonstrated in Fig.9.The load-settlement relations of the piles in the free-standing group are shown in Figs.10 and 11.Figs.12 and 13 show the comparisons of the average loadsettlement relations of single pile in a group with the pile in freestanding group.

    Fig.5.Load-settlement relations of single piles.

    Fig.6.Load-settlement relations of single piles in a group for two successive tests:(a)2×2 pile group;(b)central pile in 3×3 pile group;(c)middle side pile in 3×3 pile group;and(d)corner pile in 3×3 pile group.

    The behaviors of the piles in the 2×2 free-standing pile groups are approximately similar,but those in the 3×3 free-standing pile groups depend on their positions.Similar to single pile in pile group,the bearing capacity of the central pile is the greatest,followed by edge pile and corner pile.The bearing capacity of the pile in free-standing group is approximately equal to that of corresponding single pile in group,but the pile stiffness in the freestanding group is less due to the pile stress interaction during loading.On the other hand,the pile settlement in free-standing group increases in comparison to single pile in the corresponding group under the same load.In addition,for the same reason,the pile bearing capacity in the 3×3 pile group is slightly greater than that for the corresponding single pile.In the 2×2 free-standing group,due to larger spacing between the piles(s/d=5.2),the stiffness reduction is less than that in the 3×3 group(s/d=2.6).

    4.3.Loading test results for piled raft

    Fig.7.Average load-settlement relations of single pile and single pile in group.Δis the settlement and d is the pile diameter.

    Fig.8.Load-settlement relations for free-standing pile groups:(a)2×2 and(b)3×3 free-standing pile groups for two successive tests.

    Fig.9.Average load-settlement relations for 2×2 and 3×3 free-standing pile groups.

    Fig.10.Load-settlement relations of corner piles in 2×2 free-standing pile group for two successive tests.

    In order to compare free-standing groups with piled rafts,a series of loading tests is conducted on unpiled raft,2×2 and 3×3 piled rafts,and each test is repeated once.Figs.14 and 15 show the comparisons of load-settlement curves of piles located beneath the raft,in whichΔmaxis the maximum settlement.The corner pile curves coincide with each other in the 2×2 and 3×3 piled rafts.At the beginning of the loading,the stiffnesses of corner piles are greater than those of other piles.Fig.15 presents a comparison of the load-settlement curves for a single pile in the corner of pile group,the corner piles in the 2×2 piled raft and 2×2 freestanding pile group.In the piled raft,after pile failure,due to the increase in the stress around the piles caused by the raft pressure,a hardening phenomenon occurs.In the central piles and the middle side piles,due to negative friction caused by the raft pressure,the pile bearing capacity increases gradually.In the corner piles,because of the lower raft pressure,the hardening phenomenon is insignificant.

    Fig.11.Load-settlement relations of middle side,corner and central piles in 3×3 freestanding pile group for two successive tests.

    Fig.12.Average load-settlement relations of single piles in 2×2 group and 2×2 freestanding pile group.

    Fig.16 shows the comparison of load-settlement curves of piles in piled raft foundation and free-standing group.The behaviors of the corner piles are approximately similar.Yielding points in corner piles coincide with each other.The slight difference is due to the raft pressure in piled raft that increases the pile bearing capacity.In the other piles due to greater raft pressure and associated negative friction,the pile stiffness decreases and the bearing capacity increases significantly.In the corner,edge and central piles in the 3×3 piled raft,the increases in pile bearing capacity in comparison to single pile are approximately 16%,64%and 264%,respectively.

    The averages of measured results of pressure cells installed beneath the raft are shown in Fig.17.In unpiled raft,the corner,middle side and center of the raft yield consecutively.In other words,with approaching the center of the raft,the raft bearing capacity increases.In fact,because of the stress confinement in the central area,the failure occurs at higher stress level.

    Fig.13.Average load-settlement relations of single piles in 3×3 group and 3×3 freestanding group.

    Fig.14.Average load-settlement relations of piles in 2×2 and 3×3 piled rafts.

    Fig.15.Average load-settlement relations of piles in 2×2 free-standing group and 2×2 piled raft and a single pile in group.

    In the 2×2 piled raft,since the pressure cell installed adjacent to the piles is close to the middle side pressure cell,their curves become similar.Generally,given that the four corner piles carry a portion of the load symmetrically,the contact pressure beneath the raft is moreuniform thanothermodels.In the 3×3 piled raft and at the initial steps of loading,the piles carry the most portion of the load.After pile failure,the raft pressurerises suddenly.The pressure increases from the corner to the center of the raft.In the central pile,due to the stress interaction,the pile stiffness is smaller and therefore,the raft pressure in the central area is higher.

    Fig.16.Average load-settlement relations of piles in 3×3 piled raft and 3×3 freestanding pile group.

    Fig.17.Average contact pressure-settlement relations beneath the raft:(a)unpiled raft;(b)2×2 piled raft;and(c)3×3 piled raft.B represents the raft width.

    Fig.18.Average contact pressure-settlement relations for corresponding points:(a)center;(b)middle side;and(c)corner.

    Fig.18 compares the raft pressures in the corresponding points of test models.In the center of the raft,the pressure-settlement curves in the test models show more adjustment.In the corner area,due to greater stiffness of the corner piles,the raft pressure is small initiallyand then increases after pile failure.Magnitude of the pressure decreases with increasing number of piles.

    4.4.Discussion

    Table 1 summarizes the measured pile bearing capacities in the models.In this table,Puand Paare the ultimate and allowable loads of the piles,respectively;SPuand SPaare the corresponding settlements of the piles at the ultimate and allowable loads,respectively.The pile ultimate load is indicated by the intersection of tangent lines drawn through the initial, flatter portion of the total settlement curve and the steeper portion of the same curve(Tomlinson,2004).The factor of safety in calculating allowable load is consideredas 3.Fordesign of the pile group,the effectof pile arrangement on its bearing capacity is usually not considered.

    Table 1 Pile load and settlement in the test models.

    In Table 1,Pa(cal)is the calculated allowable load used in the usual design calculations,and it is assumed equal to the measured allowable load of single pile.Pa/Pa(cal)is the ratio of the measured to calculated allowable loads in each test.This ratio represents the amount of deviation occurred in the design process.The ratio is calculated as 2.64 for central pile in the 3×3 piled raft.It means that the measured bearing capacity of the central pile is greater than two times of the corresponding value used in design calculation.The ratio is also significant in the central and middle side piles in the free-standing group.Generally,for all piles in the freestanding groups and piled raft foundations,the measured bearing capacity is greater than the calculated one,due to the effects of pile installation and stress interaction among adjacent piles and raft.In the free-standing group,only the first factor works.In addition,the stress interactions are little for the single pile in a group and for the corner piles in free-standing group or piled raft.These piles reach their ultimate loads with a settlement of about 20%of their diameters.For the central piles in piled raft and free-standing pile group due to the above-mentioned stress interactions,the corresponding settlement at ultimate load increases.The settlement in the piled raft is also greater than that of free-standing pile due to the raft pressure effect.For the central pile in the 3×3 piled raft,the corresponding settlement at ultimate load increases signi ficantly and reaches about 64%of the pile diameter.Corresponding settlement at allowable load is less than 2%of pile diameter for the single pile and about 14%of pile diameter for the central pile in the 3×3 piled raft.

    In Fig.19,the load-settlement curve of the piled rafts is compared with that of unpiled raft.By increasing the number of piles,the settlement of the foundation decreases significantly.At the beginning of the loading,due to higher stiffness of the piles than the soil,the slope of load-settlement curves for the piled raft is greater.The piled raft with 9 piles has a steeper initial slope in the loading curve.After pile failure,the loading curve reduces and becomes parallel to that of unpiled raft.

    Fig.19.Average load-settlement relations of unpiled raft,2×2 and 3×3 piled rafts.

    In Fig.20,the variation of measured total load(pile load plus raft load)with settlement of piled raft is compared to those of freestanding group and unpiled raft.At the initial steps of loading,the curveof the 2×2 free-standing groupcoincides with thatof the corresponding piled raft.With elevated pressure beneath the raft,the curves move far away from each other.Because of the low raft pressure in the 3×3 piled raft,adjustment of the load-settlement curve of the free-standing group is significant.In Fig.21,loads of piles within piled raft measured by load cells(without considering the raft load)are determined and compared with that of freestanding group.Since the load cells are not installed on all piles,in this context,it is assumed that the bearing behaviors of the piles in corresponding place are identical.In the 2×2 piled raft,due to the minor effect of the raft pressure on corner piles,adjustment of initial part of the curve is marked.In the 3×3 piled raft,due to the raft pressure imposed on the central and middle side piles,the pile stiffness will be smaller than those of corresponding piles in the free-standing group.After pile failure due to increasing raft pressure,the pile bearing capacity increases in piled raft and the curves move far away from each other.

    The variations of BPI ratio in the test models with the number of piles are shown in Figs.22 and 23.This ratio decreases with the increasing settlement and reaches a constant value after pile failure(Fig.24).In the piled raft,the BPI value increases with the increasing number of piles(Fig.22).In the 2×2 free-standing group,BPI reduces to less than one with the increasing settlement to more than about 3%of raft width(Fig.24).

    Fig.20.Average load-settlement relations of unpiled raft,piled raft and free-standing group.

    Fig.21.Variations of pile loads with the ratio of maximum settlement to raft width in piled raft and free-standing group.

    Fig.22.Variations of bearing improvement ratio(BPI)with the number of piles beneath the raft.

    Fig.23.Variations of BPI with the number of piles in free-standing group.

    Fig.24.Variations of BPI with the ratio of maximum settlement to raft width.

    The ultimate and allowable loads(Quand Qa)of the models and the corresponding settlement to raft width ratios(Su/B and Sa/B)are listed in Table 2.By increasing the number of piles beneath the raft,the allowable bearing capacity increases and the corresponding settlement at allowable load reduces.

    Fig.25 illustrates the load-sharing within the piled raft.The pile load-sharing within the piled raft is extrapolated from the load measured by the load cell installed on the planned pile head.In 2×2 piled raft,the pile load is measured in two corner piles and the total load of all piles is extrapolated from multiplication of the average of the two loads by four.In 3×3 piled raft,the pile load is measured in corner,middle side and central piles and the total load of all piles is extrapolated from sum of multiplication of corner and middle side pile loads by four and central pile by one.Knowing pile-sharing load,the raft-sharing load is determined by subtracting the pile load from the measured total load.In the 2×2 piled raft,at the initial stage of loading,the load-sharing ratio of the piles is larger.After failure of the piles,this distributionwill be reversed.In the 3×3 piled raft,the piles always tolerate more load than the raft.The load-sharing ratio of each bearing component is shown in Fig.26.In the 2×2 piled raft,the pile load-sharing ratio reaches from 47%to 72%,and to 39%after failure of the piles.In the 3×3 piled raft,the pile load-sharing ratio reaches from 67%to 97%,and to 80%at the ultimate load.Therefore,the raft load-sharing ratio varies between 9%and 67%depending on the model properties.

    Table 2 Measured allowable and ultimate loads of models and corresponding settlement.

    Fig.25.Load-settlement behaviors of the piles and raft:(a)2×2 piled raft;and(b)3×3 piled raft.

    It has been stated that the ultimate load of the piles increases when the piles are installed beneath a raft.On the other hand,by doing this,the raft load is reduced(Fig.27).These results are also listed in Tables 3 and 4,in which the load-sharing ratios of the piles and raft at the ultimate and allowable loads are illustrated.Since the increasing pile load and decreasing raft load mentioned above are not considered in design calculations,the values in the two last columns of Tables 3 and 4 demonstrate the deviations existing in design of piled raft components.As it can be seen,at the allowable load level,the amount of the deviation is larger.In the 3×3 piled raft,the allowable bearing capacity of the raft is in fact about 25%of the allowable load for the unpiled raft.On the other hand,in this model,the pile bearing capacity is approximately 1.91 times greater than the value considered in the conventional design process.

    Fig.26.Load-sharing ratios for raft and piles:(a)2×2 piled raft;and(b)3×3 piled raft.

    Fig.27.Bearing behaviors of unpiled and piled rafts.

    Table 3 Load-sharing of piles and raft at the ultimate load level.

    Table 4 Load-sharing of piles and raft at the allowable load level.

    The amount of the deviation existing in calculating allowable bearing capacity of the piled raft is shown in Table 5.The results are also presented for the free-standing pile group.The allowable bearing capacity of the piles is calculated in two ways,i.e.allowable bearing capacity of the piles without considering the raft bearing capacity,Qa(tra)(conventional approach in the design of piled rafts)and allowable bearing capacity of the piles by considering the raft bearing capacity,Qa(new)(new method).The stress interaction effects on decreasing the raft bearing capacity and increasing the pile bearing capacity are ignored.Based on Table 5,the calculated allowable bearing capacity of the piled raft models by considering the raft load-sharing is in consistent with the measured value.In other words,decreasing the bearing capacity of the raft and increasing the ultimate load of the piles neutralize the effect of each other.Based on the conventional approach without considering the raft load-sharing,the allowablebearing capacities are underestimated by greater than 300%and 200%for the 2×2 and 3×3 piled rafts,respectively.By increasing the pile spacing beneath the raft,the use of the conventional approach becomes more uneconomic.

    Table 5 Comparison of measured and calculated bearing capacities of models.

    Table 6 Pile loads at the ultimate and allowable loads of piled raft.

    Fig.28.Arrangements of five dial gages in lateral(a-a)and diagonal(b-b)sections.

    Table 6 lists the pile loads at the allowable and ultimate loads of the piled raft.At the allowable load of the 2×2 piled raft,the pile load exceeds their allowable load and reaches 77%of their ultimate load.In the case of the 3×3 piled raft,the corner,middle side and central piles reach 62%,34%and 22%of the pile ultimate load,respectively.Among these,only the middle side pile provides the factor of safety used in the conventional design calculations.The central pile is farawayfromits ultimate load.Atthe ultimate load of the piled raft,all the piles yield and their loads exceed the failure loads,which is due to the raft pressure increase after pile failure.The percentages of the pile load beyond the failure load for the corner,middle side and central piles are 20%,15%and 2%,respectively.In the central pile due to the increase in stress interaction,the pile failure approximately occurs at the ultimate load of the piled raft.

    Table 7 lists the calculated loads of the piles and raft when Qa(tra)and Qa(new)are applied in the piled raft models.The ultimate load of the raft(Ru)considers the measured load of the raft when the maximum settlement equals 10%of the raft width.Therefore,the reduction of the bearing capacity due to the stress interaction is also considered.Based onTable 7,if the raft pressure is ignored and the foundation is designed as a free-standing group,the actual factors of safety for the piles and raft become significantly high.With increasing number of piles and decreasing raft bearing capacity,the factor of safety for the raft decreases.The total factors of safety for the 2×2 and 3×3 piled rafts are calculated as 10.85 and 6.54,respectively,with the conventional method,verifying that the design method is very uneconomic.By considering the raft pressure,the factors of safety for the piles and raft both decrease.As for the corner piles in the 2×2 and 3×3 piled rafts,the pile loads exceed their allowable loads,and the factor of safety becomes 1.36 and 1.67,respectively.In contrast,the raft still has a factor of safety greater than 3.These two opposite effects cause the total factors of safety to reach about 3 inboth models.Therefore,considering the raft load-sharing leads to an economic result.

    Table 7 Comparison of measured and calculated load capacities of piled raft.

    In Figs.28 and 29,locations of five dial gages and the distributions of the settlements on the top of the foundation cap in the lateral(a-a)and diagonal(b-b)sections are demonstrated,respectively.Table 8 represents the corner(or middle side)to center de flection ratio(δ/L)and slope of the test models(ζ)in diagonal and lateral sections at the allowable and ultimate load levels,whereδis the differential settlement between the center and corner(in diagonal section)or middle side(in lateral section)of the raft,and L is the distance between the two points.The subscripts ‘lat’and ‘dia’denote the lateral and diagonal sections,respectively.Generally,the free-standing pile groups at their ultimate and allowable loads tilt less than the corresponding piled rafts.The slopes of the raft models at their ultimate loads are greater than those at the allowable loads,but the differential settlements do not change significantly.

    Fig.29.Raft settlements along sections a-a and b-b:(a,b)FG-4;(c,d)FG-9;(e,f)unpiled raft;(g,h)PR-4;and(i,j)PR-9.

    Table 8 The estimated tilts and differential settlements in the models at allowable and ultimate loads.

    Table 9 The estimated tilts and differential settlements in the models at allowable load of unpiled raft.

    In the 2×2 piled raft,since the piles are located at the corners,the model becomes bowl-shaped and the differential settlement is greater than those in other models.In the 3×3 piled raft,the differential settlement is less than those in other models.Since the external loading area is greater than the central pile area and because of the high bearing capacity of the central pile,the raft becomes dome-shaped.The tilt of the unpiled raft at the allowable load level is greater than those in other models.By increasing the number of piles beneath the raft,the amount of the tilt decreases significantly.Table 9 shows the maximum settlement to raft width ratio(Δmax/B),raft slope(ζ)and the de flection ratio(δ/L)at a constant allowable load of the unpiled raft.Due to the raft pressure in the piled raft models,the foundation stiffness decreases and the deformation of the free-standing pile group becomes less at the same load level.According toTable 9,the unpiled raft shows greater deformation.By increasing the numberof piles beneath the raft,the settlement and tilt decrease significantly.

    5.Conclusions

    A series of loading tests is conducted on single pile,single pile in pile group,unpiled raft,piled raft and free-standing group in sand,and the test results are compared.The precision of available analytical methods in design of piled rafts is investigated.The raft and pile models are made of cast-in-place concrete.Based on the results of the model tests,the following conclusions are drawn:

    (1)By installing a single pile in a group,the bearing capacity and stiffness of the pile are increased due to the adjacent pile confinement and increased soil density during pile installation.The increases in bearing capacities of the central,middle side and corner single piles located in the 3×3 group(s/d=2.6)are measured to be 57%,36%and 11%,respectively.Thisvalueforthesinglepileslocatedinthecornerof the 2×2 group(s/d=5.2)is about 5%.In the piled raft foundation after thepilefailure,owing totheincreasedraftpressure,thestress around the piles is increased and the negative friction occurs,thus the bearing capacity of the piles in the piled raft is greater than that of the free-standing group for the corresponding piles,but the stiffness is lower.The bearing capacity of the central pile in the 3×3 piled raft(s/d=2.6)is 2.64 times greater than the single pile capacity.On the other hand,by installation of piles beneath the raft,the bearing capacities of the raft with s/d of 5.2 and 2.6 are reduced by 25%and 43%,respectively.These increases of pile capacity and decrease of raft capacity due to pile interaction and raft pressure have been ignored in available design calculations.

    (2)By increasing the number of piles,the settlement of the piled raft decreases significantly.At the initial steps of the loading test,the pile bearing contribution is greater than that of the raft,thus the slope of the load-settlement curve is steeper.After pile failure,the curve is nearly parallel to the loadsettlement curve of the unpiled raft.

    (3)At the allowable load of piled rafts with s/d of 2.6 and 5.2,the pile load-sharing from the total external load is equal to about 87%and 71%,respectively.

    (4)By designing a piled raft based on conventional approach in which the raft load-sharing is not considered,the allowable bearing capacity of the piled raft is underestimated by more than 300%and 200%for s/d of 5.2 and 2.6,respectively.On the other hand,with decreasing number of piles and increasing pile spacing,the conventional method is uneconomic.In contrast,when the raft bearing contribution is considered in the design calculations and the effect of the pile installation on the bearing capacities of the piles and raft is ignored,the difference between the calculated and measured results is insignificant.

    (5)At the allowable load level for the piled raft,the pile loads exceed their allowable loads and reach 77%of their ultimate loads for s/d=5.2.In the piled raft with s/d=2.6,the loads of the corner,middle side and central piles reach 62%,34%and 22%of the ultimate loads of the piles,respectively.

    (6)In the 2×2 piled raft,due to installation of the piles in the

    corners of the raft,the raft becomes bowl-shaped after loading,and its differential settlement increases.At the constant allowable load of the unpiled raft,the tilt and settlement are greater than those in other models studied.With increasing the number of piles beneath the raft,the settlement and tilt decrease significantly.

    Conflict of interest

    We wish to confirm that there are no known conflicts of interest associated with this publication and there has been no significant financial support for this work that could have in fluenced its outcome.

    Notation

    B Raft width

    BPI Bearing pressure improvement ratio

    d Pile diameter

    FSPileFactor of safety for the pile

    FSRaftFactor of safety for the raft

    FSPiledraftFactor of safety for the piled raft

    L Corner(middle side)to center distance

    P Pile load

    PaMeasured allowable load of pile

    PuMeasured ultimate load of pile

    Pa(cal)Calculated allowable load of pile

    Pus(sum)Summation of equivalent single pile loads

    QaAllowable load of test model

    QuUltimate load of test model

    Qa(new)Calculated allowable load of piled raft by the new approach

    Qa(tra)Calculated allowable load of piled raft bythe conventional approach

    rPPile load-sharing ratio

    rRRaft load-sharing ratio

    RuMeasured ultimate load of raft

    Ru(ur)Measured ultimate load of unpiled raft

    SPaSettlement of pile at its allowable load

    SPuSettlement of pile at its ultimate load

    SaSettlement of test model at its ultimate load

    SuSettlement of test model at its allowable load

    s/d Pile spacing to diameter ratio

    ΔmaxMaximum settlement of test model

    δ Differential settlement of test model

    δ/LlatLateral(middle side to center)de flection ratio

    δ/LdiaDiagonal(corner to center)de flection ratio

    ζlatLateral slope(tilt)of test models

    ζdiaDiagonal slope(tilt)of test models

    亚洲av.av天堂| av免费在线看不卡| 亚洲精品一区av在线观看| 欧美又色又爽又黄视频| 婷婷色综合大香蕉| 波多野结衣高清作品| 精品久久国产蜜桃| 国产精品久久视频播放| 99热6这里只有精品| 久久久国产成人精品二区| 蜜桃久久精品国产亚洲av| 可以在线观看毛片的网站| 国产伦一二天堂av在线观看| 高清午夜精品一区二区三区 | 成人综合一区亚洲| 亚洲欧美日韩东京热| 日本成人三级电影网站| 国产 一区精品| 亚洲av美国av| 男女视频在线观看网站免费| 老司机午夜福利在线观看视频| 成人综合一区亚洲| 小说图片视频综合网站| 亚洲av美国av| 插阴视频在线观看视频| 最近最新中文字幕大全电影3| 色5月婷婷丁香| 国产极品精品免费视频能看的| 99热网站在线观看| 欧美激情在线99| 精品人妻熟女av久视频| 国产亚洲精品av在线| 国产老妇女一区| 亚洲av二区三区四区| 3wmmmm亚洲av在线观看| 观看美女的网站| 精品无人区乱码1区二区| 久久精品国产鲁丝片午夜精品| 国产精品久久久久久久久免| 成人综合一区亚洲| 欧美激情久久久久久爽电影| 熟女电影av网| 免费av不卡在线播放| 精品国内亚洲2022精品成人| 亚洲内射少妇av| 少妇人妻一区二区三区视频| 日韩欧美精品v在线| 国产午夜精品久久久久久一区二区三区 | 麻豆久久精品国产亚洲av| 成人亚洲欧美一区二区av| 久久久久国产精品人妻aⅴ院| 免费av观看视频| 97超级碰碰碰精品色视频在线观看| 精品一区二区三区视频在线| 久久午夜福利片| 一夜夜www| 中文字幕熟女人妻在线| 偷拍熟女少妇极品色| 天美传媒精品一区二区| 性色avwww在线观看| 久久九九热精品免费| 一夜夜www| 国产成人aa在线观看| 99久久成人亚洲精品观看| 一区二区三区四区激情视频 | 国产淫片久久久久久久久| 日韩 亚洲 欧美在线| 特大巨黑吊av在线直播| 久久久欧美国产精品| 国产成人一区二区在线| 欧美又色又爽又黄视频| 亚洲av美国av| 看非洲黑人一级黄片| 亚洲aⅴ乱码一区二区在线播放| 午夜福利在线观看吧| 亚洲av熟女| 成人鲁丝片一二三区免费| 亚洲丝袜综合中文字幕| 看非洲黑人一级黄片| 色综合亚洲欧美另类图片| 九九热线精品视视频播放| 麻豆国产av国片精品| 国产精品永久免费网站| 精品少妇黑人巨大在线播放 | 变态另类成人亚洲欧美熟女| 精品人妻视频免费看| 长腿黑丝高跟| 亚洲欧美中文字幕日韩二区| 午夜久久久久精精品| 日本熟妇午夜| 97人妻精品一区二区三区麻豆| 国产一区二区在线av高清观看| 美女内射精品一级片tv| 亚洲av中文字字幕乱码综合| 国产白丝娇喘喷水9色精品| 波多野结衣高清无吗| 九色成人免费人妻av| 中国美女看黄片| 91精品国产九色| 国产精品人妻久久久久久| 最近中文字幕高清免费大全6| 国产真实乱freesex| 级片在线观看| 亚洲av二区三区四区| 亚洲精品日韩av片在线观看| 日韩成人av中文字幕在线观看 | 日本熟妇午夜| 精品久久久久久久久亚洲| 国产一区二区激情短视频| 一边摸一边抽搐一进一小说| 乱码一卡2卡4卡精品| 婷婷亚洲欧美| 国产精品av视频在线免费观看| av在线天堂中文字幕| 国产成人aa在线观看| 精品久久久噜噜| 欧美最新免费一区二区三区| 国产蜜桃级精品一区二区三区| av在线播放精品| 97超级碰碰碰精品色视频在线观看| 精品少妇黑人巨大在线播放 | 日本熟妇午夜| 亚洲精品一区av在线观看| 亚洲无线在线观看| 插阴视频在线观看视频| 久久亚洲国产成人精品v| 国产三级中文精品| 国产精品爽爽va在线观看网站| 久久99热6这里只有精品| 午夜免费男女啪啪视频观看 | 中文字幕精品亚洲无线码一区| 成人美女网站在线观看视频| 免费在线观看影片大全网站| 国国产精品蜜臀av免费| 六月丁香七月| 简卡轻食公司| 别揉我奶头~嗯~啊~动态视频| 国产高清不卡午夜福利| 身体一侧抽搐| 国产精品99久久久久久久久| 人妻夜夜爽99麻豆av| av在线观看视频网站免费| 国产成人91sexporn| 国产男人的电影天堂91| 免费看美女性在线毛片视频| 亚洲五月天丁香| 99riav亚洲国产免费| 亚洲高清免费不卡视频| 别揉我奶头~嗯~啊~动态视频| 午夜激情福利司机影院| 久久久久精品国产欧美久久久| 精品久久久久久成人av| 亚洲欧美精品综合久久99| 精品久久久久久久久久久久久| 99久国产av精品| 亚洲国产精品久久男人天堂| 精品99又大又爽又粗少妇毛片| 国产精品永久免费网站| 淫妇啪啪啪对白视频| 欧美丝袜亚洲另类| 亚洲国产精品合色在线| 搞女人的毛片| 欧美性猛交黑人性爽| 成人性生交大片免费视频hd| 国产伦精品一区二区三区四那| 婷婷亚洲欧美| 黑人高潮一二区| 亚洲va在线va天堂va国产| 亚洲国产精品国产精品| 欧美日韩综合久久久久久| 99久久中文字幕三级久久日本| 嫩草影院入口| 久久人人爽人人片av| 国产在线精品亚洲第一网站| 五月伊人婷婷丁香| 亚洲av一区综合| 老司机福利观看| 成年版毛片免费区| 男女下面进入的视频免费午夜| 男人和女人高潮做爰伦理| 亚洲在线自拍视频| 亚洲真实伦在线观看| 亚洲精品国产成人久久av| 精品99又大又爽又粗少妇毛片| 国产精品乱码一区二三区的特点| 人妻夜夜爽99麻豆av| 99久久精品热视频| 亚洲精品国产成人久久av| 观看美女的网站| 国产精华一区二区三区| 中文字幕精品亚洲无线码一区| 亚洲av电影不卡..在线观看| 美女被艹到高潮喷水动态| 久久亚洲国产成人精品v| av天堂中文字幕网| 大型黄色视频在线免费观看| 亚洲成人中文字幕在线播放| 免费不卡的大黄色大毛片视频在线观看 | 桃色一区二区三区在线观看| 99热这里只有是精品50| 欧美潮喷喷水| 两性午夜刺激爽爽歪歪视频在线观看| 大香蕉久久网| 日韩国内少妇激情av| 国产精品久久久久久久电影| 亚洲中文日韩欧美视频| 人妻制服诱惑在线中文字幕| 国产女主播在线喷水免费视频网站 | 在线播放国产精品三级| 亚洲av不卡在线观看| 国产又黄又爽又无遮挡在线| 免费av观看视频| 精品少妇黑人巨大在线播放 | 少妇人妻一区二区三区视频| 黄片wwwwww| av免费在线看不卡| 成年女人永久免费观看视频| 色综合站精品国产| 深爱激情五月婷婷| 亚洲国产色片| 99久久成人亚洲精品观看| 欧美激情国产日韩精品一区| 国产精品乱码一区二三区的特点| 国产精品综合久久久久久久免费| 亚洲欧美成人综合另类久久久 | videossex国产| 国产美女午夜福利| 国产精品伦人一区二区| 淫妇啪啪啪对白视频| 大香蕉久久网| 男人舔奶头视频| 亚洲综合色惰| av在线天堂中文字幕| 久久久久九九精品影院| 女人被狂操c到高潮| 99热精品在线国产| 99精品在免费线老司机午夜| av福利片在线观看| 日韩制服骚丝袜av| 女人十人毛片免费观看3o分钟| 99久国产av精品| 老熟妇乱子伦视频在线观看| 长腿黑丝高跟| 秋霞在线观看毛片| 日韩,欧美,国产一区二区三区 | 精品国内亚洲2022精品成人| 日日啪夜夜撸| 久久天躁狠狠躁夜夜2o2o| 久久人妻av系列| 成人亚洲欧美一区二区av| 哪里可以看免费的av片| 久久人人爽人人片av| 黄色一级大片看看| 我的女老师完整版在线观看| 国产人妻一区二区三区在| 久久久欧美国产精品| 亚洲精品成人久久久久久| 99riav亚洲国产免费| 一级毛片aaaaaa免费看小| 一进一出抽搐gif免费好疼| 99久久中文字幕三级久久日本| 国产美女午夜福利| 在线观看66精品国产| 国产精品一区二区三区四区久久| 成人鲁丝片一二三区免费| 人人妻人人澡人人爽人人夜夜 | 九九热线精品视视频播放| 美女 人体艺术 gogo| 熟女电影av网| 午夜亚洲福利在线播放| 国产成人a区在线观看| 亚洲av中文av极速乱| 嫩草影院新地址| 老师上课跳d突然被开到最大视频| 午夜福利在线观看免费完整高清在 | 伦精品一区二区三区| 一区福利在线观看| 久久午夜亚洲精品久久| 欧美人与善性xxx| 长腿黑丝高跟| 欧美成人精品欧美一级黄| 国产精品亚洲一级av第二区| 亚洲婷婷狠狠爱综合网| 一级av片app| 国产高清不卡午夜福利| 国产精品久久久久久亚洲av鲁大| 亚洲第一区二区三区不卡| 日韩欧美精品v在线| 午夜亚洲福利在线播放| 成熟少妇高潮喷水视频| 日日摸夜夜添夜夜添av毛片| 男女啪啪激烈高潮av片| 淫秽高清视频在线观看| 成人二区视频| 成年版毛片免费区| 一进一出好大好爽视频| 亚洲av免费高清在线观看| 人妻少妇偷人精品九色| 国产亚洲精品综合一区在线观看| 寂寞人妻少妇视频99o| 国产精品国产三级国产av玫瑰| 午夜福利视频1000在线观看| 欧美一级a爱片免费观看看| 欧美最新免费一区二区三区| 村上凉子中文字幕在线| 国产真实伦视频高清在线观看| 可以在线观看毛片的网站| 国产精品一区二区三区四区免费观看 | 午夜福利成人在线免费观看| 特级一级黄色大片| 久久精品91蜜桃| 美女黄网站色视频| 欧美在线一区亚洲| 欧美成人精品欧美一级黄| 国产激情偷乱视频一区二区| 国产精品一区二区性色av| av免费在线看不卡| 99久久无色码亚洲精品果冻| 欧美日韩综合久久久久久| 九色成人免费人妻av| 人妻久久中文字幕网| 国产女主播在线喷水免费视频网站 | 一个人看的www免费观看视频| 神马国产精品三级电影在线观看| 亚洲欧美清纯卡通| 亚洲av五月六月丁香网| АⅤ资源中文在线天堂| 乱码一卡2卡4卡精品| 97人妻精品一区二区三区麻豆| 在现免费观看毛片| 久久鲁丝午夜福利片| 噜噜噜噜噜久久久久久91| 亚洲国产精品久久男人天堂| 午夜福利18| 亚洲欧美清纯卡通| 免费看光身美女| 免费观看人在逋| 欧美潮喷喷水| 日韩欧美三级三区| 内地一区二区视频在线| 午夜福利高清视频| 一本一本综合久久| 亚洲色图av天堂| 欧美性猛交黑人性爽| 成人一区二区视频在线观看| 五月伊人婷婷丁香| a级毛色黄片| 全区人妻精品视频| 久久午夜亚洲精品久久| 色综合色国产| 成人漫画全彩无遮挡| 男女那种视频在线观看| 久久亚洲精品不卡| 极品教师在线视频| 97碰自拍视频| 麻豆国产av国片精品| 日韩精品中文字幕看吧| 国产高清有码在线观看视频| 人人妻人人看人人澡| 亚洲av.av天堂| 麻豆精品久久久久久蜜桃| 久久久午夜欧美精品| 最近手机中文字幕大全| 亚洲欧美日韩东京热| 久久久久久久午夜电影| 特大巨黑吊av在线直播| 久久久午夜欧美精品| 18禁裸乳无遮挡免费网站照片| 国产成人a区在线观看| 黄片wwwwww| 99热全是精品| 12—13女人毛片做爰片一| 久久午夜福利片| 国产午夜精品论理片| 少妇的逼好多水| 又爽又黄a免费视频| 美女大奶头视频| 老司机影院成人| 日韩,欧美,国产一区二区三区 | 99热这里只有是精品50| 久久精品久久久久久噜噜老黄 | 99热网站在线观看| 99热这里只有是精品在线观看| 寂寞人妻少妇视频99o| 免费搜索国产男女视频| 搞女人的毛片| 久久久精品欧美日韩精品| 尾随美女入室| 国产高清有码在线观看视频| 免费av不卡在线播放| videossex国产| 国产亚洲精品久久久久久毛片| 成人无遮挡网站| av福利片在线观看| 久久九九热精品免费| 悠悠久久av| 最近2019中文字幕mv第一页| 欧美日韩在线观看h| 欧美丝袜亚洲另类| 欧美日本亚洲视频在线播放| 午夜福利成人在线免费观看| 日日撸夜夜添| 青春草视频在线免费观看| 九色成人免费人妻av| 亚洲av电影不卡..在线观看| 97碰自拍视频| 简卡轻食公司| 成人特级黄色片久久久久久久| 色播亚洲综合网| 尾随美女入室| 精品久久国产蜜桃| 丝袜喷水一区| 国内揄拍国产精品人妻在线| 色视频www国产| 91久久精品电影网| 亚洲婷婷狠狠爱综合网| 三级经典国产精品| 69av精品久久久久久| 国产伦在线观看视频一区| 国产一区二区亚洲精品在线观看| 淫妇啪啪啪对白视频| 一进一出好大好爽视频| 欧美另类亚洲清纯唯美| 午夜影院日韩av| 国产精品美女特级片免费视频播放器| 我的老师免费观看完整版| 亚洲高清免费不卡视频| 成人精品一区二区免费| 黑人高潮一二区| 亚洲人成网站在线播| 亚洲乱码一区二区免费版| 国产真实乱freesex| 精品熟女少妇av免费看| 一边摸一边抽搐一进一小说| 在线a可以看的网站| 日韩av在线大香蕉| 国产乱人偷精品视频| 搡老岳熟女国产| 免费观看的影片在线观看| 亚洲成人av在线免费| 少妇猛男粗大的猛烈进出视频 | 亚洲欧美中文字幕日韩二区| 看免费成人av毛片| 国产一区二区三区在线臀色熟女| 看黄色毛片网站| 男女做爰动态图高潮gif福利片| 夜夜爽天天搞| 黄色日韩在线| 国产国拍精品亚洲av在线观看| 国产在视频线在精品| 搡女人真爽免费视频火全软件 | 午夜久久久久精精品| 精品国产三级普通话版| 国产探花极品一区二区| 久久这里只有精品中国| 日本三级黄在线观看| 日本黄大片高清| 老司机影院成人| 国产一级毛片七仙女欲春2| 高清毛片免费观看视频网站| 小说图片视频综合网站| 成人漫画全彩无遮挡| 免费人成在线观看视频色| 久久人人爽人人爽人人片va| 亚洲三级黄色毛片| 亚洲国产欧洲综合997久久,| 精品久久久噜噜| 99热只有精品国产| 亚洲人成网站高清观看| 99热只有精品国产| 免费av观看视频| 黄色视频,在线免费观看| 久久鲁丝午夜福利片| 狠狠狠狠99中文字幕| 欧美+日韩+精品| 一级毛片久久久久久久久女| 日韩成人伦理影院| 亚洲高清免费不卡视频| 国产视频一区二区在线看| 能在线免费看毛片的网站| 精品国产一区二区三区久久久樱花| 亚洲高清免费不卡视频| 美女脱内裤让男人舔精品视频| 精品卡一卡二卡四卡免费| 久久99一区二区三区| 欧美日韩av久久| 成人毛片a级毛片在线播放| 2021少妇久久久久久久久久久| 成人亚洲欧美一区二区av| 男男h啪啪无遮挡| 亚洲中文av在线| 嫩草影院入口| 国产高清不卡午夜福利| 日韩免费高清中文字幕av| 精品国产露脸久久av麻豆| av卡一久久| 精品国产一区二区三区久久久樱花| 亚洲va在线va天堂va国产| 欧美三级亚洲精品| 亚洲av免费高清在线观看| 国产成人精品无人区| 人妻少妇偷人精品九色| 亚洲精品自拍成人| 国产视频内射| 91aial.com中文字幕在线观看| 香蕉精品网在线| av福利片在线| av线在线观看网站| 亚洲国产av新网站| 99热全是精品| 高清午夜精品一区二区三区| 男人和女人高潮做爰伦理| 三级国产精品欧美在线观看| 久久精品久久久久久久性| 69精品国产乱码久久久| 欧美成人午夜免费资源| 日日撸夜夜添| 日韩精品免费视频一区二区三区 | 一级黄片播放器| 国产精品一区二区性色av| 另类精品久久| 3wmmmm亚洲av在线观看| 内地一区二区视频在线| 亚洲一级一片aⅴ在线观看| 欧美97在线视频| 丰满乱子伦码专区| 一区二区av电影网| 国产免费又黄又爽又色| 夫妻午夜视频| 国产成人一区二区在线| 一二三四中文在线观看免费高清| 女人久久www免费人成看片| 久久97久久精品| 国产免费一级a男人的天堂| 最近的中文字幕免费完整| 深夜a级毛片| 看免费成人av毛片| 少妇被粗大猛烈的视频| 在线亚洲精品国产二区图片欧美 | 日产精品乱码卡一卡2卡三| 国产无遮挡羞羞视频在线观看| 国产成人精品无人区| 久久久久国产精品人妻一区二区| 中文欧美无线码| 亚洲人成网站在线播| 菩萨蛮人人尽说江南好唐韦庄| 99热全是精品| 色婷婷av一区二区三区视频| 少妇被粗大的猛进出69影院 | 中文精品一卡2卡3卡4更新| 人妻一区二区av| 天堂8中文在线网| 国产成人精品久久久久久| 妹子高潮喷水视频| 亚洲av福利一区| 久久久久国产网址| 久久久久精品性色| 日韩伦理黄色片| 午夜免费观看性视频| 少妇猛男粗大的猛烈进出视频| 天天躁夜夜躁狠狠久久av| 91精品国产九色| 免费久久久久久久精品成人欧美视频 | 日本猛色少妇xxxxx猛交久久| 国产成人freesex在线| 在线 av 中文字幕| 欧美日韩在线观看h| 欧美97在线视频| 在线观看免费高清a一片| 亚洲激情五月婷婷啪啪| 中文在线观看免费www的网站| 9色porny在线观看| 在线看a的网站| 免费黄网站久久成人精品| 成人特级av手机在线观看| 色网站视频免费| 国产视频内射| 中文精品一卡2卡3卡4更新| 国产精品.久久久| 麻豆乱淫一区二区| 色婷婷av一区二区三区视频| 欧美老熟妇乱子伦牲交| 日本欧美国产在线视频| 久久精品久久久久久噜噜老黄| 少妇精品久久久久久久| 国国产精品蜜臀av免费| 麻豆成人av视频| 各种免费的搞黄视频| 人人澡人人妻人| 少妇被粗大的猛进出69影院 | 婷婷色综合www| 美女大奶头黄色视频| 在线观看www视频免费| 少妇被粗大猛烈的视频| 涩涩av久久男人的天堂| 一边亲一边摸免费视频| 国产成人午夜福利电影在线观看| av在线播放精品| 色网站视频免费| 简卡轻食公司| 亚洲美女黄色视频免费看| 精品99又大又爽又粗少妇毛片| 国产欧美另类精品又又久久亚洲欧美| 人人妻人人看人人澡| 日日摸夜夜添夜夜爱| 大话2 男鬼变身卡| 久久精品久久久久久久性| 日本vs欧美在线观看视频 | 国产精品国产av在线观看| 国产男人的电影天堂91| 久久久精品免费免费高清| 最近中文字幕高清免费大全6| 精品国产一区二区三区久久久樱花| 国内精品宾馆在线| av在线观看视频网站免费|